Upcoming Dates Accumulator Ring:

Upcoming Dates Accumulator Ring:. ASAC Review September 24 Collimator/Extraction Area/Design Reviews /Installation October 9, 10 FY2003 Budget issues Magnet Specification List – Individual Magnet Parameter Sheets Meeting Friday 10/4 1:30 p.m. – S. Tepikian and M. Hemmer

stesha
Download Presentation

Upcoming Dates Accumulator Ring:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Upcoming Dates Accumulator Ring: • ASAC Review September 24 • Collimator/Extraction Area/Design Reviews /Installation October 9, 10 • FY2003 Budget issues • Magnet Specification List – Individual Magnet Parameter Sheets • Meeting Friday 10/4 1:30 p.m. – S. Tepikian and M. Hemmer • Review them and SIGN THEM OFF • Monthly Report Today • DOE Review November 13

  2. ASAC Review Ring specific comments presented by the committee: • Findings and fixes (shimming) on magnets are in good progress -- continue. • It would be good to verify proper field in the presence of vacuum pipe (e.g. HEBT magnet measurement with beam pipe although Ted claimed the pipe non-magnetic. • Good to see ring half cell to be tested and delivered to ORNL; looking forward to it. • RF work as presented is well done. • Vacuum work as presented is well done; more to go. • Looking forward to see planned, detailed field measurement of injection chicane magnet near H- electron stripping foil in comparison with 3D mapping. • Endorse the proposal of a new view port and video monitoring of carbon-carbon electron collector near injection. • Good work is done on impedance reduction of the extraction kickers; more needs to be done on impedance measurement of RF cavities. • Continue to explore beam loss mitigation • Fast feedback, as presented by J. Galambos, can be tried e.g. to position beam on the stripping foil • Electron cloud: (a) procure and install elements that can disturb ring vacuum system, including clearing electrode at injection and solenoid windings at collimation section (b) procureother devices as budget allows • Comments on collective effects and others are to be included in the written summary (not presented).

  3. Hechler, Hunter, Murdoch Visit Agenda Wednesday, October 9 7:45-8:30 911B Small Conference Room BNIP phone conference W. Birkholz, J. Brodowski, G. Mahler 8:30-9:00 911B Small Conference Room Danfysik phone conference W. Birkholz, J. Brodowski, G. Mahler 9:00 – 9:30 911B Small Conference Room Tesla phone conference W. Birkholz, J. Brodowski, G. Mahler 9:30 – 11:00 911B Small Conference Room Injection area layout and installation. J. Brodowski, C. Pai, L. Russo 11:00 – 12:00 911B Large Conference Room General ME meeting J. Tuozzolo 1:00 – 3:00 911B Small Conference Room Ring Collimators and Moveable Scraper, HEBT Collimator Design, and RTBT Collimator Update H. Ludewig, N. Simos, J. Brodowski 3:15 – 5:00 817 Video Conference Room Ring Lattice Drawing, Survey, Installation Drawings, and Magnet Parameter List M. Hemmer, D. Raparia, S. Tepikian, J. Alduino

  4. Hechler, Hunter, Murdoch Visit Agenda Thursday, October 10 8:15 – 9:00 902 Assembly Area Magnet Testing, Measurement, and Assembly Schedule for Ring ½ Cell Magnets R. Anderson, S. Seberg, W. Birkholz, J. Jackson, G. Mahler, V. Badea, J. Tuozzolo, P. Wanderer. 9:00 – 10:00 817 Video Conference Room Assembly Schedule for Ring ½ Cell Magnets R. Anderson, S. Seberg, W. Birkholz, G. Mahler, V. Badea, J. Tuozzolo 10:00 – 12:00 817 Video Conference Room RTBT/HEBT Magnet/Vacuum Installation J. Rank, D. Weiss, D. Hseuh 1:00 – 3:00 817 Video Conference Room Extraction Straight Section Layout, Magnet Design Review, and Installation J. Rank, C. Pai

  5. Collimators • Friday 11:00 Weekly Meeting in the EAG Conference Room • Collimator lifting fixture design/weight reduction. • Collimator end shielding redesign. • Procurement STATUS – Weekly Phone Conference • HEBT Collimator Beam Line Layout • HEBT Stripper Design • HEBT Momentum Collimator – Installation/Shielding layout. • Ring Moveable Collimator – Installation Layout. • Moveable Shield Drawings to Back Correction fy 2003 procurement

  6. HEBT Magnets and Beamline HEBT Dipole • 1, 2, 3, 4, 5, and 6 at ORNL • ORNL has measured the magnets to 1% 8D408 at ORNL HEBT 12Q45 Quadrupole/16CD20 Corrector Requisition – • Production delivery of 17 magnets – Water fitting repair HEBT/RTBT 27CD30 Corrector • NETC – Ordering Material HEBT/RTBT 21Q40 Quadrupole • Phase II Magnets to be shipped to BNL for measurement. • Magnet Sled and Stand Design in Checking

  7. Ring Magnets • 902 ½ Cell Assembly Area • Shipping Date for #1 - October 31, 2002 - assembly status • Water fitting repairs • Lifting fixture modifications – Status • Production Schedule • 17D120 • ITF quality progress – magnets measured and accepted. • Spare magnet shipping? • 21Q40 Quadrupole – 17 magnets in house (#1) • 21 cm Production Measurement Schedule • Tesla Schedule • Water fitting repairs • 26Q Quadrupole Requisition • 2nd Iteration Chamfer Machining Status.

  8. Ring Magnets • 30Q Quadrupole Requisition – Contract w/BNIP • Magnet Measurement Completion Date • BNIP Production Schedule • 21S26 High Field Sextupole • Coil Modification ECN • 26S26 High Field Sextupole • Drawings in checking • SOW and Spec. • 27CDM30 Corrector (#3) – 29 in house • All Magnets Received • Ready Production Measurement

  9. Ring Magnets • 21CO26 Corrector (#4) – 8 in house • Ready for production measurement • 21CS26 Corrector(#2) – 8 in house • Production Measurement Status – Estimate to Complete • 41CDM26 Corrector • Magnet Measurement Complete - Approved for Production • 36CDM26 Corrector • 1st article delivered September 13, 2002 • Failed Hi-Pot • Return to Vendor ASAP – this week

  10. Special Injection Magnets – Overall Design Layout Injection Septum Magnet • Status – both magnets assembled? • Testing Complete - Magnet Travelers Injection Dump Septum Magnet Injection Chicane Magnets #2, #3 • NETC Contract, PCR for spares. Thin Foil Mechanism – Testing and Acceptance 7/30/02. Thick (Injection Dump) foil design status. Injection Magnet #4 – Acceptance Testing Status Injection Magnet #1 Complete Redesign. Injection Kicker Magnets • 1st articles ready for testing – Coated Ceramic Chamber?? • Ferrite Order Status, Ceramic Chamber Order Status • RFQ to Shops

  11. Special Extraction And RTBT Magnets Extraction Kicker Magnets • Design Status • Design Review Lambertson Magnet • Design Status • Design Review RTBT Magnets and Line – DESIGN REVIEW 17D244 Magnet Procurement – 7/31/02 – Need New Scheduled Date 36Q85 • Raynor fabrication of Magnet Cores – STATUS • Coil Material Delivered