Progress report on continued validation and fixes of the 2028 ADS PCM V1.0. Includes updates within CAISO footprint and NTTG fixes. Review of proposed agenda for upcoming meeting.
E N D
PDWGValidation of the 2028 ADS PCM V1.0 Jamie Austin Production Cost Modeling Data Work Group (PDWG) – Chair August 21, 2018
L&R Progress Report • Continued Validation of the 2028 ADS PCM V1.0 • Fixes within CAISO Footprint • Fixes by NTTG • DS approval of PDWG proposed edits • Review of Proposed Agenda for next in-person meeting, scheduled for August 28-29 Overview
L&R Progress Report Tyler Butikofer
Thermal Generation Balance – cont. Western Electricity Coordinating Council
Renewable and Other Generation Balance Western Electricity Coordinating Council
Fixes within CAISO Footprint Yi Zhang, California ISO
Two Peaker units that were originally parked should be modeled as units in service • Grapeland Peaker at 29305 • CTRPKGEN_29308 at 29308 • Remove the previously modeled BC_25187_1C and BS_25188_1E units CISC area
Remove three pumped storage units at Hyatt • EdwardCHyatt2, EdwardCHyatt4, and EdwardCHyatt6 • Change Thermalito_2, Thermalito_3, Thermalito_4 from Pumped Storage to Hydro, with Load Following flag checked Hyatt and Thermalitohydro units
Klamath Falls area • Remove Capt. Jack – Klamath Falls 500 kV, and keep Capt. Jack-Snow Goose – Klamath Falls 500 kV • Remove Malin – Klamath Falls 230 kV, and keep Malin – Snow Goose – Klamath Falls 230 kV • Meridian – Sam’s Valley – Dixonville 500 kV line impedances are wrong • Buckley – Slatt series capacitor is missing NW topology (per BPA’s comments)
Use Kevin proposed changes for Antelope Nuke, but set the Min Up/Down time to 168 hours and NOT MUST RUN Use Kevin proposed changes for Antelope Nuke, but set the Min Up/Down time to 168 hours (previously they were 1 hour)
Continued Validation of the 2028 ADS PCM V1.0 Jamie Austin