1 / 7

Kennedy Boulevard

Kennedy Boulevard. Project Overview Original Design Consultant Termination of Original Design Consultant Current Design Consultant Action Requested. Widening existing 2 lanes road to 4 lanes. Forest City Road to Wymore Road. Kennedy Boulevard. Commission District 2.

shaina
Download Presentation

Kennedy Boulevard

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kennedy Boulevard • Project Overview • Original Design Consultant • Termination of Original Design Consultant • Current Design Consultant • Action Requested

  2. Widening existing 2 lanes road to 4 lanes Forest City Road to Wymore Road Kennedy Boulevard Commission District 2

  3. Original Design Consultant • International Engineering Consultants (IEC) • Began September 1999 • Phase I: Roadway Conceptual Analysis (RCA) – Duration 150 days • Phase II: Final Design – Duration 390 days

  4. Original Design Consultant Issues • Notice of non-performance in June 2004 • After the Cure Notice was issued, County staff reminded the consultant of project issues that needed to be completed, for example: • Delivery of the 100% submittal • Construction plans • Right-of-way documents • Delivery of streetscape proposal • Delivery of minor revisions to the pond 2 detail • Delivery of minor revisions within the Lake Destiny Drive intersection to change fill/slope easements to right-of-way • Delivery of volumes of joint-use pond • Submittal of stormwater permits

  5. Original Design Consultant Issues • Contract ended in September 2006 • Failure to respond to County • Failure to complete the stormwater permit • Failure to complete construction plans • Failure to provide right-of-way documents

  6. Current Design Consultant Kimley Horn Associates • June 2007 - Continuing Design Contract • Finalize the environmental permit • Redesign the road adjacent to the radio tower near the western end of the project • Prepare all necessary documents for a Design-Build project • Budgetary restraints require completion of design phase • Right-of-way & construction phases based on funding

  7. Action Requested • Approve Sole Source Contract with Kimley-Horn Associates, Inc. for Final Engineering Design Services in the amount of $315,942.78 and issuance of a Purchase Order for $50,000.

More Related