An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Project CoordinationPresented by:Philip H. Mowry, PE, PRSBOPHM Associates, Inc.Richard A. Bernardini, PE, CCM March 9, 2006

  2. What are the options? • Clerk of the Works • Construction Management – Multi-Primes • Construction Management – 4 Primes • Architect/Engineer – Contract Administration • Single Prime** – General Construction • Design – Build ** ** (If/when possible)

  3. Project Phases Design Phase Bidding Phase Construction Phase Close Out When are they involved? ARCHITECT ROLE CONSTRUCTION MANAGEMENT ROLE DESIGN-BUILD ROLE CLERK OF THE WORKS ROLE GENERAL/PRIME CONTRACTOR ROLE

  4. How do they effect the project?

  5. Clerk of the Works • Advantage • Independent Quality assurance • “Reports” on project • Low cost • Disadvantage • Single resource, no back-up • Limited expertise • No involvement during design

  6. Construction Management – Multi-Primes • Advantages • Preconstruction Services • Team Approach • A/E Design • CM Cost and Schedule • Independent • Cost Estimating & Value Engineering • Schedule/Phasing Analysis • Constructibility Reviews • Improved CD’s • Savings offset fees

  7. Construction Management – Multi-Primes • Advantages • Primes work direct for District • Independent Advocate • Depth of Resources • Estimating Department • Multi-disciplined Staff • Professional Expertise • RA, PE, PMP

  8. Construction Management – Multi-Primes • Disadvantages • Multi-prime scope coordination • Increased number of contracts • Increased CM staffing and Fee

  9. Construction Management – 4 Primes • Advantages • Preconstruction Services • Team Approach • A/E Design • CM Cost and Schedule • Independent • Cost Estimating & Value Engineering • Schedule/Phasing Analysis • Constructibility Reviews • Improved CD’s • Savings offset fees

  10. Construction Management – 4 Primes • Advantages • Primes work direct for District • Independent Advocate • Depth of Resources • Estimating Department • Multi-disciplined Staff • Professional Expertise • RA, PE, PMP • Reduced coordination

  11. Construction Management – 4 Primes • Disadvantages • Greater Reliance on GC • Minimal CM staffing • One bad contractor significantly affects all

  12. Architect/Engineer – Contract Administration • Advantages • Continuous knowledge of project • Single source • Disadvantages • No independent analysis of issues

  13. Single Prime – General Construction • Advantages • One Source of contact • Centralized communication • Disadvantages • One Source of contact • All trades by GC • Not yet allowed by PDE

  14. Design-Build • Advantages • One Source of contact for Design and Construction • Centralized communication • Fast • Disadvantages • One Source of contact • Design and All trades by GC • Definition of Scope Critical at RFP Stage • Not yet allowed by PDE

  15. It’s all about RISK • Who do you trust to: • Cost effectively deliver the project • On time • On budget • Meet quality expectations • Protect you