1 / 22

1.040/1.401 Project Management Spring 2007 Lecture 7

1.040/1.401 Project Management Spring 2007 Lecture 7. Planning Basics. Dr. SangHyun Lee. lsh@mit.edu. Department of Civil and Environmental Engineering Massachusetts Institute of Technology. Project Management Phase. DESIGN PLANNING. DEVELOPMENT. OPERATIONS. CLOSEOUT. FEASIBILITY.

Download Presentation

1.040/1.401 Project Management Spring 2007 Lecture 7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1.040/1.401Project ManagementSpring 2007Lecture 7 Planning Basics Dr. SangHyun Lee lsh@mit.edu Department of Civil and Environmental Engineering Massachusetts Institute of Technology

  2. Project Management Phase DESIGN PLANNING DEVELOPMENT OPERATIONS CLOSEOUT FEASIBILITY Fin.&Eval. Organization Risk Estimating Planning

  3. Outline • Planning – Hierarchical Project Structures • Work Breakdown Structure • Organization Breakdown Structure • Cost Breakdown Structure

  4. Planning Components • What: Work Breakdown Structure • How: Plans and Specifications • Who: Organization Breakdown Structure • How much: Cost Breakdown Structure (via estimate) • When: Schedule

  5. Outline • Planning – Hierarchical Project Structures • Work Breakdown Structure • Organization Breakdown Structure • Cost Breakdown Structure

  6. Work Breakdown Structure • A WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the project • Work not in the WBS is outside the scope of the project • WBS is usually an operative tool used by contractors • First step towards constructing a schedule • Central role in project monitoring and control

  7. WBS: Example different summary level Source: Shtub et al., 1994

  8. Work Package • Lowest level • Distinguish from Others • Single Responsible Organization • Assigned Start and Finish • Assigned Budget • Limited Duration

  9. Types of WBS • Project WBS • Operative tool for monitoring and control contractor work • Contractual WBS • Defines the level of reporting that the seller will provide the buyer • May include less detail than Project WBS • Agreed between owner and contractor

  10. Functional Approach GAS-STEAM COMBINED POWER PLANT level 0 level 1 level 2 level 3 level 4 level 5 MAIN FUNCTIONS OF PLANT STEAM INTERFACES GAS ITEMS COMPRESSION STATION TURBINE GENERATOR UNITS COMPRESSORS GAS TREATMENT ENCLOSURE SUB-UNITS WORK PACKAGES FOUNDATIONS COMPRESSOR 1 COMPRESSOR 2 INSTALLATION DESIGN PROCUREMENT

  11. Physical Space Approach • Project • Main building • 1st floor • Structures • Plumbings • Electrical • HVAC • 2nd floor • Service building • Structures • Plumbings • Electrical • HVAC

  12. Procedure Approach • Project • Feasibility • Design • Basic • Detail • Bid documents • Shop drawings • Bid • Construction • Foundations subcontract • Main building • Piles • Concrete foundations • Service building • Piles • Concrete foundations • Steel erection • Finishings • Commissioning

  13. WBS: CSI Master Format - Example Sample Source: Schaufelberger et al., 2002

  14. Outline • Planning – Hierarchical Project Structures • Work Breakdown Structure • Organization Breakdown Structure • Cost Breakdown Structure

  15. Organization Breakdown Structure • Decomposition of necessary resources to perform job • Identification & organization of the resources responsible with carrying out activities associated with the project • Used to keep track of specific work assignments & resource allocations

  16. Organization Breakdown Structure • Project resources • Project management team • Project manager • Construction superintendent • Field superintendent • Office manager • Scheduler • Accounter/controller • Field engineer • Construction force • Worker • Subcontractor • Electrical • Plumbing • Insulation • Tankage • Roads

  17. OBS/WBS Linkages Source: Shtub et al., 1994

  18. Outline • Planning – Hierarchical Project Structures • Work Breakdown Structure • Organization Breakdown Structure • Cost Breakdown Structure

  19. Cost Breakdown Structure (CBS) • Breakdown of the costs of the various components of the structure including all work done by the subcontractors • Serves as a basis for subsequent monthly pay requests by the contractor • Used to continuously compare costs as they actually occur with the budget

  20. Cost Breakdown Structure (CBS) Source: Shtub et al., 1994

  21. Two Main Approaches • CBS = WBS • CBS is the project cost control structure • CBS ≠ WBS • CBS is the corporate multi-project cost control structure • Usually the case of a firm that has an integrated cost control system

  22. Diverse Combinations • WBS + OBS: Task assignments • CBS + OBS: Budget monitoring of crews, etc. • OBS + Schedule: Time-specific crew assignments • CBS + Schedule: Cost monitoring

More Related