PS/SPS Days O. Aberle/ R. Losito for the ATB Group 18 th January 2006

PS/SPS Days O. Aberle/ R. Losito for the ATB Group 18 th January 2006. Restart of the PS/SPS in 2006 Upgrades and repairs on ATB equipment. Overview. Sieve Internal dumps PS Beam stoppers TIDVG (SPS) Consolidation Summary. PS Sieve. 2005 Sieve dismounted

selena
Download Presentation

PS/SPS Days O. Aberle/ R. Losito for the ATB Group 18 th January 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PS/SPS Days O. Aberle/ R. Losito for the ATB Group18th January 2006 Restart of the PS/SPS in 2006 Upgrades and repairs on ATB equipment

  2. Overview • Sieve • Internal dumps PS • Beam stoppers • TIDVG (SPS) • Consolidation • Summary PS/SPS days

  3. PS Sieve • 2005 • Sieve dismounted • Mechanical parts replaced (Piston, water and air connections, bearings) • Adjustment of air and water pressure after lab. tests • Sieve re-installed and fully operational • No spare parts, no spare! PS/SPS days

  4. PS internal dumpsGoal: 2 operational (pos. 47,48) + 1 spare 2005 • Transportation shielding problem solved • Dump 48 and spare mechanically refurbished • Cables pulled from B365 to Pos. 47 and 48 • New patch panels produced for old control units and future controls (installation week 8-10) • Water and electrical connectors replaced • Cabling replaced • Capturing magnets checked • Shielded working space (bunker) in B-150 available until end 2006. PS/SPS days

  5. PS internal dumps status • Dump 48 and 47 Operational and fully tested. • Installation: 02/2006 • Spare dump (former dump 47): Operational End 04/2006 • New power supplies (thanks to PO) ready and tested PS/SPS days

  6. PS internal dumps Further work: • Develop PLC based new control units (ATB/LPE) • Replacement of the control units during shutdown 06/07 ATB-LPE • Design and production (2007) of new supports to simplify the alignment procedure • Installation of new bunker in 867 (2007) • Proposition: Delay the production of the second chariot (consolidation) to 2007. PS/SPS days

  7. PS beam stoppers • 30 stopper (~ 5 types) in the PS complex • Stoppers mechanics in acceptable conditions • Annual maintenance of installed units • Electrical and pneumatic connections have to be replaced (2006-2009) • New stopper positions required • Using revised spare stoppers • New spares have to be produced (2008) PS/SPS days

  8. SPS TIDVG (internal SPS dump)Goal: 1 operational + 1 spare • Historic: • 5 Ti foils stretched over dump core material to prevent contamination by graphite dust • Observation: foils were deformed and lifted resulting in aperture limitation! Ti-foils were removed in 2005 PS/SPS days

  9. SPS TIDVG 2005 actions • Removal of Ti foils by cutting with special tool on spare TIDVG was not successful • Opening of the core by cutting the EB welds in the central workshop • Remove and recondition all absorbing blocks • On graphite blocks: • Removal of old Ti coating • CO2 blasting • Heat treatment • Ti re-coating • Assembly, machining (CERN) and EB welding (Techmeta) PS/SPS days

  10. SPS TIDVG 2006 • Installation of modified unit in February 2006 To be done in 2006 • Store the damaged TIDVG as back up • Modification of spare core • Modify the spare cast iron body (TED type) to get a full spare TIDVG • Assemble the spare core, weld it and fit it into the transformed shielding. PS/SPS days

  11. Consolidation project on beam intercepting devices • ~250 objects from BDI/BT and other orphans (e.g. stripper) with beam intercepting but no instrumentation functions • To be analyzed one by one (all machines) • documentation to be gathered • functionality to be understood, • limitations to be evaluated in view of the new beams • Needs for maintenance and priorities • Budgets to be allocated • Maintenance to be scheduled • Interventions on break until end of consolidation project (3-4 years) • Consolidation program to be launched 15 FTE and 3 Mio CHF during the next three years (in addition to the existing capacities or after 2008) • Standardization and upgrade solutions to be studied and planned PS/SPS days

  12. Strategy until completion of consolidation • ATB and BDI commonly ensure the follow up until full transfer of know-how • ATB-TD Mechanics & ATB-LPE Electronics : • Transfer line objects were partly produced by TD, their controls are being analyzed, manpower (1 technician LPE) will be available in March 2006 • Accelerator components: staff not included in the staff plan. Very dependant on future resources (start of consolidation project). PS/SPS days

  13. Summary • PS Dumps: Two upgraded dumps plus 1 spare ready for startup 2006. New electronics ready for shutdown 2006/07. • PS sieve: Existing sieve upgraded, construction of a spare not before 2007. • PS beam stoppers: Inventory and annual maintenance, revision of beam stoppers East hall. • TIDVG: One dump ready for start up. Preparation of spare in 2006. • Integration of ~250 objects during the next 3 years rely on a consolidation project. The staff situation should improve after completion of CNGS. PS/SPS days