ECC6 Upgrade Project Lessons Learned Arieh Stark – Keter Plastic Ltd

ECC6 Upgrade Project Lessons Learned Arieh Stark – Keter Plastic Ltd. ECC6 Upgrade. Project Aim: Technical Upgrade to MySAP ERP 2005 ( ECC6 ) Why: To prepare the foundation for NetWeaver / SOA Implementation To enable new SAP Functionality .

selia
Download Presentation

ECC6 Upgrade Project Lessons Learned Arieh Stark – Keter Plastic Ltd

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ECC6 Upgrade Project Lessons Learned Arieh Stark – Keter Plastic Ltd

  2. ECC6 Upgrade Project Aim: • Technical Upgrade to MySAP ERP 2005 ( ECC6 ) Why: • To prepare the foundation for NetWeaver / SOA Implementation • To enable new SAP Functionality . • To keep up-to-date – Mainstream Maintenance over.

  3. ECC6 Upgrade Sub Projects along the Way: • BIDI Migration • GUI Deployment / Citrix Deployment . • Keter’s AS400 Data Warehouse Replication from SAP. • 64 Bit Windows / SQL implementation. • Unicode enabling of our SAP Systems.

  4. ECC6 Upgrade Business Background: • The Keter Group has 22 SBU's dispersed globally in Israel, Europe, and the USA, connected to our central SAP System in Israel, working 24 hours a day, 7 Days a week.

  5. ECC6 Upgrade Technical: Before: • Operating System is Windows 2003 Enterprise. • Our 46C DataBase was SQL 2000 – Advanced- 900 GB. After: • Operating System is Windows 2003 Enterprise 32 Bit. • With x64 – we will only require Windows 2003 Standard. • Our new ECC6 Database is SQL 2005 – Enterprise 32 Bit and already 980 GB. • The Upgrade to ECC6 added 45 GB to the Database.

  6. Upgrade Project: Management: • Defines the scope of the Project – Planning. • Kick Off - Project beginning and end. • Support, Redefinition if required. Keeping to Deadlines. Technical Aspects: • Infrastructure sizing – Servers, Communication, Desk Top. Functionality: • Modifications and Custom Development. • Mapping of Delta Functionality. • Testing of functionality and Modifications . • Training

  7. ECC6 Upgrade Application / Functionality Testing: Elad Zafrir Eyal Halfon Perli Kaplan Marina Blumenkahl Karin Givon Ness/ Team Consultants( 4 ) Independent Consultants ( 3 ) Software Development / Modification: Ala Koifman Esther Bacshian Yair Israeli Ness/ Team Consultants( 4 ) Project Team: Keter Project Leaders: Shuky Sigura Arieh Stark HP Basis Team: Moshe Yerushalmi Yagil Hadri Boaz Paz NESS Advisory: Zohar Sarig Keter IT: Ilan Yacoby Igal Verbel

  8. ECC6 Upgrade Special Issues/Decisions: • BIDI Conversion with new SAP GUI Deployment – Before or at the same time as the Upgrade. • To Build a new Dev System from the Production System or upgrade both systems independently. • Down Time or Resource minimized Scenarios. • "In House" or "Fixed Price" Bid for the Project . • To Unicode enable all customer programs or leave it as a post-upgrade project. • SPAU – Clean the SPAU in the original 4.6C system or only in the Final System.

  9. ECC6 Upgrade Pre-Upgrade Analysis: Hardware Sizing: • From the Hardware Vendor – in our case HP. SAP Functional Upgrade Check: • SAP Service that checks Hardware and performance capabilities before and after Upgrade. Application Specific Upgrade ( ASU ) tools from SAP: • Includes application specific documents that outline problems with corresponding solutions including relevant SAP Notes. • For each application area – CO , PP , MM, FI and SD. • Tools to correct known problems – Variants etc – These tools were mostly built in to the ECC6 Upgrade Package already. Solution Manager: • Upgrade Roadmap Solution Browser: Release Notes: • Was not available at the time

  10. ECC6 Upgrade Pre-Upgrade Analysis: Internal Interface analysis: • ECC6 To/From external Systems – "Real Time" machine monitoring system , Time Clocks , VAT etc. • Interfaces between BW , APO and ECC6. IntelliCorp Assessor Upgrade Edition: • Both for Functionality and Project Scope • Required a live ECC6 System to compare to. • We used an Upgraded to ECC6 Dev system and the 4.6C Production System as reference.

  11. ECC6 Upgrade Intellicorp Assessor Upgrade Edition: Executive Summary: • Project Scope. Excel Lists containing: • All SAP programs according to SAP User and their index of modification in ECC6 according to Application Area. • New SAP transactions in ECC6. • Replaced Transactions in ECC6. • Used/Unused Customer programs with Usage statistics . • Customer Batch Input Programs and used BAPI's with code placement that would probably need to be changed in ECC6.

  12. ECC6 Upgrade AUE Highlights: • The Application Area was not always clear – We manually changed the Area where there were problems – a day's work. • This is a SAP Issue because it is not always accurate. • We sorted the Lists according to Application Areas and the lists were given to the relevant "Top Users" • There was no indication of the last Programmer who did a change in the Program list. • Consequently – we merged the Programmer Name into the Excels. • This allowed us to sort the Program Changes and give the Program Change List to relevant Programmers. • We also had a list of Customer programs that were not in use ,but they were called by other programs • Estimation of required resources - manpower. • The Excel sheets were passed onto the Keter Top Users and Programmers as a preparation and guide for functional and application Testing.

  13. ECC6 Upgrade Our Upgrade Plan : Upgrade a copy of the Development System as a trial run. • To see if we were missing anything – Software CD's , Notes etc. • CookBook entries. Upgrade a copy of the Production System as a Upgrade Sandbox System: • Used to test functionality – correct bugs . • Created a separate transport for each program. • We saved the transports and ported them to the next stage. Final Upgrade of the Development Systemand Interim Test System. • Simultaneous upgrade of a copy of the Production System as an Interim Test System • Code Freeze on the R3 Landscape. • Porting of Transports from the Sandbox System to both the Final Dev System and the Interim Test System. • SBU testing and training was done on the Interim Test System. Rehearsal Upgrade of the Production System. • Testing and Final System Verification and acceptance was done on this System. Final Upgrade of the Production System.

  14. ECC6 Upgrade Testing and Training Scenarios: Application and Functionality: • Performed by Top Users and Implementation Consultants in the Keter Headquarters. • Used the Lists derived from the Intellicorp Upgrade Assessment. • Was done on our Upgrade Sandbox System first. • Corrections / modifications were done on this system – the Transports were ported to the Final Dev system. • Then testing was done on the Interim Test System. • 2nd Level testing was done by the Top Users in the SBU's. • They concentrating on their most complex procedures. • They were also responsible for local training. • This testing and training was done on the Interim Test System.

  15. ECC6 Upgrade Testing and Training Scenarios: Modifications and Customer Development: • Checked and tested by the relevant Programmers / Top Users. • Used the Intellicorp Upgrade Assessment derived Lists.

  16. ECC6 Upgrade Project Gantt:

  17. ECC6 Upgrade Upgrade Trial Run: Copy of Development System DEV Test/QA PRD R3 • To check if anything is missing. • Notes, Downloads, etc. • Ran Intellicorp Upgrade Assessment ECC6 DEV Trial

  18. ECC6 Upgrade Upgrade PRD to Sandbox: Copy of Production System DEV Test/QA PRD R3 • Testing • SPAU • Corrections • Save Transports ECC6 SandBox

  19. ECC6 Upgrade Upgrade Final DEV and PRD (Test): Copy of Development and Production System DEV Test/QA PRD R3 R3 Code Freeze. SPAU again. Transports from Sandbox Testing and Training in SBU’s ECC6 DEV Final Test/QA Transports

  20. ECC6 Upgrade PRD Rehearsal: Copy of Production System DEV Test/QA PRD R3 Testing and Final System Verification and Acceptance ECC6 DEV Final PRD Rehearsal Transports

  21. ECC6 Upgrade Final PRD – Go Live: Copy of Production System DEV Test/QA PRD R3 • Contingency Plan for Roll Back • Original PRD system exists • IP and Server Name change only. ECC6 DEV Final PRD Final Transports

  22. ECC6 Upgrade Test/QA from PRD: DB Copy of Production System DEV Test/QA PRD R3 ECC6 DEV Final Test/QA PRD Final DB Copy

  23. ECC6 Upgrade Glitches during the Upgrade Project: • Localization CD at the last moment from NESS. • HR SPAU entries.

  24. ECC6 Upgrade Post Upgrade: Go-Live Problems/Issues and Lessons: • Application Problems • Citrix/GUI Deployment Problems • Basis Problems.

  25. ECC6 Upgrade Application Problems: 1st Week Problems: • EDI did not fully work – very serious . • SAPEVT did not work. • HR Master data program did not work as before. • COHV changed - no CO13. • Changes to CS01/2/3. • Replacement of MRHR with MIRO - Traumatic 2nd Week Problems: 3rd Week Problems:

  26. ECC6 Upgrade GUI and Citrix Deployment: Hebrew GUI Problems: • 6.40 GUI icons are different from 46D • Field Painting in Hebrew. Citrix Problems: • Local DeskTop and Network Mapping. • Printing through LOCL. • Requires better quality communication lines.

  27. ECC6 Upgrade Basis : • SAP Functional Upgrade Verification. • Performance tuning. • Database tuning. • Memory Tuning. • SQL 2005 Service Pack 2 – waiting …. • SAP ABAP and Basis Support Packs. • Waiting for COP 11.

  28. ECC6 Upgrade Summary: • The SAP Technical Upgrade Process worked like a "Charm" • Requires a thorough preparation and analyses of Application functionality. • Mapping - Assessment for Upgrade Tool ( Intellicorp ) . • Requires Thorough Testing and User Training.

  29. ECC6 Upgrade Lessons Learned: • Keep the project simple - do not implement any new functionality. • Do not try to mix too many projects together. • It was problematic to Deploy Citrix and the new SAP GUI at the same time. • The Upgrade project must be known to Localization at Ness . • Localization CD at the last moment. • Do not strive for too much Perfection – Know the Business Risks and Limits. • Constantly Update Management and all Project People. • Have a Contingency Plan for Roll Back.