Westbrook Village Verdict Storm Drainage & Waterline Improvements Contract Amendment for GMP No.1 Pulice Construction, Inc. ITEM 10C April 21, 2009. Construction GMP No. 1. Drainage Construction Storm Drains: $3,110,352 Basin Modifications: $1,660,725
E N D
Westbrook Village Verdict Storm Drainage & Waterline Improvements Contract Amendment for GMP No.1 Pulice Construction, Inc. ITEM 10C April 21, 2009
Construction GMP No. 1 Drainage Construction Storm Drains: $3,110,352 Basin Modifications: $1,660,725 Drainage Costs: $4,771,077 Waterline Construction 91st Avenue waterline: $1,709,341 Beardsley Road Ph. I: $1,872,786 Beardsley Road Ph. II: $1,338,493Waterline Costs: $4,920,620 GMP No.1 $9,691,697
Westbrook Village Verdict Background • Westbrook Village Verdict was a result of a suit brought against the City of Peoria in 2005 for damages upon the Golf Courses at Westbrook Village • Staff responded by creating a drainage improvement project to address the requirements set forth in the court order
Beardsley Road Union Hills Drive Desert Amethyst Storm Drain & Basin Sun City 91ST Avenue 83RD Avenue
18” outlet OUTLET CULVERTS MODIFICATION TO PROVIDE RETENTION
18” outlet OUTLET CULVERTS MODIFICATION TO PROVIDE RETENTION
24-inch Waterline Background • 24-inch waterline, 91st Avenue • One mile of waterline between Union Hills Dr. and Beardsley Rd. • Originally programmed as CIP Project UT00096 • 24-inch waterline, Beardsley Road • Two miles of waterline between 87th Ave. and Lake Pleasant Rd. • Originally programmed as CIP Project UT00145 • These waterlines will become part of a North-South transmission system to increase the overall reliability of the City’s water system
101 Beardsley Rd. Waterline Beardsley Road 91st Ave. Waterline Lake Pleasant Road Union Hills Drive 91st Avenue 83rd Avenue
Project Schedule • Storm Drains and 24- inch Waterlines Construction • Scheduled for May 2009 to Dec. 2009 • 2 Crews (1 - Storm Drains, 1 – Waterlines) to expedite work • Work Adjacent to Parkridge Elementary • During Summer 2009 • Pavement Restoration • GMP#2 preliminary estimate: $1,255,000 • To be presented to Council in Spring 2010. • Construction to commence in May 2010, due to seasonal temperatures
American Recovery and Reinvestment Act (ARRA) • February 17, 2009 • President Obama signed the American Recovery and Reinvestment Act of 2009 • City has applied for ARRA funds • Application is pending approval by the Arizona Water Infrastructure Finance Authority • The benefit to the City is a low interest loan (20 years at 2%) • Pulice Construction’s contract has been amended to be in compliance with the ARRA funding requirements (Davis Bacon Wage Rates & Buy American)
Questions? For updated information on capital projects, please visit: www.peoriaaz.gov/buildingpeoria