Market Operations Standing Committee Change Management – Market Rule Amendment Update John MacKenzie, Supervisor Market Rules 19 Oct 2005
Purpose of Update • Update stakeholders on status of market rules approved, coming into force, under development • Identify any current requests for specific stakeholder review and comment • Solicit feedback on general market rule development issues e.g. process
New in Baseline 14.0 • MR-00261: Metering and Technical Requirements for Small Embedded Facilities • MR-00263: Correct Non-Material Discrepancies Dispatch Scheduling Algorithm Description • MR-00288: Reactive Power Capability Requirements for Induction Generators • MR-00290: Align Market Rules with OEB-IESO Protocol on Market Surveillance Panel • MR-00296: Emergency Control Actions and Counter-Intuitive Pricing – Inputs to DSO* • MR-00298: Emergency Control Actions and Counter-Intuitive Pricing – Admin Pricing** * in effect 12 Aug 05 ** in effect 12 Aug 05, sunset 1 Oct 05
Approved by IESO Board 23 Sep 05 • In effect 19 Oct 05 • MR-00295: Clarify Local Market Power Mitigation • In effect 7 Dec 05 (Baseline 14.1) • MR-00289: 14-Day Advance Outage Approval and Generator Testing • MR-00291: Adjustment Period Allocation • MR-00292: Additional Compensation for Dispatchable Loads under Admin Pricing
Under Development • High Priority • MR-00121: Treatment of Facilities with More than One Connection Point (part of Dispatch Issues; plan published 14 Oct 05) • MR-00297: IESO Processing of MP De-Rate Submissions (historical analysis to TP 25 Oct 05)
Under Development – 2 • Medium Priority • MR-00042: Dispatch Data Req’ts for Self-Scheduling and Intermittent Generators (recommended by TP; to IESO Board 18 Nov 05) • MR-00247: Operation and Compensation for Special Protection Systems (posted for review/comment; deadline 27 Oct 05) • MR-00294: Transmission Station Service Supplied through Distribution System (to be withdrawn?) • MR-00299: Regional Reserve Sharing (posted for review/comment; deadline 20 Oct 05) • Low Priority • MR-00293: Transmission Equipment Thermal Limits (amendment proposal under development)
Under Development – 3 • Pending • MR-00283: Revenue Metering for Load Facility Connection Station Service (to be withdrawn?) • MR-00284: Include Reliability Impact as Factor in Determining Non-Compliance Sanction (amendment submission under development)
On Hold • MR-00287: Resource Adequacy Market • MR-00264-MR-00276; MR-00286: Market Rules Related to Day-Ahead Market • MR-00212: Prudential Security for LDCs
Emerging Issues • Day-Ahead Commitment Processes • Renewable Energy Supply Contracted Generation • Contracted Ancillary Services Settlement Information • IESO Authorities for High-Risk and Emergency Operating States • Intertie Transaction Failure Penalties
Feedback: Comments, Questions… • Any questions or comments on this update or the rule amendment process in general?