CR 470 Site Development Update

CR 470 Site Development Update. Agenda. Site certification Look back Certification requirements Current status, what’s ahead CR 470 Widening Corridor plan Leesburg segment Current Status, what’s ahead. Site Certification. Duke Energy Site Readiness Program

sydney
Download Presentation

CR 470 Site Development Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CR 470 Site Development Update

  2. Agenda • Site certification • Look back • Certification requirements • Current status, what’s ahead • CR 470 Widening • Corridor plan • Leesburg segment • Current Status, what’s ahead

  3. Site Certification • Duke Energy Site Readiness Program • McCallum Sweeney Consulting (MSC) • Great site – lots of strengths, few weaknesses • Pursue “Site Certification” • Growing trend in Economic Development • Lets developers know site is shovel ready • State Program or 3rd party certifier • Site Certification with MSC - $29,500

  4. Site certification (Cont) • Site certification requirements • Extensive list of requirements • 3 page summarized list • 10 page detailed list • Acceptable size, 100 acre minimum • Immediately available, properly zoned • Utilities available now or within 6 months • Approved master plan, protective covenants • Boundary survey • Preliminary land sale or lease agreement

  5. Site certification (Cont) • Site certification requirements (cont) • Environmental Due Diligence • Wetland delineation • Endangered species certification • Historical/Archaeological survey • Phase I, Environmental Site Assessment • Geotechnical/soil suitability evaluation

  6. Site certification (Cont) • Endangered Species Survey – • Documented habitat areas • Field investigations • Site certification requirement – • Clearance letters from FF&WL and USF&WL • Mitigation plan executed within 6 months • concerns • Gopher tortoise, indigo snakes, eagles, sand skink, scrub jay

  7. Florida Sand Skink

  8. Site certification (Cont) • Sand skink survey – Plan A • 2’x2’ cover boards, 40/ac, checked 2/week for 4 weeks, • estimated cost for 323 ac -$94,075 • Sand Skink survey – Plan B • Visual pedestrian survey, submit results • Cost - $7,877 • Mitigation cost- $30,000 -$60,000/ac • Place all other work on hold pending results

  9. Site certification (Cont) • Sand Skink Survey • Opted for Plan B • Visual survey completed – May • No skink sightings • Reports to FF&WL and USF&WL • Positive indications from FF&WL • No response from USF&WL

  10. Site Certification QUESTIONS?

  11. CR 470 Widening • Corridor plan • Leesburg segment • Current Status, what’s ahead

  12. Use this background between titled slides and for long text, charts or graphics.

  13. CR 470 Widening • Leesburg segment – Co line to SR 33 • Approximately 4 miles, • R/W - $6m, Construction - $21m • County project, unfunded • Bridge Widening - $8m • SR 48 widening -SR 33 to Bridge - $13m

  14. CR 470 Widening • Current Status • FDOT-Sumter Co road swap • Bridge widening $$ moved by MPO • Split Lake County segment • Move 2nd segment to construction

  15. CR 470 Widening • What’s ahead • TAC approved move to construction • Final R/W acquisitions - ~ 2 acres • Push for FDOT funding

  16. CR 470 Widening QUESTIONS?