1 / 7

30Nos. Distributaries under the 3 canals are in progress and are to be completed by 3/2006.

Discharge : 950 Cusecs Ayacut : 55,000 Ac. Length : 67.60 Km. Capacity : 78 TMC FRL : 330’(+100.58M) Ayacut : 4.14L Acrs. Discharge : 380 Cusecs Ayacut : 43,000 Ac. Length : 72.92Km.

Download Presentation

30Nos. Distributaries under the 3 canals are in progress and are to be completed by 3/2006.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Discharge : 950 Cusecs Ayacut : 55,000 Ac. Length : 67.60 Km Capacity : 78 TMC FRL : 330’(+100.58M) Ayacut : 4.14L Acrs. Discharge : 380 CusecsAyacut : 43,000 Ac. Length : 72.92Km KAVALI CANAL (PKG94) North feeder canal (PKG 96) KANIGIRI RESERVOIR BAY OF BENGAL SOMASILA RESERVOIR PENNA RIVER SOUTH FEEDER CANAL (PKG 95) NELLORE ANICUT SANGAM ANICUT Discharge : 353 Cuses Ayacut : 41,000 Ac. Length : 72.00Km SOMASILA- KANDALERU FLOOD FLOW CANAL KANDALERU RESERVOIR AP – TN Boarder Cap.2.75 TMC Capacity : 68.05TMC Ayacut : 3Lakh Acres. FRL : + 279’ Poondi Reservoir • Head works, 3 main canals & Structures completed. • 30Nos. Distributaries under the 3 canals are in progress and are to be completed by 3/2006. • Lining works for all 3 Main Canals proposed in package 94, 95 & 96 for Rs.95Cr. • The Project will be completed by 6/2006 & IP of 4.14 Lakh Acres (Stab. 2.75 Lakh acres + New 1.39 Lakh acres) will be created. • Funded by AIBP. SOMASILA PROJECT (2 years period)

  2. SOMASILA PROJECT

  3. SOMASILA PROJECT

  4. SOMASILA PROJECT Pkg.No. 94/Cat-II : Easening of slops 1:5:1 providing cement concrete lining with paver in bed and side slopes of Kavali canal of Somasila Project in between Km.1.609 to Km.67.619 including Investigation, Design and estimation. Name of the Contractor : M/s. S.r.K. Bhailal Bhai (JV) Agreement Amount : Rs. 36.60 Crs. Agreement Date : 23-03-2005 Period of completion : 24 Months(8 milestones) Target date of completion : 3/2007 • Designs : HPs approved • Execution : work not in progress due to water released into the canal • Qty. of earth work done : 70,000 cum against 7,27,907cum • Machinery : Deployed 45 Nos. (Excavators-7, Tippers-19,paver-2,concrete mixers-4 Nos) • Expenditure : 2004-2005 - Rs. 1.83 Crs. • 2005-2006 - Rs. 1.83 Crs. • Cum. Exp. Mob. Adv. only - Rs. 3.66 Crs. • Bottle Neck : Forest clearance. • Forest land : Required 319.81 acres

  5. SOMASILA PROJECT Pkg.No. 95/Cat-II : Construction of distributary system of create irrigation potential of 912 Acres including investigation, design and estimation. Name of the Contractor : M/s. M.S.K. Surya Con(JV) Agreement Amount : Rs. 28.81 Crs. Agreement Date : 25-03-2005 Period of completion : 24 Months(8 months) Target date of completion : 3/2007 • Investigation : 63.325 Km length against 81.40 Km • Design : 2.00 Km length against 81.40 Km • Execution : 14 Kms length against 81.40 Kms. • Qty. of earth work done : 3,37,000 cum against 10,23,380cum • Qty. of concrete work done : 3000 cum against 61,990 cum • No. of Machinery : 43 Nos. (Excavators-5, Tippers-4, pavers-4, concrete Mixers-6) • Expenditure : 2005-2006 - Rs. 4.83 Crs. (Inc. Mob. Adv.) • Land Acquisition : Required 133.44 ac., Acquired 21.61 ac. • Bottle neck : Forest clearance and land acquisition. • Forest Land : Required 168.83 acres

  6. SOMASILA PROJECT Pkg.No. 96/Cat-II : Easening of slops 1:5:1 providing cement concrete lining with paver in bed and side slopes of G.K. Canal (NF.C) of Somasila Project in between Km.13.00 and Km.72.920 including Investigation, Design and estimation. Name of the Contractor : M/s. M.K.S. Surya Const(JV) Agreement Amount : Rs. 29.46 Crs. Agreement Date : 25-03-2005 Period of completion : 24 Months(8 milestones) Target date of completion : 3/2007 • Investigation : Completed. • Designs : In progress • Execution : 9.73 Km length against 59.92 Kms. • Qty. of earth work done : 1,25,000 cum against 9,53,297 cum • Machinery : Deployed 5 Nos. (Excavator-1, Tippers-4) • Expenditure : 2005-2006 - Rs. 3.53 Crs. (Inc. Mob. Adv.) • Forest land : Required 148.26 acres • Bottle Necks : Forest clearance

More Related