210 likes | 380 Views
Discussion Slides: Basic Options for CRYO IR1/IR5 & IR4 4 th HL-LHC Parameter and Lay-out Committee . Rob van Weelderen, Cryogenic Group, Technology Department, CERN with the contributions of L.Tavain , K . Brodzinski , G. Ferlin , U. Wagner. Overall HL-LHC layout.
E N D
Discussion Slides: Basic Options for CRYO IR1/IR5 & IR44thHL-LHC Parameter and Lay-out Committee Rob van Weelderen, Cryogenic Group, Technology Department, CERN with the contributions of L.Tavain, K. Brodzinski, G. Ferlin, U. Wagner
Overall HL-LHC layout • HL-LHC cryo-upgrade: • 2 new cryoplants at P1 and P5 for high luminosity insertions • 1 new cryoplant at P4 for SRF cryomodules • New cooling circuits at P7 for SC links and deported current feed boxes • Cryogenic design support for cryo-collimators and 11 T dipoles at P3 and P7
Main components at Point 1 and 5 (& quench buffers) Ground level Shaft Cavern ? ? ? ? ? ? Matching section Inner triplet Matching section Continuous cryostat Continuous cryostat ?=Assumed baseline: Q5, Q6 @ 4.5 K Q7 replaced by higher gradient Q7+ @ 1.9 K
Space requirement in caverns and shafts Shaft requirement In addition to the 3 SC links: - 1 compound cryoline (~DN500) - 3 warm recovery lines (~DN100-150) Cavern requirement: - 1 cold compressor box
P1 & P5 layout 1: Matching section cooled with sector cryoplants P1 or P5 S81 or S45 S12 or S56 Note: Cryo for Sector- and LSS-powering are combined except for IT & D1
P1 & P5 layout 2a: Matching section cooled with inner triplet cryoplants P1 or P5 S81 or S45 S12 or S56 Note: Cryo for Sector- and LSS-powering are as well separated (links and DFBA / DFBX leads re-arrangement)
IR1/IR5 Options considered (2a) (2b)
Interconnection for partial redundancy Present redundancy baseline w/o interconnection (IB) in between cryoplants ! “Partial” redundancy: - cold standby during technical and Xmas stops - low beam-intensity operation in case of major breakdown on the new cryoplant (full nominal redundancy not possible) - what about redundancy with detector cryogenics ? Cost increase
P4 Layout: new cryogenics for SRF module P4 S34 S45 With interconnection for partial redundancy (Accepted as baseline)
P4 cryogenic process & flow diagram UX45 UCB: 6-7 kW @ 4.5 K cryoplant (tbc)
Sector heat loads: local limitation(valves, HX, piping,…) Synchrotron radiation Image current Beam gas scattering Resistive heating
Sector heat loads: global limitation Load transfer from 1.9 K to 4.6-20 K refrigeration ~1 W/m per aperture available for e-cloud ~20 % lower than local limitation (OK !) Installed (as specified)
Interconnection box (IB) Up to 10 cryogenic valves to be integrated in the tunnel (space ?) Volume in between valves used as controlled volume for safe cryo-consignation Valve DNs depend on the level of needed redundancy
Minimum CCB requirement in cavern Best for cavern integration Double CC train Single CC train 500 W HX Depending of the total cooling capacity and operating temperature Global or distributed ? (500 W max size for distributed HX !)
Number of cold compressor trains LHC sector Present HL-LHC Requirement (tbc)
Minimum size of cold compressor box (CCB) ~5.5 m + electrical cabinets in protected area for instrumentation, AMB controllers and variable-frequency drives (~0.6 x ~2.7 x ~2.2 m3) Ground level installation of cabinets under study with 150 m of cabling (today: 25 m max) ~1.6 m ~6 m
Schedule P7 P1&P5 (type A) P1&P5 (type X) : Freeze of heat load requirement