Nodal Reliability Performance Measures WorkshopProject No. 37052 Public Utility Commission of Texas June 12, 2009
Nodal Reliability and Regulatory Oversight • Goals for Go-live: • Adequate PUCT oversight of market on first day • Enforcement to consider new market limitations • Reasonableness • Metric adjustment and tuning process • Reliability and Compliance Training Plan • Monitoring reports are tested and useable • Longer term plan for additional metrics, if needed • Clear communication of regulatory oversight and risk
Approach • PUCT, Texas RE, IMM and ERCOT ISO have taken a proactive approach • Define a minimum set of reliability metrics and criteria (NPRRs and NOGRRs) necessary to enable go live • Implement a gap analysis • Create NPRRs and NOGRRs to fill gaps • Work through Stakeholder process to enact in time for market trials with urgent status • Ensure proper reports are ready for monitoring and enforcement • Create regulatory training and roll out plan
Other Issues • Plan to submit resulting NPRRs and NOGRRs to ERCOT process for approval using urgent status • Leverage NOGRR-025 work and integrate results into stakeholder process • Reliability metrics and criteria to be in place for market trials for testing • Minimized impact to Nodal Project (no code changes to core systems)
Reliability Issues • 55 issues affecting reliability of the ERCOT grid were identified • Of these, 24 are deemed to be critical for Nodal go-live regulatory oversight • Of these 24, 12 will require protocol or operating guide changes • The remaining 12 issues are already addressed in existing protocols or operating guides • Many of the other 31 issues will be ready for go-live or should be addressed within a short time frame after nodal go-live
Design Requirements • Criteria must be defined that detail what he expect behavior is and how it will be measured • Metrics must be defined that clearly identify what is passing and what is failing • The mechanism for monitoring performance, reporting potential failure and communicating this to Texas RE must be included
Reporting • Reports will need to be developed to generate exception reports on a periodic basis (e.g. monthly) to identify failures of calculated metrics • Complaint process may be used to identify incident-oriented failures • Trending metrics may be defined that are intended to monitor an issue but that are not intended to be used for violations
Not needed @ go-live Organization Critical for go-live, already covered Critical for go-live work needed
Binding Documents • State Estimator • Telemetry Standards • Any other applicable binding documents
Real-time > ISO > Frequency OG: NP: 8.2(2)(b)(vii) Critical for Nodal go-live. Already covered.
Real-time > ISO > Event Recovery > DCS OG: NP: 8.2(b)(vii) Critical for Nodal go-live. Already covered.
Real-time > ISO > Event Recovery > EEA-EILS OG: NP: 8.1.3.1, 8.1.3.4 Critical for Nodal go-live. Already covered.
Real-time > ISO > Constraints > IROLs OG: 9.12.1(1), 9.12.4 NP: 8.2.(2)(d) Critical for Nodal go-live. Already covered.
Real-time > ISO > Constraints > SOLs OG: 9.12.1(1), 9.12.4 NP: 8.2.(2)(d) Not needed for oversight at go-live. NPRR/NOGRR required to adopt criteria.
Real-time > ISO > Constraints > Maintain proper bus voltage limits OG: 9.12.9, 2.7 NP: 3.15.1, and 6.5.7.7 Not needed for oversight at go-live. NPRR/NOGRR required to adopt criteria.
Real-time > ISO > State Estimator > State Estimator Standards OG: 9.12.1(4)(a) NP: 8.2(2)(a)(iii) Critical for Nodal go-live. Already covered.
Real-time > ISO > Operating/Ancillary Reserves > Regulation OG: NP: 6.5.7.5(1)(h) Not needed for oversight at go-live. No action required.
Real-time > ISO > Operating/Ancillary Reserves > Non-spin OG: NP: 6.5.7.5(1)(d)-(g) Not needed for oversight at go-live. No action required.
Real-time > ISO > Operating/Ancillary Reserves > Responsive Reserves OG: 9.12.2(2)(a) NP: 6.5.7.5(1)(a)-(c ),6.5.9.4.2 Not needed for oversight at go-live. No action required.
Real-time > ISO > Operating/Ancillary Reserves > LaaRs OG: NP: 6.5.7.5(1)(b),(c ),and(e) Not needed for oversight at go-live. No action required.
Real-time > ISO > Ancillary Service Energy Deployment > System Regulation Deployment OG: 9.12.2(1) NP: 8.2(2)(b)(ii) and 6.5.7.6.2.1 Critical for Nodal go-live. Already covered.
Real-time > ISO > Ancillary Service Energy Deployment > Non-spin online measures OG: NP: 6.5.7.6.2.3 Not needed for oversight at go-live. No action required.
Real-time > ISO > Ancillary Service Energy Deployment > Responsive requirements of units OG: 9.13.4 NP: 6.5.7.6.2.2, 8.2(b)(vii) Critical for Nodal go-live. Already covered.
Real-time > QSE > Operating/Ancillary Reserves > Regulation OG: NP: 8.1.1.3.1 Critical for Nodal go-live. NOGRR/NPRR required to define compliance report/possible exemptions.
Real-time > QSE > Operating/Ancillary Reserves > Non-Spin OG: NP: 8.1.1.3.3 Critical for Nodal go-live. NOGRR/NPRR required to define compliance report/possible exemptions.
Real-time > QSE > Operating/Ancillary Reserves > Responsive Reserves OG: NP: 8.1.1.3.2 Critical for Nodal go-live. NOGRR/NPRR required to define compliance report/possible exemptions.
Real-time > QSE > Operating/Ancillary Reserves > LaaRs OG: NP: 8.1.1.3.2(2) and 8.1.1.3.3(2) Critical for Nodal go-live. NOGRR/NPRR required to define compliance report/possible exemptions.
Real-time > QSE > Ancillary Services Energy Deployment > Non-spin online measures (1/3) OG: 9.13.6 NP: 8.1.1.4.3 and 8.1(3)(m) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Ancillary Services Energy Deployment > Non-spin online measures (2/3) OG: 9.13.6 NP: 8.1.1.4.3 and 8.1(3)(m) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Ancillary Services Energy Deployment > Non-spin online measures (3/3) OG: 9.13.6 NP: 8.1.1.4.3 and 8.1(3)(m) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Ancillary Services Energy Deployment > Responsive requirements of units (1/3) OG: 9.13.4 NP: 8.1.1.4.2 and 8.1(3)(k) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Ancillary Services Energy Deployment > Responsive requirements of units (2/3) OG: 9.13.4 NP: 8.1.1.4.2 and 8.1(3)(k) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Ancillary Services Energy Deployment > Responsive requirements of units (3/3) OG: 9.13.4 NP: 8.1.1.4.2 and 8.1(3)(k) Critical for Nodal go-live. NOGRR/NPRR required.
Real-time > QSE > Telemetry Standards OG: 9.3(c)(ii) NP: 8.1(3)(c)(i) Critical for Nodal go-live. Already covered.
Real-time > QSE > Event Recovery > Governor Response (1/3) OG: 2.2.7, 2.2.8 NP: 8.5.2, 8.5.1.1 and 8.5.1.2 Critical for Nodal go-live. Already covered.
Real-time > QSE > Event Recovery > Governor Response (2/3) OG: 2.2.7, 2.2.8 NP: 8.5.2, 8.5.1.1 and 8.5.1.2 Critical for Nodal go-live. Already covered.
Real-time > QSE > Event Recovery > Governor Response (3/3) OG: 2.2.7, 2.2.8 NP: 8.5.2, 8.5.1.1 and 8.5.1.2 Critical for Nodal go-live. Already covered.
Real-time > QSE > Resource Outages OG: 9.6 NP: 8.1(3)(q) Not needed for oversight at go-live. No action required.
Real-time > QSE > COP > Day-Ahead OG: 9.10(2),(3),(4),(6) NP: 8.1(3)(r ), 3.9.2, 3.16, 8.1.2 Critical for Nodal go-live. Changes recommended can wait until after go-live.
Real-time > QSE > COP > Adjustment Periods OG: 9.10(1),(5),(6) NP: 8.1(3)(r ), 3.9.2, 3.16, 8.1.2 Critical for Nodal go-live. Changes recommended can wait until after go-live.
Real-time > QSE > Energy > Adherence to dispatch orders OG: 9.4 NP: 8.1(3)(f) Critical for Nodal go-live. Already covered.
Real-time > QSE > Energy > GREDP (1/3) OG: 9.4 NP: 8.1.1.4.1(2)-(5) Critical for Nodal go-live. NOGRR/NPRR required to adopt criteria.
Real-time > QSE > Energy > GREDP (2/3) OG: 9.4 NP: 8.1.1.4.1(2)-(5) Critical for Nodal go-live. NOGRR/NPRR required to adopt criteria.
Real-time > QSE > Energy > GREDP (3/3) OG: 9.4 NP: 8.1.1.4.1(2)-(5) Critical for Nodal go-live. NOGRR/NPRR required to adopt criteria.
Real-time > QSE > Energy > Voltage Control > Maintain voltage set point OG: 9.9, 2.7.4.1, 9.2 NP: 3.15.3, 8.1(3)(o), 6.5.5.1, 8.1(3)(b) Critical for Nodal go-live. NOGRR/NPRR required to define report.
Real-time > TSP > Transmission Outages OG: 9.11.3 NP: 8.3(1)(c ) Not needed for oversight at go-live. No action required.
Real-time > TSP > Telemetry Standards OG: 9.11.2 NP: 8.3(1)(b) Critical for Nodal go-live. No action required.
Real-time > TSP > Voltage and Switching of Transmission Elements > Following TOP directives OG: 9.11.5, 2.7.4.1 NP: 3.15.2 Not needed for oversight at go-live. NOGRR25 may need more detail to explain the monthly report.
Planning > ISO > Day-Ahead Market > DRUC OG: 9.12.1(3)(a)(i),9.12.2(3)(a),9.12.4(c) NP: 8.2(2)(l), 8.2(2)(d)(iii), 8.2(2)(b)(iv), 5.3 Not needed for oversight at go-live. No action required.
Planning > ISO > Day-Ahead Market > HRUC OG: 9.12.1(3)(a)(i),9.12.2(3)(a),9.12.4(c) NP: 8.2(2)(l ),8.2(2)(d)(ii), 5.3, 8.2(2)(b)(iv) Not needed for oversight at go-live. No action required.