1 / 12

Long Term Science working group status L SWT Venice , 30/03 -01/ 04 /200 9

Long Term Science working group status L SWT Venice , 30/03 -01/ 04 /200 9. OBJECTIVES.

tao
Download Presentation

Long Term Science working group status L SWT Venice , 30/03 -01/ 04 /200 9

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Long Term Science working group status LSWT Venice, 30/03-01/04/2009

  2. OBJECTIVES • The objective of this working group (2 workshops held on 10-11/02 and 04/03) is to set up the lander functioning when the primary battery is fully discharged, that is when available energy is minimal • For that we have to: • Study the external conditions on the comet between 3 and 2 AU • Check the individual sub-system constraints in these conditions of T° and power (CDMS, PSS and secondary battery, TCS and absorbers, TxRx, …) • Set up Philae and CDMS modes to cope with all kind of conditions • Check if all test means are available to test this phase • Make that all is feasible before end of 2009

  3. R  COMET ENVIRONMENT IMPLICATIONS • Comet at 3 AU means a limited power received by 2 ways inside the thermal controlled compartment: • Solar panels redistributed in thermal and electrical energy • Absorbers redistributed in thermal energy only • The different conditions of illumination are depending on 2 parameters only (co-obliquity q, latitude f), from which 28 cases are simulated and 14 cases can be extracted (choosing the right hemisphere)

  4. COMET ENVIRONMENT IMPLICATIONS • Thermal environment gives constraints to: • the lander total dissipation • the external wall temperatures : T° cells and cell efficiency • Cold temperatures are favourable (first calculations made by CNES with the SABER tool show from +25°C to -100°C the cell efficiency is increased of about 25%) • Radiation dose effects are not favourable (first PoliMi results) • Other effects as dust or ice covering, shadows • AI on CNES for gas refreezing • AI on PoliMi for cell tests • Total dissipation and particularly by the absorbers during nights has to be precisely determined • AI on DLR

  5. COMET ENVIRONMENT IMPLICATIONS • First thermal map at 3 AU (LAM/ O. Groussin) -40°C sub-solar point, -140°C night side

  6. Y W1 W2 W3 X X W4 W5 200 ° 330 ° Sun illumination COMET ENVIRONMENT IMPLICATIONS • Optimisation of Philae orientation: • Confirmation of best attitude: to turn Wall3 (W3) to Sun highest elevation (generally South direction in northern hemisphere, North in southern) • When to do this pointing ?

  7. COMET ENVIRONMENT IMPLICATIONS • Optimisation of Philae landing site (values after orientation) 3 AU

  8. SUB-SYSTEMS CONSTRAINTS • Primary and secondary working ranges • SB maximum charge (around 95%) and maximum discharge (double protection) • SB best working temperatures in charge / discharge (AI on CNES) • Charge level measurement (CDMS measures worst case) • Solar arrays performances (AI on PoliMi) • At cell level, T° tests • At array level, shadowing and radiation effect • Shunts and MPPTs performances (AI on MPS) • Consolidation of power required by each sub-system (LUM values verified by each responsible)

  9. CDMS – PHILAE BASIC MODESPROPOSAL • Philae Wake-Up mode: this mode is required when Philae shutdown is mandatory During nights, shutdown. During day, when SA are illuminated enough, this mode is automatically switched on and compartment heating starts • CDMS Super-Low power mode: DPUs are alternately ON and OFF with regularly the 2 DPUs OFF, TCS heating and SB charging possible with power in excess, Minimal power: 2,4 W • CDMS Low power mode: DPUs are alternately ON and OFF, TCS heating and SB charging possible with power in excess, Minimal power: 3,6 W • CDMS Nominal mode: 2 DPUs ON, TCS heating and SB charging possible with power in excess, Minimal power: 4,8 W

  10. CDMS – PHILAE BASIC MODES PROPOSAL • Philae quiet mode: CDMS in nominal mode + 1 Rx ON every 30 mn for 2 mn, TCS heating and SB charging possible with power in excess Power: 7,3 W (peak value) • Philae nominal mode: CDMS in nominal mode + TxRx working during visibilities, TCS heating and SB charging possible with power in excess Power: 10,8 W (for visibility periods) -> SC TM retrieval only possible in this mode -> if the landing site is correctly chosen, if landing is nominal (operational LG / orientation possible, nominal attitude, no shadowing), possibility to achieve PQM at 3 AU (TBC)

  11. OPEN POINTS ON PHILAE WORKINGDURING LTS • 23 open actions • Decisions to be taken at the next workshop on 27/04 • Confirmation of CDMS and Philae working modes (rationale: to remain as simple as possible) • Check if all contingency cases have been taken into account • Check what has to be monitored / commanded by Ground Segment according to modes (list of HK and TC parameters, strategy of MM EEPROM use, strategy of TxRx use) • Assess the possibility to do science in CDMS modes below the nominal modes (on solar panels immediate power, on SB during comet nights) • Determine the nominal operational loop when Philae nominal power mode is achieved for day and night (science every day)

  12. LTS SPECIFIC TESTS • The current Solar Array Simulator is not usable at GRM because of too small currents • Specification of a new SAS on-going between PoliMi and LCC • Delivery of new SAS planned in autumn • In parallel to SDL tests, LTS tests will be done after CDMS V8.0 delivery end of September and before delivery to ESA in January 2010 • only 3 months • Priority to SDL phase testing in case too much work

More Related