Contents • Background • Process • Information requested • Information obtained • Issues • Current data • Road forward
Background • Resolution at RPF May 2001 • Data on budgets be adopted as basis and be expanded for future reports • Funded by Gautrans, Sabita and C&CI • Focused on provincial and national data in this presentation
Aims of the project • Provide information on: • Budgets • Selected infrastructure management aspects • Southern African road authorities • Actions taken by road authorities • Performance against budgets.
Process followed • Contacted road authorities – chief engineers etc • Slow response – regular communications • Other sources identified • Attempted to paint full picture • Verified with different sources
Responses • Positive responses re participation from • 9 provinces • NRA • 5/6 metros • 2/5 toll concessionaires • Data for • 8 provinces / NPRA • NRA • 2 metros • 1 toll concessionaire • SADC – appears positive – needs overall approval
Information required • Total budgets for department • Total road authority budgets • Breakdown of road budgets • Budgets for specific items (i.e. bitumen and cement) • Grants and transfers and non-treasury expenditure • Audited figures previous years • Changes to budgets • Quarterly performance against budget • Construction and rehabilitation programmes
Information obtained • Sources • Contacts in authorities • Budget speeches • Web-published data • Auditor-General reports • Treasury reports • Problems encountered • Response time • Manpower • Validity of data – only Auditor-General figures are final
Issues • Manpower – skills match problem • PFMA (Public Finance Management Act) – public information • More effective and efficient delivery, better value for money, improved public services • Develop capacity 2001/2002 • Internal control and audit units • Departmental structures • Availability of information • Budget and management systems • Progress against budget • Discrepancies in road network lengths and budget figures from different sources
Backlog issues • Estimated at R 23 billion • Basis for calculation of backlog in network • Target level of service • Target network profiles • Aspects included in backlog work • Need similar foundations for estimates to be credible
Current information • Budgets • Progress against budgets • Longer term budget trends • Audits • Grants • Planned expenditure • Road networks
Progress against budgets • Data for the whole department • Capital progress not necessarily shown when funds are allocated and not yet spent • Need to ensure that similar figures are reported
Spending on national and provincial roads – Intergovernmental Fiscal review
Grants • Supplementary Allocation grant • Ensure credible provincial budgets and adequate provision for infrastructure and social sectors • Ensure progress in implementing budget and financial management reforms • Provincial Infrastructure grant • Fund provincial infrastructure (roads, schools, health buildings) • Fund reconstruction of 2000 flood damage
Actual expenditure – 1997/98 to 2000/01 • Road expenditure 2000/2001- 2,9 % of total provincial expenditure • 33% of road expenditure – new and major rehab 1997/1998 to 2000/01 • 26% of provincial expenditure – routine maintenance 1997/98 to 2000/01
Planned expenditure – 2001/2002 • EC – Road maintenance R 69 million • WC – Major improvement projects (2000-2005) R 244 million • Gautrans – maintenance / rehabilitation 263 km in 2001/2002 (R 226 million) • Northern Province – Maintenance and construction (roads and bridges) R 266 million
Conclusions • Need for availability of valid information – roads focus • Need similar reporting / calculation mechanisms (backlog, progress etc) • Information is “dynamic” until the Auditor General captures it • Need a team approach
Road forward • PFMA effect on availability of budget and progress information • Service delivery measures • 2002/03 – measurable objectives, service delivery standards, targets – included in budget submissions – describe how public funds are used • Need for good management systems • Backlog calculations • Standard format for data at regular intervals