220 likes | 407 Views
PCC/TEPPC Project Coordination and Path Rating Task Force Report to TSS. April 22, 2011. Topics. Progress to Date Progress Report: Procedure for Project Rating Review (Phases 1-3) Next Steps. 2. Progress To Date. Since January 2010:
E N D
PCC/TEPPC Project Coordination and Path Rating Task Force Report to TSS April 22, 2011
Topics Progress to Date Progress Report: Procedure for Project Rating Review (Phases 1-3) Next Steps 2
Progress To Date Since January 2010: Obtained PCC approval (March 2011) and the WECC Board approval (March 2011) of the Proposed Procedures for Project Coordination Review Phases 1-3 sub-team continued work on modifying and streamlining the Procedure for Project Rating Review – Many issues were identified. Consolidate and resolved some issues 3
Progress Report: Procedure for Project Rating Review (Phases 1-3) Expanded membership: • Kent Bolton (WECC) • David Franklin (SCE) • Tom Green (Xcel Energy) • Brian Keel (SRP) • Kyle Kohne (BPA) • Peter Mackin (USE) • Bill Pascoe (TransWest Express) • Craig Quist (PacifiCorp) • Joe Seabrook (PSE) • Chifong Thomas (BSE) 4
Progress Report: Procedure for Project Rating Review (Phases 1-3) • Since last TSS meeting in January 2010 • 6 conference calls • 27 issues were identified and consolidated into 4 categories • Developing consensus recommendations to bring back to the Task Force 5
Issue Category 1: Relationship and linkages to other processes: • Annual Progress Report (APR) process • Sub-regional Planning Groups and other joint planning groups • Operating Transfer Capability Policy Committee (OTCPC) 6
Issue Category 2: Allowable time duration and requirements to remain in a Phase • The length of time a project can remain in Phase 1 or Phase 2 without further activity beyond providing APR submittals • The qualification and requirements for a project to stay in Phase 2 or remain in the Rating Process • Clarification on what facility is being rated when a project is a subset of a Path • Question on whether a proposed project, which is a subset of an established path, can/should be rated independent of the path • Clear up the requirements for providing modeling data to WECC 7
Issue Category 3: Study Assumptions • “Fictitious devices” Vs. “planned devices” that did not materialize Vs. projects that support individual ratings w/ the same resources – Leverage work already done in TSS (RAPRS) • Restrictions on facilities that can be modeled to support a Phase 2 Path Rating • Proposed project, which “morphs” into a different project(s) during Process (and impact on projects entering the Process after this “morphed” project) • “Similarly situated” projects when there are multiple projects entering phase 2 at the same time 8
Issue Category 4: Process • Procedures to remove inactive projects from the Rating Process • Clarify “Expediting the Process” • Obligation of modeling and studying for the projects that follow a project that has gone through morphing process • If the Project Rating Review Group cannot agree and the Phase 2 Report cannot be issued, need procedure for PCC intervention before going to ADR. • In which Phase should mitigation of identified potential problems be studied and determined. • Treatment of Paths with Existing Ratings, which cannot be supported in more recent path rating studies. • Treatment of projects, which rely on projects/Paths with Ratings that cannot be supported based on studies. 9
Some Thoughts on Resolution • Develop a template with check lists on requirements to help project sponsor(s) with the Processes • Further refine the Phase 2 Process into Phase 2A and 2B: • Only sensitivity studies on concurrent (“similarly situated”) Projects in Phase 2A • Simultaneous analysis will be required on those concurrent Projects in Phase 2B. 10
Demarcation criteria between Phases 2A and 2B Based on study progress: Phase 2 can be broken down into 4 major milestones – • Study plan accepted • Base cases accepted • Sharing results with PRG • Draft Report released. Sub team believes that the demarcation should be drawn between Steps 2 and 3 11
To Remain in Phase 2A or 2B • A proposed project needs to demonstrate progress. • Time line/mile stones to demonstrate progress. 2 options: • Fixed time line/mile stone for all phases of study. if a time line/mile-stone is missed, the project sponsor can request and PRG to decide whether to grant an extension • Fixed time line for development of the study plan only. Remaining time lines/mile stones will be in the study plan agreed to by project sponsor and PRG. Any deviation will need agreement from the PRG, • Sub team to develop and recommend time line/mile-stones. • Time line/mile stones are to be approved by the PCC • The decision can be appealed to TSS or PCC. 12
Fictitious Devices • Based on TSS paper on “Resources Acceptable for Project Rating Studies” • Major changes: • Resources can be modeled, as agreed to by the SRG, as long as it is feasible for these resources to be on-line during the timeframe for which the path rating is being sought. • The resource assumptions will be clearly listed in the study report. 14
Examples of Fictitious Devices • Generators (e.g., a generator that does not exist at time of rating or not feasible to be on-line during the timeframe for which the path rating is being sought, as determined by the study review group) • Load (e.g., unrealistic load conditions, such as load projections unsupported by those used in planning resources in the same time frame, or, modeling off-peak load in one area and on-peak load in another area under similar system conditions in the same study case) • Lines (e.g., change to the impedance of a line unless such changes are part of plan of service for the new project undergoing the Facility Rating Review Process) • Phase shifters (e.g., unplanned phase shifter or operation beyond its physical capability) • Shunt elements (e.g., add a non-existent or unplanned SVC) • Series elements (e.g., add unplanned series capacitors to a line) • Opening/switching lines (e.g., open a line that is normally closed) • Remedial action schemes (e.g., institute a scheme with no agreement from the provider) 15
Test for Subset of a Path • Issue: when a project is added to an existing path • Typically, combined Path incremental capability < (proposed project + existing path) • Studies cannot create a nomogram where there is no nomogram relationship. • May lead to scheduling power at a level that is above the combined path transfer capability => adversely impact system reliability. 16
Test 1 • Start with a pre-project WECC base case. • Add the proposed project to the case. • Schedule a fixed amount of power on the proposed project. • If more than X% of the scheduled power flows on the existing path being tested, then the proposed project is deemed to be a subset of the existing path. For more information see draft test 17
Test 2 • Start with a pre-project WECC base case. • Add the proposed project to the case to create a post-project base case. • Do not schedule any flow on the new project. • If the new project picks up more than Y% of the power that was flowing on the existing path being tested, then the proposed project is deemed to be a subset of the existing path. For more information see draft test 18
New Projects with flow control devices • If flow control devices are part of a new project, they may be used to control flow on the new path to the schedule on that path • But, the flow control devices cannot be used to artificially create "loop flow" on other paths. • If the flow control devices have enough control range, the new path will be independent of all other paths. 19
Application • Test will be part of the Comprehensive Progress Report. should be done early in Phase 1 of the Project Rating Process => no surprises in Phase 2. • If the proposed project is part of an existing path => proposed project must re-rate the existing path as part of rating review studies • Project rating = incremental path rating with and without the proposed project • If the sponsor of a project that is part of an existing path elects to rate the proposed project as part of an existing path, then this test is not required. 20
Next Steps • Bring recommendation to the Task Force for consideration • Incorporation into the Project Rating Review Process • Expectation: post the proposed modification by May 2011 for comments and guidance by PCC and stakeholders 21
Questions? ? 22