An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Catron County/Reserve E-911 System Upgrade Presentation to the Project Certification Committee

  2. Project History • On December 3, 2012, the Catron County/Reserve, NM Sheriff’s Office submitted a request to LGD to approve an upgrade to their current 911 call-taking equipment. The 911 equipment that Catron County/Reserve, NM currently has was installed in 2008 and manufacture discontinued in 2010. Availability of parts is a major issue for ongoing maintenance. • On February 19, 2013, the BOF approved the Catron County/Reserve, NM E-911 PSAP funding request for equipment upgrades in the amount of $239,263.79.

  3. Budget Status • The amount approved by the BOF includes funding for equipment and software upgrades for the Catron County/Reserve PSAP. The amount was based on the quote received from the current equipment provider. • IV&V was not budgeted for this project. The DFA/LGD plans to request approval from the Board of Finance to fund IV&V.

  4. Budget Breakout

  5. Project Timeline

  6. Risk & Issues • System failure prior to project completion • We will alert the back-up PSAP that there may be a need to divert 911 calls. • Site readiness • We require the PSAP to certify that the site is ready prior to giving authorization to move forward.

  7. 911 System Configuration

  8. Questions? Thank You