190 likes | 339 Views
SPIRIT of the Koala Project VOLT Critical Design Review. Anthony Anglin , Colin Harkins, Dylan Cooper, Thomas Jefferies, Starteya Pais , Joao Mansur, Andrew Trujillo, Dustin Fishelman. Mission Overview.
E N D
SPIRIT of the KoalaProject VOLTCritical Design Review Anthony Anglin, Colin Harkins, Dylan Cooper, Thomas Jefferies, StarteyaPais, Joao Mansur, Andrew Trujillo, Dustin Fishelman
Mission Overview • Prove the feasibility of using the flow of atmosphere across the surface of the BalloonSat to generate current • Expect to discover that using magnets and the spin of the satellite will generate current • We predict variation in the levels of current that will be generated • We are conducting this mission to determine the feasibility of using wind to power experiments in future BalloonSats
Design Overview • Bearings will allow BalloonSat to rotate independently of the flight tube • Magnets attached to the flight tube will rotate within a coil of wire, generating electric current • Current and voltage generated will be measured and recorded • Fins attached to the outside of the cube will be used to increase the amount of air flow
Ordered Parts • Ordered parts include: • Neodymium magnets • Sealed, ceramic, stainless steel ball bearings • Current and voltage sensor • Order Status: • Magnets: Ordered, received • Bearings: Ordered, received • Current Sensor: Ordered, received
Schedule • September 28th – Turn in proposal (4:00 pm) • September 30th - Team Meeting • October 2nd – CoDR Presentations • October 3rd – Team Meeting • October 4th – Order all the hardware • October 5th – Authority to Proceed October 7th – Finalize design + Team meeting • October 10th – Team meeting • October 13th – Acquired all hardware • October 14th – Begin construction + Team meeting • October 17th – Team meeting • October 18th – Design Document Rev A/B (7:00 am) + pCDR Slides Due (7:00 am) • October 21st – Team meeting • October 28th – Testing Day + Team meeting • November 4th – Finalize programming + Team meeting • November 7th – Team meeting • November 13th – In-Class demo • November 14th – Team meeting • November 16th – Design Document Rev C • November 18th – Team meeting • November 25th – Finalize satellite and prep for launch • November 27th – LRR Slides Due (7:00 am) • November 28th – FINAL Team meeting • November 30th – Final Weigh-in • December 1st – Launch day • December 8th – ITLL Design Expo + Design Document Rev D Due + Extra Credit Video • December 11th – Final Presentations and Reports
Proposal Requirements • Our BalloonSatwill generate electricity, powered by the rotation of the BallonSat • Using magnets rotating through coils of wire • A GO PRO video camera will be used to image the flight • Attached inside of cube opposite of the camera • BalloonSatwill be recovered • GPS and the string will keep them all attached and able to be discovered • Flight String will attach to the BalloonSatthrough a PVC pipe • Must be tied very tightly to ensure the pipe does not spin, only the cube • Temperature will remain above -10 degrees Celsius • Through dry ice testing and multiple layers of insulation • Weight will not exceed 1125 grams • Our weight budget shows we will not exceed • A three axis accelerometer will be used to measure acceleration during the flight • Shown in our block diagram, will be attached to Arduino
Proposal Requirements 2 • Design will allow for an Arduino UNO and related components • Shown in our block diagram and drawings • External temperatures will be measured • Shown in block diagrams • Canon A570IS will be used to image the environment • Placed facing outwards, opposite side of GO Pro • An active heater system will be used to maintain interior temperature • Shown in our block diagram • A visual indicator on the exterior of the BalloonSat will allow SOK to confirm that the payload ready is for launch • Will use an LED light attached to the inside to indicate launch preparedness
Test Plan • Tests will include drop tests, cooler tests, subsystems tests, functional tests, whip tests, and mission simulation tests • Will experiment with different fin types to conclude which one will create the most drag and spin • Mission Simulation will include spinning the cube by hand, and taking it to the wind tunnel for testing • Already have done drop at DLC and some whip tests • Future tests will include dry ice cooling, and more whip tests
Test Schedule • October 7th – Drop Test • October 21st – Spin Test • October 28th – Sensor Testing (Pressure, humidity, accelerator, temperature) • November 4th – Functional Test (Generator testing) • November 11th – Subsystem Test (External and internal) • November 18th – Cooler Testing • November 25th – Mission Simulation Test
First Draft Thoughts • Expect to see spin created by the fins and the rotation on the BalloonSat • From this spin there will be evidence of current and voltage created • Will show that we can supply voltage for most of the experiment, but not entirely • Results will prove that using the rotation is a sufficient method of running an experiment
Organization Chart Name: Major: Task: • Andrew Trujillo Astrophysics Researcher • StarteyaPais Aerospace Engineering Researcher/Secretary • Joao Mansur Aerospace Engineering Researcher/ Solderer • Thomas Jeffries Aerospace Engineering Team Leader/Budget Manager • Colin Harkins Open Option Engineering Secretary/Structural Design • Dustin Fishelman Aerospace Engineering Coordinator/Structural Design • Dylan Cooper Aerospace Engineering Lead Programmer • Anthony Anglin Aerospace Engineering Coordinator/Researcher
Biggest Worries • Will not generate current • Magnets will not properly rotate through coils • Not enough spin during flight • Fins will break off