RENEWABLE ENERGY & ENERGY EFFICIENCY IN MOROCCO SITUATION & PROSPECTS. Presented by M. Mustapha ENZILI Resources & Engineering Department (Morocco) CAIRO (EGYPT) – 28 JANUARY 2008. SUMMARY. Overview of Electricity in Morocco Renewable Energy Potential in Morocco
E N D
RENEWABLE ENERGY & ENERGY EFFICIENCY IN MOROCCOSITUATION & PROSPECTS Presented by M. Mustapha ENZILI Resources & Engineering Department (Morocco) CAIRO (EGYPT) – 28 JANUARY 2008
SUMMARY • Overview of Electricity in Morocco • Renewable Energy Potential in Morocco • Capacity installed of Renewable Energy in Morocco • Projects programmed (2008-2012) • Grid-Connected RE Projects in Morocco - WindFarms Projects in Morocco- Solar Thermal Power Project in Morocco • Plan for implementation Wind Farms in Morocco 2008-2012 • Wind Farms in Morocco • Desalination seawater by wind energy in Morocco • Case study of Morocco (Needs project)
ENERGY IN MOROCCO • 46 Milliards DH for imports of energy products (4 Milliards Euro) in 2006 • Average annual consumption growth of electricity : 8 % (2006/2005) • Capacity of Power Plant to install each year : 400-500 MW • The projections for the periods 2008-2010 & 2010-2015: - 2008-2010 : Consumption growth of 7.3 %- 2010-2015 : Consumption growth of 6.5 % • Energy consumption(GWh) - 2005 : 19 509 GWh- 2006 : 21 105 GWh - 2010 : 27 350 GWh- 2015 : 37 470 GWh
ELECTRICITY IN MOROCCO CONSUMPTION IN 2006 : 21105 GWh - Thermal : 91 % - Hydro : 8 % - Wind : 1 %
ELECTRICITY IN MOROCCO IN 2006 • Total Power plant : 5312 MW • Electricity consumption : 21105 GWh (2006); 19508 GWh(2005) • Growth of electrical consumption : 8.8 % per year • Electrical Power plant : - Thermal Power plant : 3469 MW ▪ Coal : 1785 MW ▪ Fuel Oil : 1284 MW ▪ Natural Gas : 400 MW - Hydraulic Power plant : 1729 MW - Wind Farms : 124 MW
ELECTRICITY IN MOROCCO IN 2006 • Electricity Consumption : 21105 GWh • Electricity production : 19822 GWh - Thermal Power plant : 18054 GWh - Hydraulic Power plant : 1585 GWh - Wind Farm : 183 GWh * Imports : 2027 GWh
RENEWABLE ENERY POTENTIAL INMOROCCO • SOLAR ENERGY : Morocco has an excellent Solar potential : 4,7 - 5,7 kWh/m2/day (2800 hours/year in the North, more than 3000 hours/year in the South of Morocco). • WIND ENERGY : Morocco has an excellent wind potential mainly in the North & in the South :- Tangier, Tetouan & Essaouira with an annual average between 9 & 11 m/s at 40 meters.- Tarfaya, Taza & Dakhla with an annual average between 7.5 m/s & 9 m/s at 40 meters. Wind Potential of Morocco : • Total Potential : 7936 TWh/year (3968 GW) • Technical Potential : 4896 TWh/year (2500 GW)(Electricity consumption in Morocco in 2006 : 21 TWh) • Wind Atlas of Morocco published in 1986 & 1995 and updated in 2007. • More than 50 measurements stations installed between 1990 & 2007
PLAN FOR IMPLEMENTATION WINDFARMS & SOLAR THERMAL PROJECTS IN MOROCCO (2008-2012) • WindFarms Programmed : 1000 MW until 2012 • WindFarmsinstalled : 124 MW (2007) • Projects programmed : • - WindFarm 140 MW (Tangier); 2009 • - Gas + Solar Thermal + : 470 MW (Oujda) • * Solar Thermal (30 MW) • - WindFarm 300 MW (Tarfaya) • - WindFarm 100 MW (Taza) • - Wind Farm 240 MW (Laâyoune) • - Wind Farm 200 MW (Foum El Ouad – Laâyoune) • - Wind Farm 60 MW (Sendouk – Tangier)
PROJECT OF 50 MW (El Koudia El Baida -Tetouan) • Project : Power : 50 MW (84 Vestas 600 kW) Date production : 8/2000 Production : 195 GWh/year (2005) Feasibility Study : CDER BOT Project : CED (EDF-Germa / France) (selled to Theolia in december 2007) • Average wind speed at 40 meters : 10 m/s • Average wind speed in the best location in the site at 40 meters : 11 m/s
PROJECT OF 3.5 MW(El Koudia El Baida -Tetouan) • Power : 3.5 MW • Date production : 3/2001 • Production : 13 GWh/year • Feasibility Study : CDER • Project : ONE • Average wind speed at 40 meters : 10 m/s
WINDFARM 60 MWCAP SIM (ESSAOUIRA) Power : 60 MW Windturbines : 71 Gamesa G52-850 kW Date production : 04/2007 Production estimated : 210 GWh/year Avearage Wind speed (40 m) : 9.45 m/s Feasibility Study : CDER Project : ONE Project Cost : 800 millions DH (72 Millions Euro)
PROJECT OF 10 MW Lafarge (Ciments Factory of Tetouan) Power : 10 MW Windturbines : 12 * 850 kW (Gamesa) Date production : 9/2005 Production estimated : 38 GWh/year Wind energy Production : for Ciments factory (extra energy selled to the national electrical grid) Project Cost : 110 millions DH (10 Millions Euro)
WINDFARM 140 MW(TANGIER) Power : 140 MW Windturbines : 165 Gamesa 850 kW Production estimated : 526 GWh/year Avearage Wind speed (40 m) : 9 m/s Feasibility Study : CDER Project : ONE Date production : 2009 Project Cost : 2750 millions DH (250 Millions Euro)
PROJECTS OF TARFAYA & TAZA • Taza : Power : 100 MW Production estimated : 300 GWh/an Average wind speed (40 m) : 8 m/s Feasibility Study : CDER Project : ONE • Tarfaya : Power : 200 - 300 MW Production estimated : 580 - 870 GWh/an Average wind speed (40 m) : 7.63 m/s Feasibility Study : CDER Begin operation of the project : 2010 (International call of tenders launched in march 2007)
FEASIBILITY STUDIES OF 8 WINDFARMS • Feasibility study CDER/IMET about 8 sites of WindFarms in Morocoo :Cap Hdid - My Bouzerktoune(Essaouira) Sidi Garn(Tan-Tan) Sahb Harcha(Tan-Tan) Tarfaya Sendouk(Ksar Sghir-Tanger) Col Touahar(Taza) Cap Cantin(Safi) • Conclusion of the study : Potential of 1500 MW in 8 siteswith a cost production between 3.31 to 5.69 Eurocent/kWh
PROJECT OF TAN-TAN Project : Desalination seawater by wind energy Situation : Tan-Tan city (933 kms in the south of Rabat) (near Atlantic coast) Water Production : - 6048 m3/day(2008) - 9502 m3/day(2010) - 11232 m3/day(2015) Wind Farms : Grid connected Power : - 5.6 MW(2008) - 8.8 MW(2010) - 11.2 MW(2015) Production estimated : 25.52 GWh/an (2015) Average wind speed (40 m) : 6.82 m/s Feasibility Study : CDER Project : ONEP
PROJECT OF AKHFENNIR • Parties of the Project : ONEP (Morocco) IMET (Italy) CDER (Morocco) • Project objectives : Desalination sea water by wind energy in Akhfennir village • Situation of the village : Near Atlantic Coast(1000 km in the South of Rabat, capital) • Number of inhabitants : 4000 residents permanently • Consumption of water : 860 m3/day (2008 - 2015) • Drinking water : Akhfennir village is supplied in drinking water by trucks cisterns from the city of Tan-Tan (120 DH/m3#11 Euro/m3)
ENERGY EFFICIENCY • Potentiel of economy of energy : 15% of the consumption until 2020 • Programme of energy efficiency: • Programme of energy efficiency in Building, • Projet of energy efficiency in Hospitals, • Programme of energy efficiency in Ministries & Publics administrations.
RE & ENERGY EFFICIENCY • New Law about Renewables Energies & Energy Efficiency (17 may 2007); • New Law about autoproduction of electricity from 10 to 50 MW(25 january 2007);
Jorf Lasfar Power Plant - Coal – Morocco 1360 MW - 10090 GWh/yr Damages Mio. EURO2000 per Year Cent2000 per kWh
Mohammadia Power Plant - FuelCoal – Morocco600 MW - 3954 GWh/yr Damages Mio. EURO2000 per Year Cent2000 per kWh
Kenitra Power Plant - Fuel –Morocco300 MW – 714 GWh/yr Damages Mio. EURO2000 per Year Cent2000 per kWh
Tahadart Power Plant - Gas - Morocco400 MW - 2920 GWh/yr Damages Mio. EURO2000 per Year Cent2000 per kWh
Jerada Power Plant - Coal - Morocco155 MW / 1080 GWh/yr Damages Mio. EURO2000 per Year Cent2000 per kWh