An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Critical Design Review Personnel Safety System: PSS0 www.europeanspallationsource.se 2018-02-08

  2. Introduction Ion Source/LEBT Test Stand • ESS follows a staged installation and commissioning plan • Ion Source and LEBT (made in Catania/INFN) have arrived in Lund and are currently installed • 1st step is to operate the Ion Source and LEBT as “test stand”safely

  3. Introduction PSS0 • PSS0 is the electrical safety system for the Ion Source and LEBT test stand • Mitigation against electrical hazards is implemented by switching off the HV PS (90kV) of the Ion source HV platform • Installation is prepared to start on 2018-02-12 (rack installation, cable termination, etc) • Scope is restricted to electrical hazards. • Radiation hazards (prompt ionising radiation/not activation) are mitigated by shielding the areas where dose levels might exceed >2microSieverts/h with lead. • Prompt radiation hazards are mitigated also indirectly by switching off the HV PS of the Isrc (no power, no beam)

  4. MP/PSS - Group Structure Machine Protection and Personnel Safety Systems Group Annika Nordt: Group Leader, WPM (2012-05) Denis Paulic: Deputy Group Leader (2015-03) Riccard Andersson: Technical Project Coordinator (2017-08) Machine Protection ICS/WP14.5: Manuel Zaera-Sanz (Senior Engineer: 2014-08) Enric Bargallo (Lead Analyst for Dependability, MP: 2017-04) Szandra Kövecses (Lead Integrator: 2017-05) Stephane Gabourin (Lead Engineer Fast Interlocks: 2017-08) Viktor Fred (Lead Engineer Electrical Installations: 2017-09) David Valdepenas (Automation Engineer: 2017-10) Fernando Carrasco Martin (Technician: 2018-02) Personnel Safety Systems ICS/WP14.9: Stuart Birch (Senior PSS Engineer, WPM: 2014-08) Morteza Mansouri (SCS Engineer: 2015-05) Yong Kian Sin (IEC 61508 Controls Engineer: 2016-02) Alberto Toral (Technician: 2017-03) Mattias Eriksson (Technician: 2017-11) Vacancies: 1 Technician Goal: Build a flexible and strong team, sharing & extending the different skill sets. Everyone has knowledge relevant for both MP and PSS. MP and PSS will follow IEC61508.

  5. Dear Review Panel: • Thank you for participating and sharing your expertise • We are looking forward to constructive review sessions