An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SED – Risk Assessment and Safety Advisory (RASA) Compliance Plan Workshop R.15-01-008/D.17-06-015 SB 1371 (Leno). Natural Gas: Leakage Abatement April 19, 2018

  2. Practical Information WiFi Access: SSID: cpucguestUser: guestPassword: will provide Restrooms: out the Auditorium doors and down the far end of the hallway. Call in information: • Phone line: 1-866-859-2737Participant code: 1682922 WebEx: • Meeting Number: 713 154 785 • Password: Safe2018!

  3. Safety and Emergency Information • In the event of an emergency, please proceed calmly out the exits. • The Evacuation Location is the courtyard between the War Memorial Building and Opera House. • It is located on the other side of City Hall. Exit the building at Van Ness and McAlister streets and walk past City Hall.

  4. Agenda • 9:30-9:15 Welcome and Agenda Review • 9:15-9:45 Compliance Plan Review Update – RASA • 9:45-10:00 Advice Letter Approval Update • 10:00-10:20 CARB Update on Social Cost of Carbon • 10:20 Break • 10:30-11:30 SEMPRA Plan Overview and Highlights • 11:30 -11:45 SEMPRA Pilot/R&D Programs • 12:00 Lunch Break

  5. Agenda - continued • 1:00-2:00 PG&E Plan Overview and Highlights • 2:15-2:30 PG&E Pilot/R&D Programs • 2:30-3:00 Southwest Gas Plan Overview and Highlights • 3:00 Break • 3:10-3:30 CUE and EDF Joint Comments on the Plans • 3:30 Open for general discussion • 4:30 Adjourn

  6. Plan Review Update • Plans Received on March 15 • RASA and CARB jointly reviewing plans • Reviews completed NLT June 30 • Priority given to Advice Letter filers • Review Letters • Will approve plan or require revisions • RASA will advise Energy Division

  7. Plan Evaluation • Completeness • All 26 BP’s addressed in some way • Innovation • Cost and Reduction Estimates • Are estimates provided for major programs? • Do any programs appear excessively costly? • RASA may request revisions

  8. Initial Impressions • Good response overall • Considering first time ever • SEMPRA’s summary table very good • Most filers followed the template • Thank you! • Emission reduction estimates very useful • Good R&D/Pilot Descriptions

  9. Reduction Estimates, MSCF

  10. Reductions by BP

  11. Reductions by BP

  12. Some Innovations • Capture blowdowns with CNG Truck • Focus on Super-Emitter Leaks • Risk-Based annual leak survey • In lieu of 3-year survey everywhere

  13. Concerns • Reduction and cost estimates missing for some plans • Perhaps review of other plans may help fill in these gaps

  14. Lessons Learned • Some BP’s just don’t apply for the smaller utilities – no high pressure, etc. • Template format becomes redundant when same answers apply for many BP’s • Appendices/Attachments should have a standard location across all plans