Modeling of profitability increase of a deinking plant Harald Janisch
Agenda • Introduction of Norske Skog Bruck • Goals of the diploma thesis • Mill balance in FlowMac • Modeling of profitability increase of a deinking plant Harald Janisch
Agenda • Introduction of Norske Skog Bruck • Goals of the diploma thesis • Mill balance in FlowMac • Modeling of profitability increase of a deinking plant Harald Janisch
Machines PM 3 PM 4 Width (cm) 530 645 Quality Newsprint LWC and MWC Grades 42 – 49 g/m² 51 – 90 g/m² Production capacity 130.000 t/a 280.000 t/a Pulp lines DIP 1 DIP 2 Wood line PGW PGW Norske Skog Bruck Employees (31.12.07): 505 Harald Janisch
Agenda • Introduction of Norske Skog Bruck • Goals of the diploma thesis • Mill balance in FlowMac • Modeling of profitability increase of a deinking plant Harald Janisch
Goals of the diploma thesis • Creating of a complete fiber and water balance of the whole paper mill • Mill balance in FlowMac • Modeling of profitability increase on the DIP 1 Harald Janisch
Agenda • Introduction of Norske Skog Bruck • Goals of the diploma thesis • Mill balance in FlowMac • Modeling of profitability increase of a deinking plant Harald Janisch
Mill balance in FlowMac Harald Janisch
Modeling DIP 1 – pulping and HD cleaning Harald Janisch
Modeling DIP 1 – screening Harald Janisch
Modeling DIP 1 – flotation Harald Janisch
Modeling DIP 1 – thickening Harald Janisch
Modeling DIP 1 – pulp storage Harald Janisch
Modeling DIP 1 – filtrate storage Harald Janisch
Agenda • Introduction of Norske Skog Bruck • Goals of the diploma thesis • Mill balance in FlowMac • Modeling of profitability increase of a deinking plant Harald Janisch
Profitability increase DIP 1 Background • Increase capacity on PM 3 • Increase share of recovered fiber on PM 3 • Save energy costs on PGW Harald Janisch
Profitability increase DIP 1 Goals • Finding the main bottlenecks on DIP 1 • Modeling of profitability increase on DIP 1 • Modeling of capacity increase on DIP 1 • Increase capacity from 270 t/d to 300 t/d Harald Janisch
Thickening DIP 1 – process old Harald Janisch
Thickening DIP 1 – new thickener 70 t/d Harald Janisch
Thickening DIP 1 – new disc filter 90 t/d Harald Janisch
Thickening DIP 1 – new disc filter 150 t/d Harald Janisch
White water PM 3 White water PM 3 Recovered paper Pulp to PM 3 Pulping HD Cleaning Screening Flotation Thickening Reject Reject Reject Reject Volume flows DIP 1 Harald Janisch
Profitability increase DIP 1 Improved filtrate consistency Harald Janisch
Modeling capacity increase DIP 1 Summary: • A complete balance for fiber, water and temperature was built for the whole mill. • First analysis for optimization on DIP 1 • 8 hours modeling work for different scenarios to increase profitability on DIP 1. • 20 minutes for the management to understand the problem and decide to do the investment. Harald Janisch