1 / 58

Techno-economic aspects of power systems

Techno-economic aspects of power systems. Ronnie Belmans Stijn Cole Dirk Van Hertem. Overview. Lesson 1: Liberalization Lesson 2: Players, Functions and Tasks Lesson 3: Markets Lesson 4: Present generation park Lesson 5: Future generation park Lesson 6: Introduction to power systems

skyla
Download Presentation

Techno-economic aspects of power systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Techno-economic aspects of power systems Ronnie Belmans Stijn Cole Dirk Van Hertem

  2. Overview • Lesson 1: Liberalization • Lesson 2: Players, Functions and Tasks • Lesson 3: Markets • Lesson 4: Present generation park • Lesson 5: Future generation park • Lesson 6: Introduction to power systems • Lesson 7: Power system analysis and control • Lesson 8: Power system dynamics and security • Lesson 9: Future grid technologies: FACTS and HVDC • Lesson 10: Distributed generation

  3. OutlineIntroduction to power systems • Power systems • Grid structure • Grid elements • New investments in the grid • Tasks of the TSO • Grid operation issues

  4. The grid of today • Transmission network • To transport the electric power from the point of generation to the load centers • All above a certain voltage • (Subtransmission) • Distribution network • To distribute the electric power among the consumers • Below a certain voltage

  5. Structure of the power gridWhat’s the difference? • Transmission system • Higher voltage (typical at least 110 kV and higher) • Power injection by generation and import, large consumers • Interconnected internationally • Meshed nature-Redundancy • (Subtransmission system) • Between transmission system and distribution system • Connection of large industrial users and cities • Open loop/partly meshed • Distribution system • 400 V to some ten of kV • Industry, commercial and residential areas • Radial

  6. Industrial network (Haasrode) • Transformer: 70 kV/10kV, 20 MVA

  7. UCTE

  8. Example: Map of the Iberian transmission system

  9. Transport of electric power • Electric power P [MW] • Alternating current S [MVA] • Two ways to increase the transported power • Increase current I • Larger conductor cross-section • Increase voltage U • More insulation • Two ways to transport electricity • Alternating current (AC) • Direct current (DC) P or S = U * I

  10. Problem faced by electricity pioneers AC or DC? • Direct Current DC • Generator built by W. von Siemens and Z.Gramme • Low line voltage, and consequently limitation to size of the system • Alternating current AC • Introduced by Nikola Tesla and Westinghouse • Transformer invented by Tesla allows increasing the line voltage • Allows transmitting large amounts of electricity over long distances

  11. Transformer

  12. AC transmission system • Frequency of 50 or 60Hz • Current changes direction 100 or 120 times a sec • Active AND reactive power in the same line • 3 phase system • Line voltages can be easily and economically transformed up and down • AC current does not use the whole conductor • Skin effect • AC conductors have larger diameters than adequate DC

  13. Switchyard

  14. DC transmission system • Only active power • Current flows in one direction • Conductor cross-sections fully used • Low transmission losses • Requires DC-AC converters to control the voltage level • Expensive • Switching of higher voltage DC more difficult

  15. AC vs DC • Advantages of AC • Cheaper transformation between voltages • Easy to switch off • Less equipment needed • Known and reliable technology • More economical in general • Rotating field • Advantages of DC • Long distance transmission • Higher investment costs offset by lower losses • on 1000 km line, 5% for DC opposed to 20% for AC • Undersea and underground transmission • No reactive power problem • Connection of separate power systems • With different frequencies (Japan,South-America) • Different control area, i.e. UCTE with Nordel and UK

  16. Cost of transmission linefunction of voltage level

  17. Lines and cables • Overhead transmission lines • Economical • However, visual pollution • Widely used in transmission over large distances • Underground cables • More expensive than lines • 5 to 25 times higher capital costs for 380kV • Underground, thus invisible to the public • Ground above the cable can be still used • However, maintenance costs are significant • Widely used in urban areas

  18. Overhead line

  19. Evaluation: different points of view Technical Economical Regulatory Environmental Transmission capacity upgrade • AC overhead • New line • Refurbishing • New conductor types • AC underground • Conventional cables • GILs • HTS

  20. Overhead AC transmissionNew line • Advantages • Widely used in transmission over large distances • Most economical (especially in rural areas) • Well-known technology Best choice from techno-economic point of view Classic approach to network reinforcement

  21. Overhead AC transmissionNew line • Environmental aspects • Visual impact • Vegetation • Population • Town planning • Cultural heritage • Natural site and landscape

  22. Overhead AC transmissionNew line • Social and political issues • Concern about health effects • Not popular → heavy resistance • NIMBY • NIMTO • BANANA • CAVE • NOPE • Regulatory • Permit process up to 15 years

  23. Overhead AC transmissionNew line Conclusion • Best from techno-economic point of view • Worst from environmental, social & political point of view • Very difficult to construct new lines in industrialized countries  alternatives needed!

  24. Overhead AC transmission Adding/replacing conductors • Increased ampacity • Without supplementary environmental impact • Within existing right-of-way • Equip second circuit • No new towers needed  cost effective • Heavier conductors • Tower and foundation modifications may be needed → very high cost  new conductor types

  25. Overhead AC transmissionNew conductor types • Material properties • Composite core • Surrounded by aluminium(-zirconium) • Increased strenght and reduced weight • Increased ampacity • Economics • Significantly higher cost • No tower modifications needed • Regulatory • Outdated standards state maximum conductor temperature independent of conductor type • Other drawbacks • New technology → limited experience e.g.: no data on expected lifetime available • Higher operating temp  losses increase

  26. AC cables • AC cables vs. overhead lines • Technical • Almost no maintenance needed • Repair more difficult • Technical difficulties at high voltages • Limited distance • Economical • 5 to 25 times higher capital costs (€/MVA) • Although cost differences have narrowed • Repair costs are significant

  27. AC cables • AC cables vs. overhead lines • Environmental • Invisibility • Dangers: oil spill, poisonous SF6 arcing by-products • Social & political • Less right-of-way needed • Permitting takes less time • Less concern for health risks (although electromagnetic fields are higher) • Ground above the cable can still be used • Widely used in urban areas

  28. AC cables • Classic • Paper insulated, oil-filled • XLPE • New types • Higher voltages • Lower losses • More expensive

  29. AC CablesNew types • Gas Insulated Cables (SF6) • Higher voltages due to better insulation • Suited to bulk transmission • C lower  suitable for long distances • Complex placement (many joints) • Arcing by-products hazardous for environment • Considered for future tunnel connections (e.g. in the Alps) • Temperature protection • Operating very close to limits • Belgium: Tihange - Avernas

  30. AC CablesNew types • High Temperature Superconducting • No conduction losses at cryogenic temperatures • Cooling losses • Cooling and cooling equipment expensive • Reduced dimensions • Environmentally friendly • Could prove economic for specific cases • R&D needed

  31. AC cables vs DC cables Source: ABB

  32. Cables

  33. Tasks of the TSO • Transmission System Operator TSO • Operates the grid • Constant monitoring of system conditions • Frequency control (active power) • Voltage management (reactive power) • Administrates the settlement of unbalances • Access Responsible Parties (ARP) need to balance their productions and consumption • TSO takes actions if ARP deviates from the schedule • TSO charges the ARP for the incurred costs “To keep the lights on”

  34. ~ ~ ~ ARP Production Import/ Export Grids ARP1 ARPN I/E I/E Consumer

  35. Frequency control

  36. Tasks of the TSO • Frequency control • Primary frequency control • Compensate for short-term unbalances at local level • Stabilize frequency within acceptable range around set point • Secondary and tertiary frequency control • Control the load-generation balance at the programmed export-import • Contribute to bringing the frequency back to its set point • Relieve the primary control reserve after an incident • Scheduled (set point) frequency (time control) • Laufenburg control centre in Switzerland • To account for the Synchronous Time deviations • 50.01 or 49.99 Hz for the whole day

  37. Tasks of the TSO • Reactive power management and voltage control • Primary voltage control • Excitation of generators • Capacitors • SVCs (Static Var Compensators) • Secondary voltage control • Zonal coordination of the voltage and reactive power control • Maintains the required voltage level at a key node • Tertiary voltage control • Optimization of the reactive power distribution • Based on real-time measurements • Device settings adjustment

  38. Tasks of the TSO • Constant monitoring of system conditions • State estimation • To get best possible picture of system conditions • Find a best-fit load flow • Based on metered values (imperfect measurements) • Contingency analysis • N-1 security rule • One accident cannot bring the system in danger • Redundancy

  39. From national to international grid

  40. Synchronous areas in Europe • UCTE • Established in 1951 as UCPTE, 9 control zones, currently 27 • 23 countries, 33 TSOs, 620 GW installed capacity, 295 TWh exchanges • Full synchronous operation of its members in 1958 • absorbed many “smaller” initiatives along the way • CENTREL, SUDEL, COMELEC • 450 mln. people, annual electricity consumption 2500 TWh. • Nordel • F,SWE,NO,DK (part) • UKTSOA • UK • ATSOI • Ireland • UPS/IPS • Ex Commonwealth of Independent States

  41. Synchronous areas (1)Why create synchronous areas ? • Increase grid reliability and mutual support • Improved system frequency control to minimize major disturbances • Mutual support in case of emergencies • Sharing reserve capacities • Facilitate functioning of the electricity market • non-discriminatory domestic and cross-border access to the grid • No need for synchronous area as such, also possible with dc links Example of direct benefits • Zone of 15 GW production capacity loses its largest unit 1 GW • Isolated: needs to develop 1 GW in less than 5s to avoid collapse • As a part of UCTE it needs to develop its share of the two largest UCTE unit, and thus x% of 3GW, in 15-30s.

  42. Synchronous areas (2)Challenges • Coordination and control of the power flows • Interdependency of power flows • Interconnected systems share benefits and problems • Problems on top of the above • Often different standards applied in control zones

  43. Technical standards differences • Exact same line can have different capacities • Different interpretation of frequency control • Different operational standards Source: IAEW

  44. Synchronous areas (3) Operational handbook (UCTE) “Stronger interconnections require common and consistent understanding of grid operation and control and security in terms of fixed technical standards and procedures” • Result of discussion between all TSO’s involved • Successor of past technical and organizational rules and recommendations • Unification and formalization of standards • To make the best possible use of benefits of interconnected operation • To keep the quality standards in the market environment Operation handbook: http://www.ucte.org/publications/ophandbook/

  45. Cross-border power flowsin European grid • Typical power flow pattern • Countries structurally exporting or importing • However • Unstable production strongly influences the pattern • Wind generation • Restrictions consist typically of several lines • What matters for the grid are individual lines flows! • This differs considerably from the physical “border capacity”

  46. UCTE physical energy exchanges 2004 [GWh]

  47. Level of congestion between EU Member States Source: DG COMP

  48. Franco-Belgian Border 2001 • Unexpected flows not just ONE TIME event • More like a permanent thing

  49. Wind power is a problem • Large wind parks problematic for the network • Unstable dispatch within a zone • Will there be wind? Not too much? • Unstable loop flows • Benelux case • Positive correlation between loop flows and wind in Germany • Up to 0.4 • Loop flows almost entirely through BE and NL

  50. Phase shifter investments in the Benelux in order allow power flow control • Meeden (Nl) • Gronau (D) • Kinrooi (B) • Kinrooi (B) • Zandvliet (B) • Monceau (B) 1 2 5 3 4 6

More Related