Manufacturer’s Recommendation for Setting up a Theodolite

Manufacturer’s Recommendation for Setting up a Theodolite. 1) Ensure that :-. the tripod head is approximately level. the tripod feet are firmly fixed in the ground. This should be done BEFORE removing the theodolite from its box.

sergioperry
Download Presentation

Manufacturer’s Recommendation for Setting up a Theodolite

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Manufacturer’s Recommendation for Setting up a Theodolite 1) Ensure that :- • the tripod head is approximately level • the tripod feet are firmly fixed in the ground • This should be done BEFORE removing the theodolite from its box. 2) Place the theodolite on top of the tripod, and tighten the centring screw to clamp the theodolite centrally on the tripod head. 3) Use the optical plummet to focus onto the survey station (e.g. nail in top of peg) • Turn the optical plummet eyepiece to focus the reticle (i.e. the black • circular mark) • push (or pull) the optical plummet focussing ring to focus on the • survey station

  2. Optical Plummet Rotate to focus reticle Pull in / out to focus on the ground (survey station)

  3. Manufacturer’s Recommendation for Setting up a Theodolite 1) Ensure that :- • the tripod head is approximately level • the tripod feet are firmly fixed in the ground • This should be done BEFORE removing the theodolite from its box. 2) Place the theodolite on top of the tripod, and tighten the centring screw to clamp the theodolite centrally on the tripod head. 3) Use the optical plummet to focus onto the survey station (e.g. nail in top of peg) • Turn the optical plummet eyepiece to focus the reticle (i.e. the black • circular mark) • push (or pull) the optical plummet focussing ring to focus on the • survey station 4) By rotating the levelling foot SCREWS, using all three in a random manner if necessary, centre the reticle (black circle) in the optical plummet onto the survey station. 5) Carry out an approximate levelling. Using the pond bubble and by adjusting the length of TWO tripod LEGS, bring the pond bubble into the centre of the pond bubble tube.

  4. Manufacturer’s Recommendation for Setting up a Theodolite 1) Ensure that :- • the tripod head is approximately level • the tripod feet are firmly fixed in the ground • This should be done BEFORE removing the theodolite from its box. 2) Place the theodolite on top of the tripod, and tighten the centring screw to clamp the theodolite centrally on the tripod head. 3) Use the optical plummet to focus onto the survey station (e.g. nail in top of peg) • Turn the optical plummet eyepiece to focus the reticle (i.e. the black • circular mark) • push (or pull) the optical plummet focussing ring to focus on the • survey station 4) By rotating the levelling foot SCREWS, using all three in a random manner if necessary, centre the reticle (black circle) in the optical plummet onto the survey station. 5) Carry out an approximate levelling. Using the pond bubble and by adjusting the length of TWO tripod LEGS, bring the pond bubble into the centre of the pond bubble tube. The theodolite is ROUGHLY LEVELLED AND CENTRED over the station.

  5. (continued) Manufacturer’s Recommendation for Setting up a Theodolite 6) Fine level the theodolite using the PLATE level bubble tube and foot SCREWS • Position a) align the plate level bubble tube with two foot screws. • Centre the bubble by rotating the two foot screws in opposite • directions. The bubble follows the LEFT thumb.

  6. Position a Bubble follows LEFT THUMB

  7. Plate Level Bubble Tube Required to move the bubble to the right Foot Screws Bubble follows direction of left thumb Both thumbs move in (or out)

  8. Position a Bubble follows LEFT THUMB

  9. Position a

  10. Manufacturer’s Recommendation for Setting up a Theodolite 6) Fine level the theodolite using the PLATE level bubble tube and foot SCREWS • Position a) align the plate level bubble tube with two foot screws. • Centre the bubble by rotating the two foot screws in opposite • directions. The bubble follows the LEFT thumb. • Position b) align the plate level bubble tube with the third foot screw. • i.e. 900 from position a) • Centre the bubble by rotating the the third foot screw (only) • The bubble follows the LEFT thumb.

  11. Position b 900 to position a Bubble still follows LEFT THUMB

  12. Using the third footscrew only Select “Setting up a theodolite --- 3”