1 / 22

Maryland Transportation Builders & Materials Association Paul L. Shank, P.E.,C.M. Chief Engineer

Maryland Transportation Builders & Materials Association Paul L. Shank, P.E.,C.M. Chief Engineer November 14, 2014 October 30, 2014. B/C Connector. Old Concourse C. New Concourse C. Major Projects Old Concourse C Security Checkpoint. Major Projects New Concourse B/C Security Checkpoint.

Download Presentation

Maryland Transportation Builders & Materials Association Paul L. Shank, P.E.,C.M. Chief Engineer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maryland Transportation Builders & Materials Association Paul L. Shank, P.E.,C.M. Chief Engineer November 14, 2014 October 30, 2014

  2. B/C Connector

  3. Old Concourse C

  4. New Concourse C

  5. Major ProjectsOld Concourse C Security Checkpoint

  6. Major ProjectsNew Concourse B/C Security Checkpoint

  7. Major ProjectsNew B/C Connector

  8. Major ProjectsNew B/C Connector

  9. Major ProjectsNew B/C Connector

  10. DE Connector Exterior

  11. Final Upper Level Sterile Corridor for International Arrivals Concession Core New Holdrooms Widened Circulation Corridor Secure side Connector New 8 lane Security Checkpoint

  12. Final Arrival Level Future Outbound Baggage Expansion Future International Baggage Claim Expansion Mechanical Support Spaces

  13. DE Checkpoint – Early Massing Diagram

  14. DE Checkpoint - Final Design

  15. 5- Gate Concourse E Extension – Planning Concept

  16. Overall Program 2011-2015 Runway Safety Areas – 2015 Deadline

  17. Overall Program 2011-2015

  18. Overall Program 2011-2015 • Meet all FAA Runway Safety Area Standards • Long Term Runway Pavement Rehabilitation (20+ Years) • Connecting Taxiways in Concrete at Runway Ends • Concrete Runway Ends • New Hold Aprons (Runway 15R/33L) • NAVAID Replacement • Resolution of FAA Modifications of Standards (MOS) • Taxiways meet Engineering Brief 75 Standards and -13A • Removal of Historic Identified “Hot Spots” • Complete Dual Parallel Taxiway System • Obstruction Removal for Runways 10-28 and 15R-33L

  19. Overall Program 2011-2015 • 52 Design Tasks Completed/Underway • 7 Property Negotiations Completed/Underway • 10 Inter-Governmental/Agency Agreements Executed • 24 Construction Projects Substantially Complete • 2 Construction Projects Underway

  20. Runway 15R Deicing Pad Rehabilitation & Runway 15R-33L RSA, PMP & Standards Project

  21. Upcoming Procurements Construction Management & Inspection Services – Ad 12/14 Est. Value $40M SBP Roadway and Sidewalk at CRCF – Ad 12/14 Est. Value $500k Comprehensive Interior/Exterior Improvements – Ad 1/15 Est. Value $40M Est. Task Range $200k-$5M SBR Comprehensive Interior/Exterior Improvements – Ad 2/15 Est. Value $5M Est. Range $25 – 250k Comprehensive Pavement Marking – Ad 2/15 Est. Value $3M Comprehensive Paving – Ad Fall 2015 Est. Value $20 million Est. Task Range $50k - $5M