220 likes | 291 Views
Access to Intermodal Supply Chain Networks Igoumenitsa’s Case. Konstantinos Grinias Development Director. TEN-T Core Network. The Core Network will: connect 83 major European Ports. connect 37 major European Airports. include 15.000 km high speed rail network .
E N D
Access to Intermodal Supply Chain Networks Igoumenitsa’s Case KonstantinosGrinias Development Director
TEN-T Core Network The Core Network will: • connect 83 major European Ports. • connect 37 major European Airports. • include 15.000 km high speed rail network. • include 35 major cross-border projects to reduce traffic congestion. • include 4 Greek ports (Pireaus, Thessaloniki, Igoumenitsa, Patras)
Demand flows in the area (2015) – “Elaboration of the East Mediterranean Motorways of the Sea Master plan”
Estimated Maritime flows (2015) “Elaboration of the East Mediterranean Motorways of the Sea Master plan”
EAST MED Intermodal Corridors “Elaboration of the East Mediterranean Motorways of the Sea Master plan” • The maritime-based corridors: • The Black Sea Eurasian land-bridge corridor • The Black Sea-Aegean North-South corridor • The Adriatic-Ionian corridor • The North Africa-Europe corridor • The North Africa- Middle East corridor • The Middle East- Europe corridor
Port Clusters “Elaboration of the East Mediterranean Motorways of the Sea Master plan”
Existing maritime links between catchment areas of Ionian Sea& North Adriatic ports clusters
Igoumenitsa – Shangai(United Nations Economic Commission for EuropeEconomic & Social Commission for Asia & the Pacific)
EgnatiaOdos Transport Corridor ROMANIA Black Sea BULGARIA FYROM Adriatic Sea ALBANIA TURKEY
EgnatiaOdos Transport Corridor Pan European Road Network System K. GRINIAS
E-65 Transport Corridor Motorway of Central Greece
The Port Phase A’ 1 Port Land area: 130,000 m2 2 Land Area: 80,000 m2 3 Twelve (12) piers 7 4 6 5 Berth Length: 781 m Canal: 1,500 m length - width 100 m - depth 10 m Fire Station Building: 612 m2 Central Passengers Terminal Building: 6,326 m2 PHASE A’ INFRASTRUCTURES
The Port Phase A’ 1 Port Land area: 118,000 m2 2 One (1) finger pier 197.6 m length 3 New pier: berth 371 m length / 10.20 m depth 4 5 6 Canal: length 1,700 m / width 170 m / depth 10.5 m Passengers Terminal 2nd Building : 3,040 m2 Passengers Terminal 3rd Building (Extra Schengen): 2,324 m2 Phase B’ (Under Construction) PHASE B’ INFRASTRUCTURES
The Port PHASE B’ PHASE A’ 1 Two (2) berths for Ro-Ro/Ro-Pax ships 2 Two (2) Finger piers 198 m each 3 One (1) berth for Railway connection (Ra-Ra)93 m 4 5 One (1) cargo terminal 2,013 m2 Total Land Area: 90,000 m2 PHASE C’ PHASE C’ INFRASTRUCTURES
C’ Phase Future Investments Domestic Destinations Port Old Port B’ Phase Construction Works New Port (Phase A’) B’ Phase Construction Works The Port Of Igoumenitsa • Egnatia Odos Motorway