Pandora’s Box Project Epimetheus Proposal

Pandora’s Box Project Epimetheus Proposal. Charles Bogenberger- team manager Michael Curl- electrician and systems integration Nicole Demandante- O3 sensor David – camera and structure Lisa Rowan- Budget, schedule, and organization Juhyun Lee- graphics and videography

Download Presentation

Pandora’s Box Project Epimetheus Proposal

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pandora’s BoxProject Epimetheus Proposal • Charles Bogenberger- team manager • Michael Curl- electrician and systems integration • Nicole Demandante- O3 sensor • David – camera and structure • Lisa Rowan- Budget, schedule, and organization • Juhyun Lee- graphics and videography • Aleks Jarosz- accelerometer and structure

  2. Structural Redesign • Design • Changed from cube to rectangular • Shape redesigned around camera • Cut out for mirrors • Better imaging of earth and balloon • Protects mirrors • Better positioning of camera • Allows for more imaging options • Improved impact absorption and structural strength

  3. Parts and Components Status • Have all major components • Having to spend more on miscellaneous parts • O3 Sensor • Three out of four chemicals here fourth one on its way • Chemicals took longer to get. • This experiment will be practically impossible to test. • Force sensor • Accelerometer not feasible • Will probably use home made device

  4. Stair Pitch Test • No critical damage done • Performed several tests: • Pitched downward from 1 story • Pitched up to a height of 3 stories and freefall • New Design showed improved impact absorption • Major damage was to corners • Overall structurally sound

  5. Cold Test • Attempted Cold Test on Sunday 2/11/03 • Status: INCOMPLETE • HOBO failed • Timing Circuit failed • All other components were functioning • Cold test will be re-done ASAP depending on diagnosis • Parts may need to be re-ordered • Projected re-evaluation on Sat.

  6. Budget

  7. Timeline • November 3 Launch Readiness Review #1 • November 4 Assessment of Launch Readiness • November 17 Modifications completed for Launch Readiness Review #2 • November 19 Launch Readiness Review #2 • November 20 2nd round modifications completed • November 22 Launch Day • November 25 Prepare Final Report and Presentation • December 4 Complete Final Report and Presentations • December 6 ITLL Design Expo • December 8 Final Reports and Team Presentations

  8. Questions?