1 / 38

Cost and Time Value of $$

Cost and Time Value of $$. Prof. Eric Suuberg ENGINEERING 90. Cost and Time Value Lecture. What is our goal? To gain an understanding of what is and what is not a good project to undertake from a financial point of view. What are our tools? Material presented by Prof. Crawford

shanta
Download Presentation

Cost and Time Value of $$

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost and Time Value of $$ Prof. Eric Suuberg ENGINEERING 90

  2. Cost and Time Value Lecture • What is our goal? • To gain an understanding of what is and what is not a good project to undertake from a financial point of view. • What are our tools? • Material presented by Prof. Crawford • Discounting / Time Value of Money • Tax Savings through Depreciation

  3. So, what are we starting today? • Go through some of the “fun” math for Present Value Calculations • Do a teaching example of purchasing a machine for a manufacturing plant • Talk about costs – both the obvious kind as well as the non-obvious types • Time value of money calculations • Cost Comparisons • Depreciation • Put it all together – inc. continuous discounting and after-tax cost comparisons

  4. Have I Got a Deal for You • Would you be interested in investing in a company that has $1 million in annual sales?

  5. What More Would You Like to Know? • Annual operating expenses (salaries, raw materials, etc.) • Suppose these were $900,000/yr • Are you interested? (Come on - I’ve got to know now. There are a lot of people interested)

  6. Profit Profit = Sales (revenues) - expenses (costs) • Basis for taxation - What goes into the calculation is of great interest to Uncle Sam

  7. In Our Example • Profit = $1,000,000/yr - $900,000/yr = $100,000/yr • Is this a good business?

  8. What Would You be Willing to Pay Me for this Business? • $1 million? $2 million? • How do you decide? • This is one of the questions that we will answer in this part of the course.

  9. Present Value Calculations • Essential element of evaluating a business opportunity • Different variants • Simple discounting • Replacement and abandonment • Venture Worth, Present Value, Discounted Cash Flow Rate of Return

  10. Information Required What information do we need? • Investment (Capital assets, working capital) • Lifetime and Salvage Values • Operating Costs • Fixed • Variable • Interest Rate • Tax Rate • Depreciation Method • Revenues

  11. Capital Investment - Facility • Purchased Process Equipment • Field Constructed Equipment • Wiring, Piping, Instrumentation • Construction, Installation Costs • Site Preparation, Buildings • Storage Areas • Utilities • Services (Cafeterias, Parking lots, etc.) • Contingency

  12. Capital Investment- Manufacturing • Costs of process equipment may represent only 25% of actual investment! • Costs of process equipment scale according to the “six-tenths rule” • C2/C1 = (Q2/Q1)0.6 • See, for example: • “Cost and Optimization Engineering” by F.C. Jelen and J.H. Black, McGraw-Hill, 1983.

  13. Other Items • Working Capital • Raw materials and supplies inventory • Finished goods in stock and Work in Progress • Accounts Receivable, Taxes payable • Operating Costs • Labor and Raw Materials • Utilities and Maintenance • Royalties • Fixed Costs • Insurance, rent, debt service, some taxes

  14. Time Value of Money • $1 today is more valuable than the promise of $1 tomorrow • Has nothing to do with inflation • “Discounting” is the term used to describe the process of correcting for the reduced value of future payments • Discount rate is the return that can be earned on capital invested today

  15. Future Worth of an Investment • P = Principal • i = Annual Interest Rate • S = Future value of investment Compound Interest Law S1 = P (1+i) at the end of one year S2 = S1(1+i) = P(1+i)2 at end of year 2 Sn = P (1+i)n at end of year n

  16. Present Value of a Future Amount P = Sn / (1 + i)n = Sn (1 + i)-n (1 + i)-n = Present Value Factor or Discount Factor The promise of $1 million at a time 50 years in the future @ i = 15%/yr P = $1,000,000(1+0.15)-50 = $923

  17. Simple Example • What is the PV of $10.00 today if I promise to give it to you in fifteen years, given a discount rate of 20%? • PV = 10(1.20)-15 • = $.65 • Not enough to buy a soda these days

  18. Take Home Message • Not all dollars of profit are the same • Those that come earlier are “worth” more

  19. Start with Simple Example from Everyday Life • Do you buy the better made equipment with the higher price tag? or the low first cost equipment that has high maintenance?

  20. Cost Comparisons What are we doing here? • Comparing one project to another • Deciding to buy the expensive computer that has free maintenance versus the cheap one that makes you pay for service vs.

  21. Simple Cost Comparisons • Strategy • Reduce costs (and/or revenues) to a common instant, usually the present time • Work on full year periods • approximate costs or revenues which occur over the year as single year-end amounts • Basic Rule: All comparisons must be performed on an equal time period basis

  22. Unequal Lifetime Cost Comparisons • Repeatability Assumption (to get to same time basis) • Annuity Comparison • Co-termination assumption

  23. x x x x x x x x 1 (m-1) 2 m 3 4 5 6 0 x = annuity First Some Useful Mathematical Machinery • Uniform periodic annual payments (annuities) • Projects frequently generate recurring income or cost streams on an annual basis

  24. Discounting a Series of Payments

  25. Discounting a Series of Payments con’t

  26. Capital Recovery Factor

  27. Future Equivalents of Annuities Link to summary of useful formulae

  28. Examples • What future payment N years from now shall I accept in return for an investment of $P now, given I could instead invest my money elsewhere (e.g. a bank) and earn i %/yr? • What set of annual revenues for N years will entice me to invest $P, given the same alternative as above?

  29. Examples • What price should I pay for an investment which returns $X/yr for N years, if i %/yr is available to me in a bank? • What annual interest rate (bank, etc.) would be required to make an investment returning $S in N years on a present investment of $P?

  30. A Simple Replacement Problem • Process to be operated for 4 years and then junked • Do you buy a new low-maintenance machine now or not??? DATA (neglect tax effects) Options Stick w/old Buy newPurchase Price ($) 0 4000Operating Cost ($/yr) 2000 500Lifetime (yrs) 4 4

  31. 0 3 4 2 1 $2000 $2000 $2000 $2000 Cash Flow Time Lines OLD NEW 0 3 4 2 1 $4000 $500 $500 $500 $500

  32. If management demands i = 20 %/yrPold=$5180, Pnew=$5295 old is better choice The Key Role of Interest Rates • If management demands i = 10 %/yrPold=$6340, Pnew=$5585 new is better choice

  33. Note • In a replacement problem like this you could have added revenues to the analysis, but no need to do so if they are the same for both options.

  34. Financial Comparisons with Unequal Lifetimes • Simple Example: Choose between 2 pieces of equipment, one of which is better built and has a longer lifetime • N is not the same for both • Not a fair comparison with N=2 unless process is to be shut down and both options have no residual value 20 year life Well Built Poorly Built 2 year life

  35. Poorly Built 2 year life What to Do? • Option 1 - Repeatability Well Built 20 year life (Buy 1) (Buy 10)

  36. Alternative 1 Alternative 2 Purchase Price ($) 10,000 20,000 Annual Op. Cost ($/yr) 1500 1000 1000 Salvage Value ($) 500 3 Service Life (yrs) 2 Option 2 - Annualized Costs • Convert the investment and maintenance for both options into a single annual payment i = 0.15 / yr

  37. Annualized Cost of Alternative 1 Now =

  38. Annualized Cost of Alternative 2 1000 = 0 0 3 2 1 2 1 3 20,000 1000 1000 1000 9472 9472 9472 In this case, choose alternative 1 because yearly cost is lower.