School Building Committee – December 17 , 2018 Design Development Phase

Get the latest updates on the design development phase of the Wareham Elementary School project, including responses from the MA Historical Commission, PARP report delivery, and MSBA project scope and budget conference. Explore Wareham-inspired themes and the project timeline.

sarahc
Download Presentation

School Building Committee – December 17 , 2018 Design Development Phase

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. School Building Committee – December 17, 2018 Design Development Phase

  2. General Updates • MA Historical Commission • MHC Response to Draft Report Received November 7th • PARP Report Delivered to MHC December 6th • MSBA Project Scope & Budget Conference Held November 9th • ALL spaces eligible for reimbursement, no ineligible SF in design • $51.8M Maximum MSBA Grant Amount Negotiated ($38.6M District Share) • MSBA Board Meeting December 12th • Unanimous MSBA Board Vote

  3. Work Plan Overview • Commissioning Agent / Engineer’s Kickoff Meeting • LEED Kickoff Meeting w/ Engineers • Design Review – Stakeholders / Teachers • Interior Color Theory Meetings • Site Design Review Meetings • Security Design Review Meetings • Site & Building Design Review Meetings w/ Municipal Officials

  4. Wareham Inspired Themes • NATIVE AMERICAN “Summer Home” Wampanoag Heritage Shell Fishing Still Thrives

  5. Wareham Inspired Themes • CRANBERRIES Cranberry Harvest Label Art – United Cranberry Company

  6. Wareham Inspired Themes • EAST WAREHAM E Wareham Light Agawam Hall Old E Wareham Train Station

  7. Wareham Inspired Themes • ONSET Historic Onset Bay Wicket’s Inn & Pub Marc Anthony’s

  8. Wareham Inspired Themes • WEST WAREHAM West Wareham School Historic Tremont Train Station

  9. Wareham Inspired Themes • WAREHAM CENTER Tobey Hospital Rosebrook Village Train Station

  10. Wareham Inspired Themes • VIKINGS GO VIKINGS !

  11. Main Entrance

  12. Kindergarten Entrance

  13. Gymnasium – Cafeteria - Music

  14. Cafeteria Entrance

  15. PROJECT TIMELINE Wareham Elementary School 90% Design • Oct 11, 2019 Estimate Set • Oct 14–25 Estimating • Oct 28–Nov 1 Reconciliation & VE • Nov 15 Submission to MSBA • Trade / GC Pre-qualification • Nov 4-27 Request for Qualification (RFQ) Period • Dec 6 Prequalified Firms Notified • Dec 7-31 Bid Protest Schedule Contingency Construction • Phase 1 New Construction • Systems Commissioning • Punchlist & Closeout • Building Occupancy 2021 Design Development • Mar 22, 2019 Estimate Set • Mar 25–Apr 12 Estimating • Apr 15-19 Reconciliation & VE • Apr 26 Submission to MSBA YOU ARE HERE DD 60% 90% 100% 100% Design • Dec 24, 2019 100% Design Complete • Dec 31, 2019 100% Submitted to MSBA • Bidding • Jan 1-Jan28 Trade Bidding • Jan 1-Feb11 GC Bidding • 60% Design • Jul 19, 2019 Estimate Set Due • Jul 22–Aug 9 Estimating • Aug 12-16 Reconciliation & VE • Aug 23 Submission to MSBA Early EnablingPackage • Apr 19, 2019 Bid Package Due • May 24, 2019 Bids Due • Jun – Sept Abate/Demo/Site Prep Last updated 11.17.17

  16. Baseline Schedule – DD & 60% Design

  17. Baseline Schedule – 90/100% Design & Bidding

  18. Market Evaluation – Other MSBA Projects in DD

  19. ProjectCashflow

  20. ProjectBudget

  21. Key Dates / Next Steps • Oct 22, 2018: Town Meeting Vote – 2/3 Approval Nov 6, 2018: Ballot Vote for Project Funding – Simple Majority Dec 12, 2018: MSBA Board of Directors Meeting (Approval of Schematic Design & Budget) Mar 22, 2019:DD Estimate Set Due Apr 15-19, 2019: Target SBC Meeting - DD Value Management Apr 26, 2019: DD Submission to MSBA May 24, 2019: Early Package Bids Due Jul 19, 2019: 60% Estimate Set Due Aug 12-16, 2019: Target SBC Meeting – 60% Value Management Aug 23, 2019: 60% Submission to MSBA

  22. New BusinessMSBA Assignment of Commissioning AgentPublic Comment PeriodMeeting Adjournment