A County Is Considering Using A Piece Of Focus Dreams/tutorialoutletdotcom
FOR MORE CLASSES VISIT www.tutorialoutlet.com A county is considering using a piece of park land for one of two alternative recreation projects. Project A would require construction costs of $2 million (year 0) and generate net benefits of $1 million per year for 10 years. (Assume the benefits are realized at the ends of years 1 through 10). Project B would require construction costs of $4 million and generate net benefits of $1 million per year for 20 years. (Assume the benefits are realized at the ends of years 1 through 20). If these figures are in real dollars, and the real discount rate is 7 percent, which project would the county select?
★
★
★
★
★