WECC-098 Gov Droop DT. May 29, 2013. BAL-003-1 Requirements.
E N D
WECC-098Gov Droop DT May 29, 2013
BAL-003-1 Requirements R1. Each Frequency Response Sharing Group (FRSG) or Balancing Authority that is not a member of a FRSG shall achieve an annual Frequency Response Measure (FRM) (as calculated and reported in accordance with Attachment A) that is equal to or more negative than its Frequency Response Obligation to ensure that sufficient Frequency Response is provided by each FRSG or BA that is not a member of a FRSG to maintain Interconnection Frequency Response equal to or more negative than the Interconnection Frequency Response Obligation. 2
The Interconnection Frequency Response Obligation (IFRO) is based on the resource contingency criteria (RCC), which is the largest category C (N-2) event identified except for the Eastern Interconnection, which uses the largest event in the last 10 years. In the West, the RCC is 2,740 MW or a double Palo Verde outage. IFRO for the WI is 840 MW Interconnection Frequency Response Obligation
FROBA = IFRO x (Annual Gen BA + Annual Load BA) (Annual Gen INT + Annual Load INT) Where does the data come from? For the BA FERC Form 714 For the Interconnection – Sum of all the BAs. Balancing Authority Frequency Response Obligation (FRO)
FROGO = FROBA x Annual Gen GO Annual Gen BA or FROGO = FROBA x MW Gen GO Total MW Gen BA Generator Owner Frequency Response Obligation (FROGO) Proposal