Rushern L. Baker, III County Executive. Haitham A. Hijazi Director. Project Information Meeting. Sunnyside Avenue Bridge Replacement. Agenda Exhibit Review Welcome Presentation Q/A. Beltsville Academy May 17, 2012. Sunnyside Avenue Bridge Replacement. Existing Roadway.
E N D
Rushern L. Baker, III County Executive Haitham A. Hijazi Director Project Information Meeting Sunnyside Avenue Bridge Replacement Agenda • Exhibit Review • Welcome • Presentation • Q/A Beltsville Academy May 17, 2012
Sunnyside Avenue Bridge Replacement Existing Roadway
Sunnyside Avenue Bridge Replacement Existing Bridge • Bridge History • - Type: single span, steel • multi-beam bridge with • a concrete deck • - Length: 37 feet • - Clear Width: 22 feet • - Built: 1946 • - Frequent flooding • - Structurally Deficient
Sunnyside Avenue Bridge Replacement Existing Bridge Extensive Deterioration
Sunnyside Avenue Bridge Replacement Existing Bridge Extensive Deterioration
Sunnyside Avenue Bridge Replacement Proposed Bridge
Sunnyside Avenue Bridge Replacement Planned Improvements Mitigate flooding Create a “Green / Complete Street” that includes shoulders, bike paths, sidewalks and street lights Create additional environmental features, including additional wetland beneath the bridge, Storm Water Management facilities
Sunnyside Avenue Bridge Replacement Proposed Roadway • Mitigate flooding • Create Green / Complete Street • Create additional wetland beneath the bridge • Create Storm Water Management facilities
Sunnyside Avenue Bridge Replacement Right-of-Way and Environmental Impacts Beltsville Agricultural Research Center (BARC) 2.67 Acres 0.34 Acres Fee Simple Right-of-Way • 2.67 acres Temporary Construction Easement • 0.34 acre Permanent Section 4(f) Use • 3.01 acres (2.67 acres + 0.34 acre)
Sunnyside Avenue Bridge Replacement Right-of-Way and Environmental Impacts Washington Metro Area Transit Authority (WMATA) 0.21 Acre 0.11 Acre Fee Simple Right-of-Way • 0.21 acre Temporary Construction Easement • 0.11 acre
Sunnyside Avenue Bridge Replacement Proposed Bridge
Sunnyside Avenue Bridge Replacement Construction Stage I • Maintain traffic on existing bridge • Construct south portion of new bridge • Construct south portion of approach roadway • Relocate Utilities South Side
Sunnyside Avenue Bridge Replacement Construction Stage II • Shift traffic to the new bridge • Remove the existing bridge • Construct the north portion of new bridge • Construct the north portion of approach roadway South Side North Side
Sunnyside Avenue Bridge Replacement Construction Stage III • Reset the temporary barrier and shift traffic to the • final lanes of new bridge • Construct the sidewalk on the south portion of new bridge North Side South Side
Sunnyside Avenue Bridge Replacement Next Steps Complete Final Design Spring 2013 Right-of-Way Acquisition Fall 2013 Advertise for Construction Fall 2013 Begin Construction Spring 2014 Total Construction Duration 18 Months
Sunnyside Avenue Bridge Replacement QUESTIONS? Prince George’s County DPW&T Project Website: WWW.PRINCEGEORGESCOUNTYMD.GOV/DPWT