1 / 11

14 June 2011

NPD – Project Timing. 14 June 2011. 1. Accumax500 #1265 – Current Timing 5/24/2011 Quantity per year – 10 Units Prototype Timing (Units #1 & #2 / one Poultry & one Red Meat) 3/8 Frame / Hopper Prints released 3/31 Shaft Feed Screw Print Released

slade
Download Presentation

14 June 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NPD – Project Timing 14 June 2011 1

  2. Accumax500 #1265 – Current Timing 5/24/2011 Quantity per year – 10 Units Prototype Timing (Units #1 & #2 / one Poultry & one Red Meat) 3/8 Frame / Hopper Prints released 3/31 Shaft Feed Screw Print Released 4/17 Pump Box Print Release & 8 Misc. Parts 4/27 Top Plate Print Complete 5/12 End Conveyor Prints Complete 6/1 Pump Box Mounting Prints Complete 5/24 Unit #1 Parts Receipt – Frame Etc. (Frame Rework Complete) 6/6 Unit #1 Pump Box Receipt (and Unit #2) 6/14 Unit #1 Hopper Rework Complete 5/31 - TBD Top Plate / End Conveyor Parts Receipt 6/15 - TBD Conveyor Parts / Drive Roller 6/1- 6/30 Unit #1 Mokena Machine Build and Test (4 weeks) 6/30 Milestone – Unit #1 Prototype Machine Build Complete - Poultry 6/22 Unit #2 Parts Received – Frame Etc. 6/20 Unit #2 Hopper Received 7/1-8/15 Unit #2 Mokena Machine Build and Test (6 weeks) 8/15 Milestone – Unit #2 Prototype Machine Build Complete – Red Meat 7/15 – 10/15 Customer trials (12 weeks) 10/15 Milestone – Machine Certified as Production Released Note – total of 4 units expected to be sold in 2011

  3. Accumax500 #1265 - Parts Timing

  4. Frame Timing (2 Units) Machine Mounting Fixtures at Walco 3/15-4/7 Ship machine parts to Ace 4/8 Form / weld Frames at Ace 4/8 – 4/27 Send Frame #1 to Walco 5/3 Machine Frame #1 at Walco 5/3 - 5/12 Send Frame #1 to Ace 5/12 – 5/13 Final Frame work / Sand blast 5/13 Receive Frame #1 at Provisur 5/17 / Rework 5/24 Receive Frame #2 at Provisur 6/22 Hopper Timing (3 Units / one for Rotary) Pre-Machine Parts from Walco 4/19 Assemble Hoppers at Ace 4/20–5/3 Ship Hoppers back to Walco 5/3 Machine Hoppers at Walco 5/3-5/20 Ship Hoppers back to Ace 5/20 Final shot blasting at Ace 5/20-5/23 Hopper #1 / Feed Screws to Provisur (Accumax) 5/25 Hopper #2 / Feed Screws to Provisur (Rotary) 6/20 Hopper #3 / Feed Screws to Provisur (Accumax) 6/20 Accumax500 #1265 - Parts Timing

  5. Pump Box Rotary Grind Rough top and bottom 4/28 Nomura Edge one side 4/29 6va-Vertical CNC Rough top side 5/3 6va-Vertical CNC Rough bottom side 5/5 Surface grind True up 5/6 Niigata-Horizontal CNC Front finish (Had to do 3 steps Vert.) 5/20 Niigata-Horizontal CNC Back finish 5/23 6va-Vertical CNC Finish Top Service/True Pocket 5/25 Saw/Lathe Plug Plug – Cut and Turned 5/25 Weld Weld Plug onto Pump Box 5/26 Polish Polish Plug Weld on Box 5/27 Surface Grind Finish Grind to 0.002” 5/31 6va-Vertical CNC Finish Bore top side 6/1 6va-Vertical CNC Finish Bore bottom side 6/2 Polish All Exterior to 32mF 6/3 Deburr All internal passages 6/4 Plating Electroplating-3 Day 6/7 Ship to Provisur At Provisur 6/8 Accumax500 #1265 - Parts Timing

  6. 1000mm Rotary Former #1305 – Current Timing Quantity per year – 5 Units Prototype Timing (Unit #1) 11/1/2010 Long Lead time items kicked off (mandrel, enclosure, pump box, drum raw material) 2/28 Milestone - Prints Complete 2/28-3/8 BOM review, MFG strategy Review, Packages assigned (1 week) 3/8-3/15 Quotes Complete – Part Kickoff (1 week) 3/15-6/30 Parts Received (10 weeks) 6/21-8/1 Machine Build (6 weeks) Hopper/Frame expected 6/21 Mandrel 6/30 Knockout assembly TBD 8/1-9/1 System Electrical Configuration (4 weeks) 9/1 Milestone – Prototype Machine Build complete 9/1-10/1 Internal Mokena Trials (4 weeks) 10/1-12/1 Customer Trials (8 weeks) 12/1 - 12/31 Machine revisions / updates as needed (4 weeks) 1/1/2012 Milestone - Machine Certified as Production Release Production Timing (Unit #2 / #3) 6/1 Mandrel Material (26 week lead time) Current plan – use Carbon Steel Mandrel Material (At Walco) for Unit #2 Unit #3 Mandrel Material TBD & to be ordered 8/15/2011 Estimated balance of part to be kicked off for Unit #2 1/1/2012 Unit #2 – Parts to Mokena 2/15/2012 Unit #2 Shipment

  7. 1000 mm Rotary Former Unit #1 #1305 - Parts Status

  8. 1000 mm Rotary Former Unit #1 #1305 - Parts StatusParts Delivery All Parts planned for 5/15 delivery w/ noted exceptions:Mandrel Due 6/30 (Walco) Enclosure & Frame Due 6/21 (Note: pitting – what allowable?) (Ace)Pump Box Due 6/17 – Send to Empire 6/14 for Chrome (Walco)Pump Pump Received (Waukesha) Note Unit #2 – Waukesha may make assembly Pump Gear Casing Mfg not as easy as thought – not a stock tube – Ace formed tube (Walco/Ace) Due 6/24 Stainless part done – ready It is at Tin Plate / Assembly & finish bore remains to be finishedHopper Assembly Due 6/20 (Walco/Ace) Knockout Assembly Kicked of 4/7 – Due 7/5 (HM)SERVO MOTOR (WITTENSTEIN) TIMING TBD

  9. The following lists the steps and estimated completion dates 1. Purchase material 2. Programming 3. Tooling 4. Nomura boring mill:                                3/3 Center Bore 5. Leblond Lathe                                           3/5          Rough OD 6. Niigata                                                   3/9         Rough Facing / Boring Bore Steps inside 7. 6va MCVA Gantry                                    3/23       Rough outside mill work 8. Niigata                                                   4/18       Finish inside boring 9. Nomura                                                  6/13       Center Bore–inside boring & CN added holes 10 .Leblond Lathe                                              6/14          True up OD 11. 6va  MCVA Gantry                                     6/17       Finish outside milling - ECN 12. OD Grinding                                             6/24        Outside Shop - Grinding 13. 6va   MCVA Gantry                               6/27      Final vacuum pocket manufacture 14. Plating                                                  6/27       Send to Chrome Plating 15. Plating                                                  6/30      Review at Walco 16. Ship to Provisur Technologies                 6/30 1000 mm Rotary Former Mandrel Timing - #1305

  10. 250 mm 3 sets now identified for Keystone field test:#1293 1 – 10 wt. Hamburger – Done 1 – Nugget knockout drum released – is already started (low carbon steel) NOW HOT.. CR to Change ID - Re-Honing caused inconsistent ID Reboring the ID 6/13 Platen being machined Fill Slot received – out of Royalloy TARGET COMPLETION 6/20 RISK – May have to re-manufacture 1 – “Value Chicken” to be made out of PerformAlloy – Due 7/201000 mm TBD – based on where it is going#1305 3 Parts Drum Est. 12 wk lead time (1st part) Knockouts & Inner Platen Plan 6/1 kickoff for 9/1 delivery Rotary Former Tooling - Timing

  11. Kraft 72” CF 3K – “Continuous Feed 3K” - #1309 / #1337 Quantity per year – 2/3 Units Key Milestone Dates Prints Complete 5/24/2011 Stage Gate Review June 6th Parts Received 7/15/2011 Loaf Loader system customer for Kraft #1337 in design Unit Ship 10/18/2011

More Related