Ashton Coal Operations Pty Ltd Community Consultative CommitteePresentation - 24 Sept 2013
Ashton Statistics June 2013 ROM 36,539 t Saleable Coal (CHPP) 10,356 t Total Coal Sales 47,678 t One Lost Time Injury (LTI) Three Total Recordable Injuries (TRI’s) One High Potential Incident (HPI) Total Employees 286.9 Staff 77 Wages 139 Contractors 70.9 July 2013 ROM 250,269 t Saleable Coal (CHPP) 108,357 t Total Coal Sales 55,576 t One LTI One TRI Nil HPI Total Employees 293.3 Staff 76 Wages 139 Contractors 78.3 August 2013 ROM 416,084 t Saleable Coal (CHPP) 143,106 t Total Coal Sales 129,779 t One LTI + Two previous injuries becoming LTI’s Two TRI Nil HPI Total Employees 302 Staff 76 Wages 139 Contractors 87 YTD 2013 ROM 1,757,423 t Saleable Coal (CHPP) 600,452 t Total Coal Sales 624,046 t
Projects • 5.5m Main Fans commissioning • Gas Drainage Plant civil works • Tailing Dam construction of ramps to install pumps • Willow removal along Bowmans Creek Stage 1 • BCD tree planting works • Gas Well Drilling Longwall 102
Around Site Left: Slashing fire trails Right: Irrigating Eastern BCD Above and Right: Slashing of NEOC rehabilitation pasture areas.
Air Quality Network Air Quality & Noise Monitoring Locations
Noise Monitoring Statutory noise monitoring was conducted in August 2013. The monitoring occurred while there was north westerly winds, at the time it was the near the best production we’ve had from the underground and CHPP in a 24hr period in the last two years; dozers were on stockpiles and there where two trains loaded at 1615 and 2030 during the noise monitoring. We were at full production and operation – basically the worst case scenario for the possibility of a noise exceedence. There were no exceedences for the reporting period.
Complaints There were seven complaints received during this quarter. Total complaints Direct: 2, Indirect: 5, Total enquiries: 0. The two complaints received directly to Ashton were in regards to the school bus obscuring access to Dairy Lane. A larger area has been constructed for the bus to turn off the highway and turn around allowing access to Dairy Lane. Five complaints were received via the Department of Planning & Infrastructure (DoP&I) relating to excessive noise at Ashton Coal. Investigations were carried out upon each complaint and found no issues regarding Ashton.