An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Outage(Steam & Electrical) Commencing March 21, 2009

  2. March 21st Utility Outage • Why are we doing this? • What utilities will be shut off? • How soon we will have them back on line? • What maintenance is being completed? • Who will be affected?

  3. Why Are We Doing This? • Mechanical Systems deteriorate • This is a systematic plan to: • Repair known problems • Extend the life of our equipment • To allow for major infrastructure improvements: • Siceluff Hall – Renovation • Electrical Spine – Freudenberger Hall Switches • Scheduled for March 21st • Weekend before Spring Break • Heads Up: • One more Electrical Outage - May 2009

  4. Utilities Affected: • STEAM • Hot water • Kitchens • Humidity Control (Library) • ELECTRICITY • DOMESTIC WATER • No booster Pumps (above 5th floor) • No hot water heaters • CHILLED WATER FOR A/C

  5. Steam System Shut Off: Saturday March 21st at 1:00 am • Scope: • Supports the Electrical Outage • Steam Distribution System Repairs • Condensate System Repairs • This is water returned to the boiler Turn On: Saturday March 21st -2 hours after Electrical Power is restored.

  6. Buildings Affected by Steam Outage: • Art Annex • Blair - Shannon House • Carrington Hall • Cheek Hall • Craig Hall • Ellis Hall • Greenwood Lab School • Freudenberger House • Hill Hall • Karls Hall • Kemper Hall • McDonald Arena • Morris Hall (Taylor Health and Wellness Center & Bookstore) • Plaster Sports Complex • Plaster Student Union • Power House • Pummill Hall • Siceluff Hall • Temple Hall • Wells House • Woods House

  7. Electrical Repairs: Saturday, March 21st 9:00 am – 9:00 pm • To increase reliability of our campus electrical spine • To support switch replacement in the tunnels • To support switchgear replacement at Siceluff Hall

  8. Buildings Affected by Electrical Repairs: • Art Annex • Blair – Shannon House • Carrington Hall • Central Stores & Maint. • Cheek Hall • Craig Hall • Ellis Hall • Greenwood Lab School • Freudenberger House • Hill Hall • Karls Hall • Kemper Hall • Kings Street Annex • McDonald Arena • Morris Hall (Taylor Health and Wellness Center & Bookstore) • Plaster Sports Complex • Plaster Student Union • Power House • Pummill Hall • Siceluff Hall • Temple Hall • Wells House • Woods House

  9. Shutdown Summary: STEAM: Saturday, March 21st – 22nd 1:00 am – 1:00 am ELECTRICAL: Saturday, March 21st 9:00 am - 9:00 pm

  10. Questions?