An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DESIGN AND STABLISHMENT OF THE ELECTRICAL DISTRIBUTION SYSTEM / LOAD CENTER WITH DIRECT CONNECTION TO THE NATIONAL GRID CORPORATION OF THE PHILIPPINES IN BICOL UNIVERSITY MAIN CAMPUS PROJECT 1: PRE ENGINEERING EVALUATION Engr. Fernan D. Dematera, Project 1 Leader

  2. STUDY 1: Status of Existing Electrical Equipments and Devices To determine the existing electrical equipment and devices (ex. Size of wires, type of connection, type of electrical devices) of Bicol University Main Campus 2. To find out if each building in the Main Campus comply with standards based on Philippine Electrical Code latest edition (2009

  3. STUDY 2: Analysis of Installed Transformers at the BU Main Campus    To determine the existing kVA installed capacity of transformers at the B.U. Main Campus and to determine the buildings supplied by each transformer   To determine the peak load for each building at the Main Campus To determine if BU Main can comply with all the requirements of N.G.C.P. for direct connection

  4. FINDINGS: 1. Based on the data of the peak load being measured in every building, the approximate daily KW consumption by the BU Main Campus ranges from 500 – 600. 2. Serviceentrance conductor shall not be located in wet locations such as down spout, gutters and etc., Such case involves BU College of arts and Letters were in, the service drop conductors are located near the down spout of the college building.

  5. FINDINGS: 3. Service raceway shall be equipped with a raintight service head at the point of connection to service drop conductors. Some of the building in the BU Main Campus does not comply with the code. Some are already damage and subjected for replacement: IPESR and other establishment of BUCE. 4. Service conductors must be readily accessible and must be at standard clearance and height. -service drop supplying loads into some college building does not comply with the code likewise in the case of BU admission office wherein service head are not readily accessible and excide the standard height prescribe by the code.

  6. FINDINGS: 5. The smallest service conductor shall be at 8.Omm2 at 60 ampere trip. - some establishments in BU Main Campus did not comply in the code. 6. Standard mounting height for Kilo-watt Hour meter shall be implemented. Standard mounting height must be 6ft.

  7. PROBLEMS MET: 1. The requested research equipments such as Megger, heavy duty clamp ammeter, ladder was not yet delivered/purchased. 2. Two succeeding Research Assistants hadn’t renew for the contract. 3. WEC was not considered to the Project Leader due to its part time status from June to October 2011.