60 likes | 161 Views
Loudoun Water’s Potomac Water Supply Program. RWI/PRWPS- Request for Qualifications Pre-submittal Conference– July 9, 2013. AGENDA. Introduction Overview-Potomac Water Supply Program Overview-Process/Submission Requirements Overview- RWI/PRWPS Design Questions/Answer Period Close.
E N D
Loudoun Water’s Potomac Water Supply Program RWI/PRWPS- Request for Qualifications Pre-submittal Conference– July 9, 2013
AGENDA • Introduction • Overview-Potomac Water Supply Program • Overview-Process/Submission Requirements • Overview- RWI/PRWPS Design • Questions/Answer Period • Close
What is the Potomac Water Supply Program? • River Intake Structure • Raw Water Pumping Station • Raw Water Transmission Main • Water Banking Quarries • Water Treatment Plant • Finished Water Transmission Pipe
June 2014 Anticipated Approved for In-river Work May 2016 RWI/RWPS Final Completion January 2014 RWI/RWPS NTP Program Construction Schedule Feb 2017 RWI/RWPS Re-mobilize for Program Commissioning May 2016 RWT Final Completion Feb-April 2014 WTP and RWT NTP February 2017 WTP Substantial Completion