490 likes | 1.65k Views
PERT/CPM Models for Project Management. Project Management. Characteristics of Projects Unique, one-time operations Involve a large number of activities that must be planned and coordinated Long time-horizon Goals of meeting completion deadlines and budgets Examples Building a house
E N D
PERT/CPM Models for Project Management © The McGraw-Hill Companies, Inc., 2003
Project Management • Characteristics of Projects • Unique, one-time operations • Involve a large number of activities that must be planned and coordinated • Long time-horizon • Goals of meeting completion deadlines and budgets • Examples • Building a house • Planning a meeting • Introducing a new product • PERT—Project Evaluation and Review TechniqueCPM—Critical Path Method • A graphical or network approach for planning and coordinating large-scale projects. © The McGraw-Hill Companies, Inc., 2003
Example: Building a House © The McGraw-Hill Companies, Inc., 2003
Gantt Chart © The McGraw-Hill Companies, Inc., 2003
PERT and CPM • Procedure • Determine the sequence of activities. • Construct the network or precedence diagram. • Starting from the left, compute the Early Start (ES) and Early Finish (EF) time for each activity. • Starting from the right, compute the Late Finish (LF) and Late Start (LS) time for each activity. • Find the slack for each activity. • Identify the Critical Path. © The McGraw-Hill Companies, Inc., 2003
Notation t Duration of an activity ES The earliest time an activity can start EF The earliest time an activity can finish (EF = ES + t) LS The latest time an activity can start and not delay the project LF The latest time an activity can finish and not delay the project Slack The extra time that could be made available to an activity without delaying the project (Slack = LS – ES) Critical Path The sequence(s) of activities with no slack © The McGraw-Hill Companies, Inc., 2003
PERT/CPM Project Network © The McGraw-Hill Companies, Inc., 2003
Calculation of ES, EF, LF, LS, and Slack GOING FORWARD • ES = Maximum of EF’s for all predecessors • EF = ES + t GOING BACKWARD • LF = Minimum of LS for all successors • LS = LF – t • Slack = LS – ES = LF – EF © The McGraw-Hill Companies, Inc., 2003
Building a House: ES, EF, LS, LF, Slack © The McGraw-Hill Companies, Inc., 2003
PERT/CPM Project Network © The McGraw-Hill Companies, Inc., 2003
Example #2: ES, EF, LS, LF, Slack © The McGraw-Hill Companies, Inc., 2003
Reliable Construction Company Project • The Reliable Construction Company has just made the winning bid of $5.4 million to construct a new plant for a major manufacturer. • The contract includes the following provisions: • A penalty of $300,000 if Reliable has not completed construction within 47 weeks. • A bonus of $150,000 if Reliable has completed the plant within 40 weeks. Questions: • How can the project be displayed graphically to better visualize the activities? • What is the total time required to complete the project if no delays occur? • When do the individual activities need to start and finish? • What are the critical bottleneck activities? • For other activities, how much delay can be tolerated? • What is the probability the project can be completed in 47 weeks? • What is the least expensive way to complete the project within 40 weeks? • How should ongoing costs be monitored to try to keep the project within budget? © The McGraw-Hill Companies, Inc., 2003
Activity List for Reliable Construction © The McGraw-Hill Companies, Inc., 2003
Reliable Construction Project Network © The McGraw-Hill Companies, Inc., 2003
The Critical Path • A path through a network is one of the routes following the arrows (arcs) from the start node to the finish node. • The length of a path is the sum of the (estimated) durations of the activities on the path. • The (estimated) project duration equals the length of the longest path through the project network. • This longest path is called the critical path. (If more than one path tie for the longest, they all are critical paths.) © The McGraw-Hill Companies, Inc., 2003
The Paths for Reliable’s Project Network © The McGraw-Hill Companies, Inc., 2003
ES and EF Values for Reliable Constructionfor Activities that have only a Single Predecessor © The McGraw-Hill Companies, Inc., 2003
ES and EF Times for Reliable Construction © The McGraw-Hill Companies, Inc., 2003
LS and LF Times for Reliable’s Project © The McGraw-Hill Companies, Inc., 2003
The Complete Project Network © The McGraw-Hill Companies, Inc., 2003
Slack for Reliable’s Activities © The McGraw-Hill Companies, Inc., 2003
Spreadsheet to Calculate ES, EF, LS, LF, Slack © The McGraw-Hill Companies, Inc., 2003
PERT with Uncertain Activity Durations • If the activity times are not known with certainty, PERT/CPM can be used to calculate the probability that the project will complete by time t. • For each activity, make three time estimates: • Optimistic time: o • Pessimistic time: p • Most-likely time: m © The McGraw-Hill Companies, Inc., 2003
Beta Distribution Assumption: The variability of the time estimates follows the beta distribution. © The McGraw-Hill Companies, Inc., 2003
PERT with Uncertain Activity Durations Goal: Calculate the probability that the project is completed by time t. Procedure: • Calculate the expected duration and variance for each activity. • Calculate the expected length of each path. Determine which path is the mean critical path. • Calculate the standard deviation of the mean critical path. • Find the probability that the mean critical path completes by time t. © The McGraw-Hill Companies, Inc., 2003
Expected Duration and Variance for Activities (Step #1) • The expected duration of each activity can be approximated as follows: • The variance of the duration for each activity can be approximated as follows: © The McGraw-Hill Companies, Inc., 2003
Expected Length of Each Path (Step #2) • The expected length of each path is equal to the sum of the expected durations of all the activities on each path. • The mean critical path is the path with the longest expected length. © The McGraw-Hill Companies, Inc., 2003
Standard Deviation of Mean Critical Path (Step #3) • The variance of the length of the path is the sum of the variances of all the activities on the path. s2path = ∑ all activities on path s2 • The standard deviation of the length of the path is the square root of the variance. © The McGraw-Hill Companies, Inc., 2003
Probability Mean-Critical Path Completes by t (Step #4) • What is the probability that the mean critical path (with expected length tpath and standard deviation spath) has duration ≤ t? • Use Normal Tables (Appendix A) © The McGraw-Hill Companies, Inc., 2003
Example Question: What is the probability that the project will be finished by day 12? © The McGraw-Hill Companies, Inc., 2003
Expected Duration and Variance of Activities (Step #1) © The McGraw-Hill Companies, Inc., 2003
Expected Length of Each Path (Step #2) The mean-critical path is a - b - d. © The McGraw-Hill Companies, Inc., 2003
Standard Deviation of Mean-Critical Path (Step #3) • The variance of the length of the path is the sum of the variances of all the activities on the path. s2path = ∑ all activities on path s2 = 1/9 + 1/4 + 1/4 = 0.61 • The standard deviation of the length of the path is the square root of the variance. © The McGraw-Hill Companies, Inc., 2003
Probability Mean-Critical Path Completes by t=12 (Step #4) • The probability that the mean critical path (with expected length 11 and standard deviation 0.71) has duration ≤ 12? • Then, from Normal Table: Prob(Project ≤ 12) = Prob(z ≤ 1.41) = 0.92 © The McGraw-Hill Companies, Inc., 2003
Reliable Construction Project Network © The McGraw-Hill Companies, Inc., 2003
Reliable Problem: Time Estimates for Reliable’s Project © The McGraw-Hill Companies, Inc., 2003
Pessimistic Path Lengths for Reliable’s Project © The McGraw-Hill Companies, Inc., 2003
Three Simplifying Approximations of PERT/CPM • The mean critical path will turn out to be the longest path through the project network. • The durations of the activities on the mean critical path are statistically independent. Thus, the three estimates of the duration of an activity would never change after learning the durations of some of the other activities. • The form of the probability distribution of project duration is the normal distribution. By using simplifying approximations 1 and 2, there is some statistical theory (one version of the central limit theorem) that justifies this as being a reasonable approximation if the number of activities on the mean critical path is not too small. © The McGraw-Hill Companies, Inc., 2003
Calculation of Project Mean and Variance © The McGraw-Hill Companies, Inc., 2003
Spreadsheet for PERT Three-Estimate Approach © The McGraw-Hill Companies, Inc., 2003