Analysis of the grid access barriers

Analysis of the grid access barriers. Emilien Simonot , Technical Department. 08/07/2010. Directive 2009/28/CE , article 16: “Access to & Operation of the grids”. Responsibility of the MS for guaranteeing the connection of the RES: Development of transmission and distribution grids.

Download Presentation

Analysis of the grid access barriers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Analysis of the grid access barriers Emilien Simonot, Technical Department 08/07/2010

  2. Directive 2009/28/CE , article 16: “Access to & Operation of the grids” • Responsibility of the MS for guaranteeing the connection of the RES: • Development of transmission and distribution grids. • Access (priority of access) for RES. • Dispatching priority – Justification of curtailments.

  3. Directive 2009/28/CE , article 16: “Access to & Operation of the grids” • Responsibility of the MS for guaranteeing the connection of the RES: • Actions to be taken: • Define and make public the rules & costs for connection. • Define how connection costs are shared between developers and TSOs/DSOs. • Give access to estimate connection costs, procedure timeframe & connection deadline.

  4. Directive 2009/28/CE , article 16: “Access to & Operation of the grids” • Responsibility of the MS for guaranteeing the connection of the RES. • Actions to be taken. 3 FUNDAMENTAL CONCEPTS OBJECTIVITY TRANSPARENCY NON-DISCRIMINATION

  5. Schematic overall procedure 2. Building consent 3. Construction of the wind farm 1. Investment decision 6.Productive wind farm 4. Grid access consent 5. Physical grid access Lead time

  6. Schematic grid access procedure Wind Farm Basic Technical Project Request for Connection Point (Bank Guarantee) Wind Farm Developer Evaluation Pcc Assignment & Access DSO + Technical requirements to connection If not enough grid capacity FINAL TECHNICAL PROJECT TSO APPROVAL Evaluation + Connection & access contract Connection of the wind farm

  7. There are obstacles and unknowns along the way… • Who shall I contact? • When shall I contact to get my authorization in time? • How much will it cost? Shall I support this cost myself? • Where can I connect my wind farm? • Where can I built my evacuation line? • What are the connection requirements?

  8. The grid access process is not the critical factor…

  9. … Even if it is sometime unpredictable…

  10. … And where there is enough grid capacity. Insufficient grid capacity is reported to be responsible for projects to get stuck by almost 60% of the developers. Main reasons for project to get stopped

  11. … Where there is enough grid capacity. Lack of grid capacity X X X X X X X X X X

  12. Evacuation lines projects, a social challenge… • Especially in southern European countries: • Spain, up to 209 people • Portugal, up to 105 people • Italy, up to 90 people

  13. … With consequences. Main reasons for project to get stuck Changes in cable routes are reported to be a cause for projects to get stopped by almost 20% of the developers at EU level. (Reaching more then 50 % in some countries).

  14. Experience can be gained, from emerging markets to developed markets… Decision making process is more transparent Deadlines? Costs decrease Lead times decrease

  15. … and new problematic can raise. • In spite of being the second EU market, Spain presents one of the highest grid access lead time explained by • Overload of the system operators treatment capacity. • Grid capacity sold out.

  16. What could be done? (1/2) • Make public the information on the grid characteristics: • To carry out access capacity studies by wind developers • To propose technical and managements solutions which allow to increase the grid capacity • To establish a realistic calendar for the connection of the installations. • More transparency in the decision making as well as to avoid asymmetrical treatment between companies. • Infrastructure Plans for the construction and reinforcement of lines should be realistic and fulfilled. Developers could be able to give financial support. • Avoid to much request at the same node.

  17. What could be done? (2/2) • Implement coordination between distribution and transmission companies (for execution of new infrastructure as well as in the flow of information on connection requests and for the operation of wind farms) • Grid codes have to be realistic, coherent with the state of the art of the technology and never retroactively applied. It is important to make an effort of harmonization at EU level. • Infrastructure for wind farms interconnection should be of public interest and land occupation should be facilitated, creating the adequate economic compensations for the land owners. • Give possibility to the developers to get involved in the financing of grid reinforcements.

  18. Thank you for your attention Emilien Simonot, Technical Department Spanish Wind Energy Association esimonot@aeeolica.org