Visalia WCP Trickling Filter Upgrade Project 1994/1995. Trickling Filters, Pump Station and Flow Control Box Modifications. VISALIA TF UPGRADE. Project Manager - David Stringfield P.E. Design Engineer - Steve Beck P.E. Resident Engineer/Construction Manager - David Watson. Project Phases.
E N D
Visalia WCP Trickling Filter Upgrade Project 1994/1995 Trickling Filters, Pump Station and Flow Control Box Modifications
VISALIA TF UPGRADE Project Manager - David Stringfield P.E. Design Engineer - Steve Beck P.E. Resident Engineer/Construction Manager - David Watson
Project Phases • New Effluent Distribution System • Junction Box A Rehabilitation • 54” Primary Effluent Pipeline Replacement • Flow Metering Manhole Construction • Butterfly Valve Control Box Retrofit • Trickling Filter Pump Station Retrofit • Overhaul of 2 180’ Diameter Trickling Filters Mechanism and Structure
Junction Box A Rehabilitation • Box Rehabilitation. • Slide Gate Replacement • Wall Spool Renovation
Effluent Pipeline • Replace Effluent Pipeline • Construct New Manhole Meter Station • Install New Butterfly Valve • Construct New Wall Spool in TFPS
Trickling Filter Pump Station • Structural Rehabilitation • Install New Piping • Install New Pumps and VFD Units • Install New Stairway and Grating • Install New St Stl Slide Gates
Trickling Filter Rehabilitation • Demo Old Distributor Structures • Cut Filter Walls • Add Rebar Layers • Construct New Concrete Walls • Install New Channel Piers and Slabs • Install New Underdrain Block • Install New Plastic Media • Install New Distributors and VFD Units
Additional Construction Items • Pave Plant Site • Install New Light Fixtures • Install New Irrigation System • Install New Electrical Components