1 / 6

Southwest Pass MS River Denial of Consistency Determination

Southwest Pass MS River Denial of Consistency Determination. Keith Lovell, Administrator Office of Coastal Management Department of Natural Resources. Timeline: January 29, 2009 – OCM Issued Conditional Consistency (Conditions Refused by Corps)

rue
Download Presentation

Southwest Pass MS River Denial of Consistency Determination

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Southwest Pass MS River Denial of Consistency Determination Keith Lovell, Administrator Office of Coastal Management Department of Natural Resources

  2. Timeline: • January 29, 2009 – OCM Issued Conditional Consistency • (Conditions Refused by Corps) • February 2009 – SW Pass working group was convened. • August 2009 – Working Group issued White Paper to Corps • November 23, 2009 – OCM Denied Consistency • October 13, 2010 – Denied • October 7, 2011 - Denied • October 4, 2012 – Denied

  3. Importance of SW Pass of MS River: • OCM is wholly aware of the economic and strategic value, to the State and the Nation, of safe and unencumbered navigation of the Mississippi River. • OCM recognize that dredging Southwest Pass to maintain such a dynamic channel is a complex and challenging task. • The intent of the State is for the Corps to continue to maintain the full authorized channel dimensions so navigation and maritime commerce on the river are not compromised and that beneficial use becomes an integral part of the management of the lower river.

  4. Consistency Denial: • OCM determined that proposed disposal activity is inconsistent with the Louisiana Coastal Resources Program. • OCM’s objection lies solely with the unsound dredged material disposal practices proposed for this valuable resource. • Insufficient funding is no justification for failure to achieve full consistency with Louisiana’s Coastal Resources Program. The Corps must seek adequate funding from Congress for the maintenance activity. Per federal • consistency regulations at • 15 CFR 930.32(3)

  5. Possibly of New Beneficial Use Site: • OCM received a Public Noticed from the Corps on June 12, 2012 proposing to designate an additional disposal area for the placement of dredged material into shallow open water areas of West Bay. • OCM responded that we fully support this beneficial use concept for future maintenance dredging activities in these areas.

  6. Maintenance of Southwest Pass: • We reiterate that neither the Department of Natural Resources Office of Coastal Management nor the State of Louisiana has any wish for navigation of the River to be impeded, and we urge the NOD to forego that course of action.

More Related