Progress during the period 23rd Apr - 29th Apr 2018 #58Virtual Review of Polavaram Project by Hon’ble Chief Minister Dt. 30th April 2018 Polavaram Irrigation Project Water Resources Department
Project status • Head works – Main dam • Excavation for spillway & spill channel : 806.29 lakh cum completed out of total 1115.59 lakh Cum (72.30%). • Concreting for spillway & St. Basin: 5.76 lakh cum (excluding 1.65 L Cum of crevices filling) completed out of 16.39 lakh Cum (35.10%). • CC blocks concrete in spill channel (started on 23.04.2018) -1400 cum completed. • D’wall concreting done for 1214.6 Rm out of 1427/1397 Rm (85.10%). • Fabrication of Radial Gates completed for 10,800MT out of 18000 MT (60%). • Jet Grouting for d/s Coffer dam completed for 1098 m out of 1417m (78%). • Jet Grouting for U/s Coffer dam completed for 1153.5 m out of 2050 m (56.30%). • PIP– Main Canals • RMC : Excavation completed for total length of 177.9 Km (100%), Lining completed for 149.395 KM out of 176.20 Km (84.8%). Structures 185 completed. • LMC : Excavation completed for 164.748 Km out of 210.927 Km (78%), Lining completed for 124.593 KM out of 210.927 M (59%). Structures 137 Completed. * As per Revised estimate **As per out turn
# percentage on total Qtty This week’s Progress in Nutshell (23rd April – 29th April)
Excavation Status Target Date Aug’ 2018 Total Qty 124 L Cum Balance Qty 28.51 L Cum Target Date Dec’ 2018 Total Qty 50 L Cum Balance Qty 30.76 L Cum Left flank Godavari River 26% U/S Coffer dam Godavari River D/S Coffer dam ECRF dam Target Date Jun’ 2018 Total Qty 163 L Cum Balance Qty 70 L Cum River diversion Target Date Sep’ 2018 Total Qty 163 L Cum Balance Qty 64.51 L Cum Target Date Aug’ 2018 Total Qty 448 L Cum Balance Qty 45.45 L Cum Target Date DEC’ 2018 Total Qty 131 L Cum Balance Qty 101.48 L Cum Qtty for CC Blocks &Embkt: 38.59 L cum Pilot Channel 902 Hill Target Date Mar’ 2019 Embt. Qty 7.79 L Cum Filters exvn Qty 30.78 L Cum Approach Channel Total Qty 161 L Cum Balance Qty Nil PERCENTAGE COMPLETION Spill Channel Spillway
Earthwork - Progress Achieved (Period 23rd Apr – 29th Apr’18) *Total Quantity involved including excavation for CC Blocks, Filters, Qtty for Embkt., etc
Revised Programme of Earthwork Excavation Revised on 16 Apr’18
Physical Status of Spill Way & Stilling Basin Concrete * Crevices/undulations
Progress for the period : 32098 cum This Month(Apr, 2018)Cumulative : 1,15,658 cum Cumulative in March 18 : 91,761 cum Cumulative in Feb‘18 : 40,077 cum Cumulative in Jan‘18 : 25,500 cum Cumulative in Dec ‘17 : 55,685 cum Cumulative in Nov : 44,651 cum Cumulative in Oct : 57,156 cum Cumulative in Sep : 60,950 cum Cumulative in Aug : 64,559 cum Cumulative in July : 78,860 cum Cumulative in June : 33,529 cum Cumulative in May : 30,063 cum Cumulative in Apr : 19,754 cum Cumulative in Mar : 17,832 cum Cumulative in Feb : 3,118 cum Cumulative in Jan‘17 : 2,076 cum Cumulative in Dec’16 : 90 cum Total spillway qtty. : 16.39 L Cum Total Executed : 5.76 + *1.65 L Cum Balance : 10.63 L Cum * Crevices/undulations
Progress for the period : 1400 cum This Month(Apr, 2018)Cumulative : 1400 cum Total spill channel qtty. : 18.75 L Cum Total Executed : 1400 Cum Balance : 18.735 L Cum
Progress of Diaphragm Wall during the period 23rd Apr – 29th Apr 2018 Ch.58m to 1485.6m Total no. of Panels : 400 , Completed : 326 Nos., Balance length: 212.4m
Progress of Jet Grouting during the period (23rd Apr – 29th Apr’18) ** will be taken up after River diversion during May 2018. * 400m of River lean flow width is involved
Elevation: +25.185 M Programme & Progress - Gate Leaf
Elevation: +26.00 M Hydraulic Hoist Spillway Stop log Gates Elevation: +25.316 M River Sluice Gates Elevation: +17.30 M
Dt. 29th April 2018 Main Works to be completed & Funds Required for River Diversion
For EL + 45.72 m (FRL) LA and R&R Status (L.A, Submergence, Land to Land and Housing)
For EL + 41.15 m LA and R&R Status (L.A, Submergence, Land to Land and Housing)
Quality Control tests Conducted during 23rd Apr – 29th Apr’18
Quality Control tests Conducted during 23rd Apr – 29th Apr’18
Quality Control tests Conducted during 23rd Apr – 29th Apr’18