An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CDM Basics Marcos Castro, World Bank Institute CFCB Sao Paulo Workshop São Paulo City Hall, 4 May 2010

  2. Financing Low Carbon Development in Cities The CDM Option 20.08.2014 2

  3. CDM survival kit for city officiers: 1. Baseline The 3 key points: 1. Baseline;2. Additionality; 3. CDM Toolbox Reveals how much GHG can be saved and therefore demonstrates Carbon Financing potential (ex-post and market-dependent!) Carbon credits = emissions Baseline Greenhouse gas emissions Actual emissions Project start Time Historical Trend

  4. CDM survival kit for city officiers: 2. Additionality The 3 key points: 1. Baseline;2. Additionality; 3. CDM Toolbox Proves that the targeted emmissions wouldn‘t be saved without CDM (precondition for every CDM project) Carbon revenue makes the project attractive relative to investment alternatives Investmentthreshold Revenue / NPV / IRR Project without carbon revenue is profitable – but not sufficiently profitable compared with alternatives Project without carbon element Project with carbon element

  5. Some examples of additionality Capturing methane from an urban landfill and flaring it Carbon credits represent the only source of income for undertaking this activity Capturing methane from an urban landfill and utilising it to generate electricity • Project developer would have to demonstrate that the electricity revenue alone would not make this project attractive ? • Building a large hydro project for the grid in Ethiopia • Questionable additionality: there is already plenty of hydro activity in Ethiopia   20.08.2014 5

  6. 6 to 12 months 1.5 months Crediting period of the project Project Developer PIN PDD Recall: CDM Project Cycle Depicts the step-by-step approach to CDM as well as the key institutions Recall: CDM Methodologies Depict the approach for different project types Host country approval DNA Project verification Project validation DOE Project registration CER issuance CDM EB http://cdm.unfccc.int/methodologies/index.html CDM survival kit for city officiers: 3. CDM Toolbox • The 3 key points: 1. Baseline;2. Additionality;3. CDM Toolbox • The Carbon Finance add-on challenge! Project CDM Cycle

  7. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE Project registration CER issuance CDMExecutiveBoard 20.08.2014 7

  8. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 8

  9. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 9

  10. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 10

  11. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 11

  12. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 12

  13. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE CDMExecutiveBoard Project registration CER issuance 20.08.2014 13

  14. The CDM project cycle 6 to 12 months 1.5 months Crediting period of the project Project Developer Project feasibility assessment / PIN CDM project development / PDD Host country approval DNA Project verification Project validation DOE Project registration CER issuance CDMExecutiveBoard 20.08.2014 14

  15. Roles and timing for starting a CDM project in Cities

  16. Thank you very much for your attention! t. +44.(0)207.983.4627