City of San Mateo. Flood Control Efforts & Needs. Preliminary FIRM (2008). Completed Capital Projects ($22.7M). SM Creek South Levee Wall ($1.2M) Completed 2001 Raising of Norfolk Bridge ($1.9M) Completed 2002 Caltrans Culvert – US101/3 rd Ave ($10M) Completed 2004
E N D
City of San Mateo Flood Control Efforts & Needs
Completed Capital Projects ($22.7M) • SM Creek South Levee Wall • ($1.2M)Completed 2001 • Raising of Norfolk Bridge • ($1.9M)Completed 2002 • Caltrans Culvert – US101/3rd Ave • ($10M) Completed 2004 • SM Creek North Levee Wall • ($730k) Completed 2005 • O’Neill Slough Tide Gate & Levee • ($1.5M) Completed 2007 • South Bayfront Levee Project • ($7.4M) Completed 2011 South Levee Project Creek Floodwall and Railing Seal Slough hydro-seeding/erosion control
Remaining Capital Projects ($22.35M) Rehabilitate Pump Stations at Raise North Levee at Coyote Point Beach ($7.35M) Poplar Avenue ($7.5M) Coyote Point ($7.5M)