Chapter 3 a. Project Management. Given the information below, what is the total additional cost to crash the project as much as possible?. c=6. f=8. a=7. d=4. Path Durations a c f = 21 a d g = 16 b e g = 20. b=6. g=5. e=9.
E N D
Chapter 3a Project Management
Given the information below, what is the total additional cost to crash the project as much as possible? c=6 f=8 a=7 d=4 Path Durations a c f = 21 a d g = 16 b e g = 20 b=6 g=5 e=9 if then cost result
d PERT Example g a b e c h f Critical path: Expected project duration T = Standard deviation of critical path σcp = Prob(X > 48)? Prob(X < 43)? Prob(43 < X < 48)? Predict a completion date that you’re 80% sure you can meet.