1 / 18

E&C Cost Perspectives: Engineering & Construction Mission Areas Overview

This presentation provides an overview of the mission areas in Engineering & Construction, including programming, design, and recommendations for the Tulsa District. It also discusses the cost issues that can impact all phases of project development.

sbernard
Download Presentation

E&C Cost Perspectives: Engineering & Construction Mission Areas Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tulsa DISTRICT Engineering & Construction (E&C)Cost Perspectives19 March 2019 • Shawn Painter, P.E. • Chief, Engineering Branch • Tulsa District, USACE

  2. E&C Cost Perspectives • Mission Areas Overview • Programming • Design • Recommendations • Conclusion E&C Hydropower Implementation

  3. Mission Areas Overview USACE Mission is diversified and Tulsa District has nearly every mission. Planning Regulatory Recreation Dam and Levee Program (Flood Risk Management) Emergency Management Civil Works Operations & Maintenance Hydropower Navigation Interagency Support Military Construction Military Sustainment, Restoration, and Modernization (SRM) Environmental Real Estate File Name

  4. Mission Areas Overview USACE Mission is diversified and Tulsa District has nearly every mission. Planning Regulatory Recreation Dam and Levee Program (Flood Risk Management) Emergency Management Civil Works Operations & Maintenance Hydropower Navigation Interagency Support Military Construction Military Sustainment, Restoration, and Modernization (SRM) Environmental Real Estate File Name

  5. Mission Areas Overview USACE Mission is diversified and Tulsa District has nearly every mission. Planning Regulatory Recreation Dam and Levee Program (Flood Risk Management) Emergency Management Civil Works Operations & Maintenance Hydropower Navigation Interagency Support Military Construction Military Sustainment, Restoration, and Modernization (SRM) Environmental Real Estate File Name

  6. Military & IIS Mission • Engineering • Construction • Installation Support Vance AFB Pantex Tinker AFB Altus AFB McAlester Fort Sill Sheppard AFB

  7. Cost and the Mission • DoD (and Industry Partners by Extension) Are: • Stewards of Taxpayers Dollars • Risk Informed Decision Makers • Process Improvers • Partners in Success/Failure • Supporting our Nation with Critical Infrastructure • Cost Issues Can Impact All Phases of Project Development • Planning & Programming • Design • Construction • Operations & Maintenance

  8. Planning & Programming Steps in the MILCON Budget Process: Identification of the Project Need & Constraints (NEPA, Siting, Alternatives, Scope, etc.) Project Initiation – Requirements Documentation/Project Definition Identify Execution Method (D/B, DBB, etc.) Budgetary Cost Development Submit Package for Funding Authorization from Billpayer (Congress, CF Hydropower, etc.) Design, Construction, O&M/SRM, Disposal MILCON Programming Programming is the process of developing and obtaining approval and funding for Military Construction (MILCON) projects (AFI 32-1021) Planning Charrette to Develop the DD1391 Form at Installation for Agency & Congressional Approval. 5 Year process for MILCON projects (minimum)

  9. DD 1391 Example CCL PA

  10. Example Timeline for MILCON projects

  11. Programmatic Discussion Items • Incorporation of Risk When Developing the DD1391? • Price of working inside the fence vs. outside (Area Cost Factors accurate?) • Price of government process and controls vs. private industry • Market conditions, worker availability, material cost fluctuations (forecasting contractor risk?) • Acquisition approach • Unforeseen conditions • Lost design/Scope Reduction/User Requested Changes • Incorporate Lessons Learned • Due diligence during PDR/CDR • Understanding Program Estimate Limitations ($/SF) • Cost is not definitized by actual scope and design of this specific project • Standard designs can help, but there are local conditions that may not be included (safe rooms, SSMR, foundations, sustainability measures, etc.). • Unique facilities that don’t fit in the typical cost/SF • Economy of scale impacts • Material selection • Type of building construction • Sustainability • Utility requirements

  12. Design Discussion Items • Cost Accuracy Improves During Design • Develop the Independent Government Estimate (IGE) • Iterative Design Process Sharpens IGE Accuracy with Time • Value Engineering • Risk Identification (*Not All) • Design Cost Drivers • Change in Criteria/Codes • Quality Management Performance • Sustainable Features • Site Issues (Drainage, AT/FP, etc.) • Construction Material Selection (ICF, PEMB, CMU, tilt-up, etc.) • Architectural Compatibility • Foundation Type • Utility Uncertainties • PDR/CDR Omissions • Real Property Installed Equipment • MILCON & SRM Extents (Colors of Money) • Biddability & Constructability of Design

  13. Cost Concerns - MILCON • Don’t Push Design Problems to Construction • Ability to timely impact change is LOW • Cost to impact change is HIGH • Ambiguity/Conflicts Create Disputes Between Gov/Ktr (REAs/Claims) • Partnership Suffers • Quality Design = Better Cost Control • Don’t Delay • Reprogramming Can Take 6-8 Months • Identify Potential Design Issues Immediately (Ktr  Area OfficesDOR) • Design Corrections During Construction Impact Schedule and Cost • Re-work Costs Everyone

  14. Recommendations • Programming Phase • Develop Risk Matrix During PDR/CDR (Gov & Ktr Risks) • Cost-Schedule-Risk-Analysis (CSRA) Approach during DD1391 Development • Independent Development of DD1391 Costs with Peer Review/Validation • Inclusion of Lessons Learned During PDR/CDR (Correct People on the Bus) • Program to Minimum Facility Requirement AND Add 5-10% in User Options • Installation/Owning Agency Consider What Is Minimally Acceptable • Installations consider SRM funded Investigations/Survey/Site Assessment Prior to PDR/CDR • DoD Consider Funding DDC Via Discretionary Pot vs. Project Funds (DDC Is Deducted from Contingency) • Design Pre-Award Phase • Design to 95% of CCL (Sacrifice Options if Needed) • Enforce Independent Government Estimate with Peer Review/Validation • Insure Proper Design Quality Management • Upward Report Cost Concerns During Design Immediately • Incorporate Ktr Risk Reduction Measures • Contractor Involvement in Common Construction Problems (e.g. MATOC Pool Queries/Surveys) • Value Engineering • Partner on Cost Concerns • Ktr’s Provide Cost Reduction Recommendations During Bidder Inquiry • Ktr’s Provide Feedback to KO After Pre-bid Site Visits

  15. Questions?

  16. Backup Slides

  17. References • ICEAA Link: http://www.iceaaonline.com/ready/wp-content/uploads/2014/06/MM-1-Presentation-Military-Construction-Cost-Estimating.pdf • Whole Building Design Guide: http://wbdg.org

  18. Programmatic Concerns • Costs Concerns • After Congressional authorization, the funding available for construction is locked at the PA and includes a standard 5% contingency. (reprogramming above the 5% is authorized at Agency level up to $2M or 20% - whichever is less, otherwise Congress has to reauthorize) • Construction cost estimate in the DD1391 Block 9 is derived using historic SqFt estimates for facility type for the services nationwide. Not definitized cost estimates. • Facilities have unique local requirements (SafeRooms, SSMRs, foundations, sustainability,etc) that can be cost increasers compared to national averages. • Economy of scale can be advantage/disadvantage • Area Cost Factors (ACF) are used to adjust for perceived local market rates and can be incorrect (local industry interest, access requirements, etc) • Programmatic cost estimates are not “real time” inclusive of market trends (steel tariffs, labor availability, material shortages, etc). Cost books can capture project costs well beyond the last 2 years. • Acquisition requirements are not fully established at DD1391 development. (i.e. will project be split into multiple acquisitions) • Rolling risk into the DD1391 is very challenging as the process doesn’t lend itself to cost risk outside the standard 5%. • Installations/commands are competing for a line in the agency budget submission. So, too much cost can put the project at risk. • Programming charrettes can be performed more than 5 years out of the program year and local conditions may change the associated project scope & risks.

More Related