The site is located in waste land with 9-12m of underlying alluvial clay. This was compounded by the lack of detailed loadings information at the design stage. Based on the ground investigation report provided by the client, the piles were initially estimated at between 35-40m long. Our SCIA models were crucial in analyzing differential and final displacements of the various structures. Explore this PDF for complete information.
E N D
Ince Biomass Energy Plant THESOLIDAPPROACH
About Project InceBiomassEnergyPlantutilizes advancedgasificationtechnologyto process170,000tofwoodwasteannually. Itproduces21.5MWofrenewable electricity. Itisexpectedtosave65,000t ofcarbondioxideeachyear; the equivalentoftaking40,000averagecars offtheroad.