280 likes | 290 Views
Get the latest updates and progress of the Polavaram Irrigation Project, the lifeline of Andhra Pradesh. Learn about the construction program, excavation status, concrete progress, and more.
E N D
Polavaram Irrigation Project Lifeline of Andhra Pradesh #83 Virtual Review by Hon’ble CM dt: 26th Nov. 2018 Water Resources Department Progress During 19th Nov – 25th Nov ,2018
PROJECT PROGRESS STATUS • Main Dam Components:- • EXCAVATION for Spillway, Spill Channel, Approach Channel, Pilot Channel & Left Flank : 909.34 lakh cum completed out of total 1115.59 lakh Cum (81.51%). • CONCRETING for Spillway, Stilling Basin & Spill Channel : 18.54 lakh cum (including 1.65 L Cum of crevices filling) completed out of 36.79 lakh Cum (50.40%) • RADIAL GATES fabrication : 11,156 MT completed out of 18000 MT (61.98%). • DIAPHRAGM WALL concreting : 1396.6 m completed out of 1396.6 m (100%). • JET GROUTING CUTOFF’S for Coffer Dams : 3462 m ( as per site condition) completed out of 3467 m ( 100%) • U/S COFFER DAM: 0.54 L cum completed out of 77.81 L cum (0.69%). • CONNECTIVITIES : 59.50% of work completed. • Left Connectivities : 47.91% Completed • Right Connectivities : 72.54 % Completed • RIGHT MAIN CANAL : Excavation completed for total length of 177.9 Km (100%), Lining completed for 157.563 KM out of 176.20 Km (90.0%). Structures 199 completed out of 255 Nos. • LEFT MAIN CANAL : Excavation completed for 179.948 Km out of 210.927 Km (85.31%), Lining completed for 124.593 KM out of 210.927 Km (59%). Structures 146 Completed out of 452 Nos. Water Resources Dept., Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 2
CONSTRUCTION PROGRAMME 0F PIP MAIN DAM WORKS • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 3
WEEKLY PROGRESS - SUMMARY (19th Nov- 25th Nov’18) • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 4
Excavation Status Target Date Jan’ 2019 Total Qty 124 L Cum Balance Qty 16.49 L Cum Target Date Dec’ 2018 Total Qty 50 L Cum Balance Qty 30.51 L Cum Left flank Godavari River U/S Coffer dam Godavari River D/S Coffer dam ECRF dam Target Date Jun’ 2018 Total Qty 163 L Cum Balance Qty 70 L Cum River diversion Target Date Dec’ 2018 Total Qty 163 L Cum Balance Qty 31.47 L Cum Target Date Mar,2019 Total Qty 131 L Cum Balance Qty 101.48 L Cum Approach Channel Qtty for CC Blocks &Embkt: 38.59 L cum Pilot Channel 902 Hill Total Qty 161 L Cum Balance Qty Nil Target Date Dec’ 2018 Total Qty 486.59 L Cum Balance Qty 26.30 L Cum Spillway Spill Channel PERCENTAGE COMPLETION Water Resources Dept., Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 5
EXCAVATION - WEEKLY Progress (19th Nov- 25th Nov’18) • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 6
EARTH WORK PROGRAMME/PROGRESS In L.cum PILOT CHANNEL SPILL CHANNEL APPROACH CHANNEL LEFT FLANK • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 7
REVISED PROGRAMME FOR EXCAVATION Reviseddt. 14th Oct 2018 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 8
CONCRETE - WEEKLY PROGRESS (19th Nov- 25th Nov’18) • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 9
Physical Status of Spill Way ,Stilling Basin & Spill Channel Concrete 1 Km • Polavaram Irrigation Project - Lifeline of Andhra Pradesh • Water Resources Dept., • Govt. of Andhra Pradesh 10
CONCRETE- WEEEKLY PROGRESS ANALYSIS • Water Resources Dept., • Govt. of Andhra Pradesh 11 • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
Proposed by NEC on 18.11.2018 REVISED SPILLWAYCONCRETEPROGRAMME/PROGRESS Spillway Total = 16.39 L cum Executed = 12.17 L cum Balance = 4.22 L cum REVISED SPILL CHANNELCONCRETEPROGRAMME/PROGRESS Spill Channel Total = 18.75 L cum Executed = 4.72 L cum Balance = 14.03 L cum • Water Resources Dept., • Govt. of Andhra Pradesh 12 • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
COFFER DAMS -WEEKLY PROGRESS(19th Nov- 25th Nov’18) • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 13
Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 14
RADIALGATES–SPECIFICATIONS • Water Resources Dept., • Govt. of Andhra Pradesh Polavaram Irrigation Project - Lifeline of Andhra Pradesh 15
RADIAL GATES - WEEKLY Progress (19th Nov- 25th Nov’18) Elevation: +25.185 M • Water Resources Dept., • Govt. of Andhra Pradesh 16 • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
Weekly Progress - Hydraulic Hoist Elevation: +26.00 M Weekly Progress – Prestressed Anchorage System Elevation: +25.316 M Weekly Progress - River Sluice Gates Elevation: +17.30 M • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 17
STATUS OF DESIGNS - ABSTRACT • Water Resources Dept., • Govt. of Andhra Pradesh 18 • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
SCHEDULE FOR PENDING DESIGNS 19 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
CONNECTIVITIES-WEEKLY PROGRESS (19th Nov- 25th Nov’18) 20 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
LEFT & RIGHT MAIN CANALS -WEEKLY PROGRESS (19th Nov- 25th Nov’18) 21 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
Reviseddt. 21 Oct 2018 For EL + 45.72 m (FRL) LA and R&R Status (Works, Submergence, Land to Land and R&R Colonies) • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 22
For EL + 41.15 m Reviseddt. 21 Oct 2018 LA and R&R Status (L.A, Submergence, Land to Land and Housing) • Water Resources Dept., • Govt. of Andhra Pradesh 23 • Polavaram Irrigation Project - Lifeline of Andhra Pradesh
Quality Control tests Conducted during 19th Nov- 25th Nov’18 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 24
Quality Control tests Conducted during 19th Nov- 25th Nov’18 • Water Resources Dept., • Govt. of Andhra Pradesh • Polavaram Irrigation Project - Lifeline of Andhra Pradesh 25
Expenditure & Reimbursement Revised estimate – Comparative Statement: Rs. in Crores Availability of irrigation Component • Water Resources Dept., • Govt. of Andhra Pradesh Polavaram Irrigation Project - Lifeline of Andhra Pradesh
Information, Education & Communication Awareness Programme for Farmers and Students on visit to Polavaram Irrigation Project * Total No. of days : 217 days • Water Resources Dept., • Govt. of Andhra Pradesh Polavaram Irrigation Project - Lifeline of Andhra Pradesh
THANK YOU 28