1 / 35

Computer Associates International, Regional Office

Computer Associates International, Regional Office. Herndon, VA. Seth R. Takoch AE Senior Thesis. Structural Option April 15, 2003. Presentation Outline. Background Information Existing Structural Conditions Design Criteria Redesign Construction Management Lighting Design

shiri
Download Presentation

Computer Associates International, Regional Office

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Computer Associates International, Regional Office Herndon, VA Seth R. Takoch AE Senior Thesis Structural Option April 15, 2003

  2. Presentation Outline • Background Information • Existing Structural Conditions • Design Criteria • Redesign • Construction Management • Lighting Design • Conclusions and Recommendation • Acknowledgements SETH R. TAKOCH STRUCTURAL OPTION

  3. Location • 15min. Off Beltway • 35mins. Outside D.C • Wood Oak Dr. • Baseball Field

  4. Background Information • Function: Computer Associates Int. Regional Headquarters • Size: 233,000 sq. ft. – 6 floors • Rentable Office Space: 207,000 sq. ft. • Architectural Features: • Precast Concrete Façade with Glass Curtain Wall • Six Story Glass Enclosed Atrium • Adjacent Day Care Facility

  5. Project Team • Owner – Computer Associates International • Arcitect – Davis, Carter, Scott • Structural Engineer – Smislova, Kehnemui, & Associates. • General Contractor – Clark Construction • Developer – Tishman Speyer Properties • Mechanical – GHT Limited • Plumbing – GHT Limited

  6. Existing Structure • Flat Slab Construction • Concrete Structure • 30’ x 30’ Bays • 9” Thick Slab Thickness • 10’ x 10’ x 5-1/2” Drop Panels • 24” x 24” Conc. Columns

  7. Existing Structure • Wind Loads are Transferred by Diaphragm Action of Façade • Transferred to Framing by Tributary Area • 8 Frames N-S and 9 Frames E-W • Concrete Frames Resist Lateral Forces • Short and Long Frames • Floor Slab Adds Resistance due to Diaphragm Action

  8. Design Limitations • Old Code – BOCA 96 • New Code – IBC 2000 • Local Zoning Ordinances • Similar Square Footage • Minimal Architectural Changes • Floor-to-Floor Heights

  9. Proposal • To Redesign a Feasible and Desirable Alternative Structural System and to Incorporate Construction Costs and Schedule Length Into My Solution Time = Money … Money = Time $$$$

  10. Possible Faming Alternatives • Composite Steel Construction • Non-Composite Steel Construction

  11. Steel Construction • Code – IBC2000 • LRFD Analysis • Parameters • 30’ x30’ Typical Bays • Fy = 50ksi ASTM A992 Steel • F’c = 3ksi • Normal Weight Concrete • Shear Studs - 3-1/2”high, ¾” diameter (composite) • 22 gage Metal Deck

  12. Composite Steel Construction • Gravity Analysis – RAM • Determined Beam Sizes • Determined Column Sizes • 2 Story Column Lengths 26’ – 28’ Tall • Ranging from W10’s to W12’s • Beam Sizes W12x14 Spaced at 6’ o.c. • Girders as Deep as a W21’s

  13. Non-Composite Construction • Gravity Analysis – RAM • Determined Beam Sizes • Determined Column Sizes • 2 Story Column Lengths 26’ – 28’ Tall • Using W12’s • Beam Sizes W12x14 Spaced at 6’ o.c. • Girders as Deep as a W24’s

  14. Depth Comparison • Composite Steel • Average – W12’s • Critical Depth – W21 Composite Saves 20 Tons of Steel • Non-Composite Steel • Average – W12’s • Critical Depth – W24 • Advantage – Composite Steel Construction

  15. Lateral System • Shear Wall to Resist Lateral Loading • Based on Critical Wind Loading and Torsion • 2 – 60’ Long Shear Walls • Reinforced to Resist Forces • Deflection of h/400

  16. Design • Reinforcement Based on the Following • Vn =  (2f’c bd + Avfyvd/s) • Mn = Asfy (d-a/2)

  17. Construction Management ` • Address Two Main Issues • Cost Comparison • Project Duration

  18. Construction Management ` • Total Building Cost • D4 Cost • Total = $27,678,667 • 20-25% Accurate • Range of $34.6 million to $20.8 million • Not Very Accurate • $115.33 / sq. ft.

  19. Construction Management ` • Total Building Cost • Means Building Construction Cost Data • Separate Estimates for Steel and Concrete • 10 -15% Accurate • More Precise Than D4 • Steel Framing = $96.74 / sq.ft. • Concrete Frame = $98.45 / sq.ft. • Difference = $1.71 / sq.ft. = $410,400

  20. Construction Management ` • Cost Comparison • D4 Cost = $115.33/sq.ft. = $27,678,667 • Means Steel = $96.74/sq.ft. = $23,217,600 • Means Concrete = $98.45/sq.ft. = $23,628,000 • Percentage Savings Using Steel = 1.7% Savings

  21. Construction Management ` • Scheduling • Means Data to Calculate Duration • Primavera Utilized to Schedule Sequences • Total Duration Steel Erection = 376days • Total Duration Concrete Placement = 847 days

  22. Construction Management ` After Scheduling Concrete – 260 Days

  23. Construction Management ` After Scheduling – 150 Days

  24. Construction Management ` • Savings • Advantage Composite Steel Construction • Time • Advantage Composite Steel Construction • Composite Design is Considered One of the Most Economical Methods of Floor Construction for an Office Building

  25. Construction Management ` • Crane Sizing • On Site 3-1/2 Months • Tower Crane • Placed Through Atrium • Liebherr 200HC • Hook Radius – 197ft. • Capacity – 5,070# • Satisfies Critical Lift of 3,000# @160ft.

  26. Lighting Design • Design of Lighting of Daycare Facility • Minimum Footcandles of 30fc • Fluorescent Luminaries • 120’ x 56’ Space to Illuminate • 2’ x 4’ Fixtures with 3” Louvers Spaced on a 16’ x 8’ grid • Specification From Lithonia • Workplane of 2-1/2 ft.

  27. Lighting Design • Designed Using Luxicon • Renderings on April 15, 2003 • At 9:00 am with Daylighting • At 1:30 pm with Daylighting • At 5:00 pm with Daylighting • Without Daylighting

  28. Lighting Design • 9:00 am

  29. Lighting Design • At 1:30 pm

  30. Lighting Design • At 5:00 pm

  31. Lighting Design • Without Daylighting

  32. Lighting Design • The Lighting Design Meets Required Parameters of 30fc

  33. Conclusion • In Conclusion, Composite Steel Construction is a Better Alternative to Non-Composite Construction. • Composite Steel is a Viable Alternative to a Two-Way Flat Slab System

  34. Shout Outs’ My Family My Friends The AE Student Body The Entire AE Faculity Smislova, Kehnemui, & Associates, P.A. Computer Associates The ‘U’ And All Of Those Out There That Stuck With Me

  35. Questions ?

More Related