Process. Process Analysis Meeting Process Meetings: LAUNCH, STRAT, PLANNING, Weekly STATUS 2 of 14 meetings have no planned time for the entire project. But, none of meetings for the 2 nd cycle had no planned time. 75% of times, the planned time for the meetings have been exceeded.
E N D
Process • Process Analysis • Meeting Process • Meetings: LAUNCH, STRAT, PLANNING, Weekly STATUS • 2 of 14 meetings have no planned time for the entire project. • But, none of meetings for the 2nd cycle had no planned time. • 75% of times, the planned time for the meetings have been exceeded. • But, we have improved the meeting process comparing to the first cycle. • Risk Management Process • Risk Management starts from the 2nd cycle. • 4 risks • Planned to have Risk Meetings after every Status Meeting, but actually have the Risk Meetings 50 % of times
Process • PIPs • 3 PIPs from the 1st cycle